Water Supply · Definition

How Current Must a Flow Test Be, and Who Can Perform One?

Reviewed by a licensed Professional Engineer · NY, NJ, PA, MD, DE · Last reviewed · Code basis: NFPA 13 (2022) 4.5.1.1; NFPA 13 (2019) Ch 4; NFPA 13 (2025) Ch 4; NFPA 13 (2016) Ch 23 via NYC 2022 Building Code Appendix Q; NFPA 291 (2022) Ch 4; NFPA 25 (2023) Ch 13

General guidance, not a code determination for any project. Confirm the adopted code and local amendments with the authority having jurisdiction.

A current flow test, for sprinkler design purposes, is a water supply test run no more than 12 months before the working plans are submitted, unless the authority having jurisdiction (AHJ) approves an older one. The rule sits in Section 4.5.1.1 of the 2022 edition of NFPA 13, the National Fire Protection Association standard for sprinkler installation. The test itself is run by the water purveyor, or by a contractor the purveyor permits on its mains, and the reviewing AHJ decides whether the result is recent enough to design on.

The 12-month limit is short on purpose. Water mains age, pressure zones get re-valved, pumps are reset and demand grows, so a reading taken 3 years ago can overstate what the main will deliver on the day the sprinklers open. This article defines what “current” means, what a usable test record contains, which NFPA 13 edition carries the rule in each state DGA works in, who is allowed to run the test, and how a flow test differs from the letters and tests it is often confused with.

At a Glance: Flow Test Currency

  • Definition: a hydrant flow test is current when it was run within 12 months before the sprinkler working plans are submitted for review, or when the AHJ has approved an older test.
  • Governing code and section: NFPA 13 (2022) Section 4.5.1.1, as referenced by the 2024 International Building Code (IBC) in New York State and New Jersey. Pennsylvania and Maryland county permits use NFPA 13 (2019) Chapter 4; Delaware uses NFPA 13 (2025) Chapter 4; New York City uses NFPA 13 (2016) Chapter 23, as modified by Appendix Q of the 2022 Building Code.
  • Who performs it or who it applies to: the water purveyor runs or permits the test on public mains; the owner’s contractor runs it on private mains; the sprinkler designer relies on it; the AHJ accepts or rejects it.
  • When it’s required: before working plans are submitted, again if the project stalls past 12 months, and whenever the purveyor changes the system that feeds the site.
  • Typical output: a one-page test record with date, hydrant locations, static and residual pressures, pitot reading and flow, and the name of the party that ran the test.
  • Often confused with: a purveyor availability or will-serve letter, a fire pump acceptance flow test, and the NFPA 25 main drain test. None of the three measures the main’s capacity at the connection.

What the 12-Month Rule Says

NFPA 13 (2022) Section 4.5.1.1 requires that the water supply flow test used for the hydraulic design be conducted no more than 12 months before the working plans are submitted, unless the AHJ approves otherwise. The clock runs from the test date to the submittal date, not to the permit date or the installation date. A test that is 11 months old at submittal and 18 months old at acceptance is still a current test under the rule.

“Working plans” are the sealed sprinkler shop drawings and hydraulic calculations that the installing contractor or engineer submits for approval; NFPA 13 (2022) Chapter 28 lists what they carry, including the water supply information. DGA’s article on what sprinkler shop drawings contain describes that set. A preliminary design or a feasibility study can be built on older data, but the plan examiner reads the 12 months from the working plan submittal.

The exception is the AHJ-approval clause. A reviewer can accept an older test when the purveyor confirms that nothing in the system has changed, or when a newer test is not practical, for example a winter submittal in a district that does not flow hydrants below freezing. That acceptance is the AHJ’s decision, not the designer’s, and it should be in writing before the calculations are run on the older numbers.

What a Current Flow Test Record Includes

Age is only one of the things a reviewer checks. A test that is 2 months old but missing the hydrant elevations, the main size or the name of the party that ran it is a current test that cannot be used. The record should carry the items in the table; NFPA 291 (2022) Chapter 4 describes the procedure and what is recorded, and the hydraulic calculations in the working plans repeat the key numbers.

