Approvals by Jurisdiction · Comparison

DOB or FDNY: Who Approves What in New York City?

General guidance, not a code determination for any project. Confirm the adopted code and local amendments with the authority having jurisdiction.

In New York City, the Department of Buildings (DOB) reviews, permits and signs off sprinkler, standpipe and smoke control construction work and issues the certificate of occupancy, while the Fire Department of the City of New York (FDNY) reviews and approves fire alarm systems, fire protection plans and non-water suppression systems such as commercial kitchen range hood and clean agent systems. Once a building is in use, FDNY enforces the Fire Code for every one of those systems, whichever agency approved the installation.

The split dates from Local Law 195 of 2018, which moved fire alarm and several other plan reviews from DOB to FDNY for filings made on or after June 2, 2019. Most projects still touch both agencies, so the useful question is which one owns each step. This article sets the two agencies side by side, system by system, and shows how to tell which one owns a given filing.

At a Glance: DOB vs FDNY Approvals

  • Option A, DOB: reviews and permits construction work in DOB NOW: Build, including the sprinkler (SP), standpipe (SD) and mechanical systems (MS) work types, signs off each permit, and issues the Letter of Completion, temporary certificate of occupancy (TCO) and certificate of occupancy (CO).
  • Option B, FDNY: reviews fire alarm, emergency alarm, in-building auxiliary radio communication system (ARCS), fire protection plan and non-water suppression documents on FDNY Business, inspects the installed system, issues the Letter of Approval, and enforces the 2022 NYC Fire Code after occupancy.
  • Deciding factor: the system type, and whether the task is construction (design, installation, sign-off) or operation (inspection, testing, maintenance, permits and Certificates of Fitness).
  • When DOB applies: water-based suppression and smoke control construction, special inspections listed on the Technical Report: Statement of Responsibility (TR1), and the job’s Letter of Completion, TCO and CO.
  • When FDNY applies: any system Local Law 195 of 2018 moved to FDNY, battery energy storage equipment approval and outdoor installations, and the life of every system once the building is occupied.
  • Cost and complexity direction: a job with both water-based and alarm work runs two filing tracks with separate applications, fees and inspections. FDNY charges a flat $420 plan examination fee per TM-1 application, not based on job cost (as of November 2026).

What Do DOB and FDNY Each Approve?

DOB is the city’s construction regulator. DOB reviews construction documents under Title 28 of the NYC Administrative Code, issues work permits, inspects or accepts special inspection reports, signs off each permit under Article 116 and issues certificates of occupancy under Article 118. For fire protection, DOB’s work is the water-based systems and the building features they protect.

FDNY is the city’s fire code regulator. FDNY’s Bureau of Fire Prevention reviews the systems Local Law 195 of 2018 transferred to it, mainly on the Application for Plan Examination/Document Review (Form TM-1), inspects those installations, approves equipment, certifies the people who supervise systems through Certificates of Fitness, issues Fire Code permits and inspects occupied buildings. Section 907.1.1 of the 2022 NYC Building Code (BC 907.1.1) now sends fire alarm construction documents to the Fire Department only.

The two codes also divide the work. BC 901.2 says fire protection systems are installed, repaired, operated and maintained under both the Building Code and the Fire Code, and Section 901.4.1 of the 2022 NYC Fire Code (FC 901.4.1) requires systems to be designed and installed under the construction codes. In practice the Building Code governs design and installation, and the Fire Code governs operation, inspection, testing and maintenance under FC 901.6.