ItemWhat the record showsWhy the reviewer needs it
Date and time of dayCalendar date and clock time of the readingsStarts the 12-month clock and shows whether the test caught peak demand (morning in a residential zone, midday in an industrial one)
Static pressurePressure at the residual hydrant with no hydrants flowing, in psiThe top of the supply curve
Residual pressurePressure at the same hydrant while the flow hydrant is open, in psiThe second point that fixes the slope of the supply curve
Pitot reading and flowPitot pressure at each flowing outlet, outlet size, coefficient and the flow in gpmThe flow that produced the residual drop
Hydrant locations and elevationsStreet addresses or hydrant numbers, a sketch, and the elevation of each hydrant relative to the siteLets the designer correct pressures to the point of connection
Main size and pressure zoneDiameter of the main the hydrants sit on and the purveyor’s zone or gradient nameConfirms the test represents the main that will feed the building
Who ran it and who witnessed itPurveyor crew, permitted contractor or engineer, plus any fire department or AHJ witnessThe AHJ accepts tests from parties it recognizes
Season and system conditionNotes on pumps running, valves closed, tanks being filled or mains flushed nearbyExplains an unusually high or low reading and supports a request to accept an older test

The elevation reference and the pressure zone carry the most weight in design. Without them the designer cannot show that the pressure at the hydrant is the pressure available at the building’s point of connection.

Figure 1: From Request to Submittal: Where the 12 Months Run

1. RequestThe owner, engineer or contractor files the purveyor’s flow test request: site address, point of connection, the hydrants to use and a contact who can give site access.
2. TestThe purveyor crew or a permitted contractor runs the test to NFPA 291 (2022) Chapter 4 and records static, residual, pitot and flow. The 12-month clock starts on this date.
3. ReportThe purveyor issues the written record, usually within a few weeks; Delaware’s State Fire Marshal wants it on the supplier’s letterhead.
4. DesignThe engineer or contractor builds the hydraulic calculations on the test and prepares the working plans.
5. SubmittalWorking plans go to the AHJ. If this date is more than 12 months after step 2, the designer needs a new test or the AHJ’s written acceptance of the old one.
NFPA 13 (2022) Section 4.5.1.1 measures the 12 months from the test date in step 2 to the working plan submittal in step 5. Purveyor turnaround on steps 1 to 3 runs from about 2 weeks to 8 weeks as of November 2026, so a project that orders the test early and submits late can use up most of the window before design starts.

Where the Code Sets the Rule in Each State

The 12-month rule comes from NFPA 13, and the edition depends on which building code the state adopts, because the building code’s referenced standards chapter names the NFPA 13 year. The reviewer who accepts the test is the same authority that reviews the sprinkler working plans. In Maryland, the county building permit reviews sprinklers to NFPA 13 (2019) through the 2021 IBC, while the State Fire Prevention Code (NFPA 1, 2024) references NFPA 13 (2022).

JurisdictionNFPA 13 edition and where the age rule sitsWho accepts the test (AHJ)Filing the test travels with
New York State (outside NYC)NFPA 13 (2022) Section 4.5.1.1, referenced by the 2024 IBC under the 2025 Uniform CodeLocal code enforcement officialBuilding permit; sprinkler working plans and hydraulic calculations
New York CityNFPA 13 (2016) as modified by Appendix Q of the 2022 Building Code; the 12-month rule sits in Chapter 23 of the 2016 editionDepartment of Buildings (DOB) plan examiner; Fire Department of New York (FDNY) on fire protection items it reviewsDOB NOW sprinkler work type filing with the hydraulic calculations
New JerseyNFPA 13 (2022) Section 4.5.1.1, referenced by the 2024 IBC under the Uniform Construction Code (UCC), effective August 17, 2026Municipal fire protection subcode officialUCC construction permit, fire protection subcode technical section
PennsylvaniaNFPA 13 (2019) Chapter 4, referenced by the 2021 IBC under the UCC (January 1, 2026)Municipal or third-party code official; Philadelphia Department of Licenses and Inspections (L&I) in the cityUCC building permit; Philadelphia fire suppression permit
MarylandNFPA 13 (2019) Chapter 4 through the 2021 IBC at the county permit; NFPA 1 (2024) references NFPA 13 (2022)County fire marshal or fire and life safety plan reviewer; State Fire Marshal where it has jurisdictionCounty building permit, fire protection plan review
DelawareNFPA 13 (2025) Chapter 4 under Regulation 701 (2026)Office of the State Fire Marshal (Wilmington Fire Marshal inside the city)State Fire Marshal plan review; the Preliminary Sprinkler Form asks for a flow test within the past 12 months on the water supplier’s letterhead

Editions as adopted as of November 2026. Local amendments and purveyor rules are not shown.

Opens the Project Desk with your sentence. Our licensed PEs review every brief and reply within one business day.

Who Can Perform a Flow Test

On a public main, the purveyor owns the hydrants and the valves, so the purveyor decides who opens them. Most purveyors in the region run the test with their own crew on request; some issue a permit that lets a licensed sprinkler contractor run it, often with a purveyor inspector watching. On a private main, the owner’s contractor runs the test, and in New York City that is typically a licensed master fire suppression piping contractor. The AHJ then decides whether the party that ran the test, and the date it ran, meet the standard.

Figure 2: Who Runs the Test and Who Accepts It, by State

StatePublic main: who runs the testHow it is requestedWho decides an older test is acceptable
New York CityDepartment of Environmental Protection (DEP) runs hydrant flow tests on the city distribution systemRequest for Hydrant Flow Test filed online through DEP’s Permit and Review Information System (PARIS)DOB plan examiner
New York StateThe purveyor (municipal water department, water authority or private utility) runs or permits the testThe purveyor’s request form or letterLocal code enforcement official
New JerseyThe purveyor (New Jersey American Water, municipal utilities and municipal utilities authorities) runs or permits the test; Passaic Valley Water Commission, for example, takes a Hydrant Flow Test Application and lets the requester attendThe purveyor’s application; results are sent to the requesterFire protection subcode official
PennsylvaniaPhiladelphia Water Department runs tests on request; Aqua, Pennsylvania American Water and municipal authorities run or permit tests on their mainsPhiladelphia: a letter of request with a utility plan or sketch, emailed with “FLOW TEST REQUEST” in the subject lineCode official; L&I in Philadelphia
MarylandWashington Suburban Sanitary Commission (WSSC) offers fire flow tests on its system; Baltimore City Department of Public Works (DPW) runs tests and reports measured pressure and flow at named hydrantsWSSC Water’s online Fire Flow Test Application, which also takes payment (requests by mail ended September 2, 2026); Baltimore DPW Fire Flow Test Request Form with a site plan showing the connectionCounty fire marshal or plan reviewer
DelawareThe purveyor (Artesian, Tidewater, Veolia or a municipal utility) runs or permits the testThe purveyor’s application; the State Fire Marshal wants the result on the supplier’s letterheadOffice of the State Fire Marshal
In every state the purveyor controls who opens a public hydrant and the AHJ controls whether the result is accepted. Delaware’s State Fire Marshal applies the 12-month limit on its own Preliminary Sprinkler Form, so an older test there needs the Fire Marshal’s agreement before the form is filed.

Where a purveyor permits a contractor to run the test, the permit usually names the hydrants, the date and the purveyor inspector, and the contractor’s record should say so. A test run on a public main without the purveyor’s knowledge is rarely accepted, and in several districts it is a violation. How the test is actually run and read is covered in DGA’s article on how a hydrant flow test is run and read under NFPA 291.

How a Flow Test Differs From the Documents It Is Confused With

Three documents get sent to reviewers in place of a flow test, and none of them satisfies NFPA 13 (2022) Section 4.5.1.1. Each measures or states something different, and each has its own use.

DocumentWhat it actually saysWhy it does not replace a flow test
Purveyor availability or will-serve letterThe purveyor confirms it can supply the site and may quote a modeled pressure or a hydraulic grade; WSSC’s Hydraulic Information Sheet is one example and is a theoretical estimate at one point in the systemIt is a commitment or a model, not a measurement. The hydraulic calculation needs two measured points, static and residual at a known flow
Fire pump acceptance flow testMeasures what the pump delivers at churn, rated flow and 150 percent of rated flow after installationIt tests the pump, not the main feeding it. The suction supply to the pump still comes from the hydrant flow test, as described in DGA’s article on what happens at a diesel fire pump acceptance test
NFPA 25 main drain testOpens the system’s main drain and records the static and residual pressure at the riser gauge to detect a closed valve or an obstructionThe flow through a 2 in. drain is unknown and small, so the two readings do not define a supply curve

The practical difference shows up in the calculation. A flow test gives the designer the two points needed to plot the supply curve against the sprinkler demand; DGA’s article on plotting sprinkler demand against the supply curve shows that step. A letter, a pump test or a main drain reading gives one number or the wrong number.

When a Current Flow Test Is Required

A current test is required at three points. The first is before working plans are submitted, which is the rule itself. The second is when a project stalls: if the plans were drawn on a 10-month-old test and the submittal slips 4 months, the test is 14 months old at submittal and the designer needs a new one or the AHJ’s written acceptance. The third is when the purveyor changes the system that feeds the site, such as a new pressure zone boundary, a replaced main or a booster station taken out of service; a test older than that change is not representative no matter its age.

Reviewers in New York City, New Jersey and Philadelphia check the test date against the submittal date as a matter of routine. Ordering the test early in design and submitting the working plans inside the window is cheaper than running it twice.

Common Misconceptions

“A 5-year-old test plus a purveyor letter is enough.” No. The letter confirms service; it does not refresh the measurement. The AHJ can accept the old test under the approval clause, but that is a decision the reviewer makes and documents, not a substitution the designer makes.

“The annual main drain test keeps the supply data current.” No. The main drain test under NFPA 25 (2023) Chapter 13 checks that the supply is still connected and the control valve is open. It does not measure flow, so it cannot replace the hydrant flow test behind a hydraulic design.

“The contractor can flow the street hydrants on the morning of the test.” Only with the purveyor’s permit. The hydrants belong to the purveyor, and a test run without its permission is usually refused by the AHJ and can draw a fine from the utility.

Who Needs to Act

WhoOne action
OwnerOrder the flow test as soon as the sprinkler scope is known and keep the written record with the project file; a lapsed test delays the permit.
EngineerCheck the test date against the planned submittal date before building the hydraulic calculations, and ask the AHJ in writing if an older test must be used.
Sprinkler contractorPut the test date, hydrant numbers, elevations and the name of the party that ran it on the hydraulic calculation sheet, not only in an attachment.
PurveyorIssue the record with the pressure zone, main size and any abnormal system condition noted, so the AHJ can judge whether it still represents the supply.
InsurerAsk for the test behind the design when underwriting; a current test with a margin above demand is the simplest evidence the water supply works.

Key Takeaway: NFPA 13 (2022) Section 4.5.1.1 makes a sprinkler flow test current for 12 months, measured from the test date to the working plan submittal, with any extension granted by the AHJ and not assumed by the designer. The purveyor, or a contractor it permits, runs the test on public mains; the owner’s contractor runs it on private mains; and the record must carry the date, hydrant locations and elevations, static, residual, flow and the tester’s name to be usable.

Frequently Asked Questions

How old can a flow test be for sprinkler design?

No more than 12 months old on the date the working plans are submitted, under NFPA 13 (2022) Section 4.5.1.1. The AHJ can accept an older test, but that acceptance is the reviewer’s decision and should be in writing.

Can a sprinkler contractor run a hydrant flow test?

Conditional: on a private main, yes, since the hydrants belong to the owner. On a public main the contractor needs the purveyor’s permit, and many purveyors in New York, New Jersey, Pennsylvania, Maryland and Delaware run the test themselves on request instead.

Does a purveyor availability letter count as a flow test?

No. An availability or will-serve letter confirms the purveyor can serve the site and may quote a modeled pressure. A flow test is a measurement of static and residual pressure at a known flow, and the hydraulic calculation needs the measurement.

What happens if the test expires while the plans are under review?

Nothing, in most jurisdictions. The 12 months are measured to the working plan submittal, not to approval or installation. A test that was 11 months old at submittal is still a current test if the review takes longer.

This article is general information, not a substitute for a project-specific code analysis. Code editions, local amendments, purveyor rules and reviewer practice change; confirm the adopted code and the authority having jurisdiction for the project.

Is the Flow Test Still Good for the Submittal?

Send the flow test record, the site address and the target submittal date. DGA checks the test age, the data the reviewer will look for and the margin against the sprinkler demand, and orders a new test or requests AHJ acceptance where needed. Project briefs get confirmation and preliminary code feedback within one business day.

Send a Project Brief → View Related Services

Leave a Reply

Your email address will not be published. Required fields are marked *

Quick inquiry

Ready when you are.

Your name, a way to reach you, and where the project is. One of our licensed PEs replies within one business day. No sales calls.

Prefer to describe it first? Open the Project Desk