Figure 1: The DOB Lane and the FDNY Lane

Department of Buildings (DOB)
  • Sprinkler (SP) and standpipe (SD) filings, permits and sign-off
  • Smoke control under the mechanical systems (MS) filing
  • Special inspections on the TR1: BC 1705.18, 1705.29, 1705.30
  • Range hood ductwork and gas valve work
  • Indoor battery storage installations of FDNY-approved equipment
  • Letter of Completion, TCO and CO
Fire Department (FDNY)
  • Fire alarm, emergency alarm and ARCS plans on the TM-1
  • Fire protection plans
  • Range hood (TM-R2) and clean agent suppression
  • Battery unit approvals; outdoor and rooftop battery installations
  • Letter of Acceptance, inspection, Letter of Approval
  • Certificates of Fitness, Fire Code permits, ongoing inspections
Since Local Law 195 of 2018 took effect for filings on or after June 2, 2019, DOB keeps sprinkler, standpipe and smoke control construction and issues the Letter of Completion, TCO and CO, while FDNY reviews fire alarm, emergency alarm, ARCS, fire protection plan and non-water suppression filings and governs all systems after occupancy.

Side by Side: Who Reviews, Inspects and Signs Off Each System

The table follows each common fire protection system through plan review, inspection or test, the document that closes the work, and what FDNY requires once the system is operating. Sources are DOB and FDNY pages and the 2022 NYC codes, as of November 2026.

SystemPlan reviewInspection or testSign-off documentAfter occupancy (FDNY)
SprinklerDOB, SP work type in DOB NOW: Build; small changes by a licensed fire suppression piping contractor as a Limited Alteration Application (LAA)Special inspection under BC 1705.29 by a DOB-registered agency named on the TR1SP permit sign-off by DOB final inspection or certified TR Final; DOB Letter of Completion or CO for the jobInspection, testing and maintenance under FC 901.6; monthly inspection by an S-12 Certificate of Fitness holder (FC 903.5)
StandpipeDOB, SD work type in DOB NOW: BuildSpecial inspection under BC 1705.30SD permit sign-off; DOB Letter of Completion or COFC 901.6 maintenance; S-13 holder, or S-14 continuous supervision of a multi-zone system (FC 905.1.1); fire department connection hydrostatic test at least every 5 years (FC 912.6)
Fire alarm and emergency alarmFDNY, Form TM-1 on FDNY Business; Letter of Acceptance with stamped plansFDNY inspection requested on Form B-45 (Request for Inspection Date), or a professionally certified installation under Title 3 of the Rules of the City of New York (3 RCNY) 104-02 for components other than core componentsFDNY Letter of Approval; failed items go on a Notice of DefectTesting and servicing by Certificate of Fitness holders (FC 901.6.3); S-95 holder or Fire and Life Safety Director (F-89) depending on the building
Smoke controlDOB, as part of the MS filingSmoke control testing special inspection under BC 1705.18MS permit sign-offMaintenance program with periodic tests under FC 909.1.1
Range hood suppressionFDNY, Form TM-R2; hood ductwork, ventilation and gas valve work filed with DOBFDNY inspectionFDNY inspection approval closes the jobServicing of wet chemical systems by S-17 or S-71 Certificate of Fitness holders
Clean agent and other non-water suppressionFDNY, two TM-1 filings, mechanical and electrical; the electrical approval requires proof of the mechanical approvalFDNY inspectionFDNY Letter of ApprovalServicing by gaseous system Certificate of Fitness holders (S-16, S-61)
Fire protection planFDNY, under Administrative Code Article 109, with the DOB job numberNot a physical systemFDNY Letter of ApprovalNot applicable
Battery energy storage system (ESS)FDNY certificate of approval for each battery unit (FC 608, FC 112); installation reviewed by DOB if indoor and FDNY-approved (FC 608.6.1), by FDNY if outdoor, rooftop or mobile (FC 608.6.2)FDNY installation approval for large outdoor systems (3 RCNY 608-01)Closed by the reviewing agency: DOB for indoor installations, FDNY for outdoor, rooftop and mobile systemsFDNY permit under FC 105.6 (FC 608.3); operation under Certificate of Fitness supervision (FC 608.7)

Fire alarm jobs filed in the Buildings Information System (BIS) before June 2, 2019 stayed with DOB through amendment and sign-off.

Two rows split across both agencies by design. A commercial kitchen hood needs FDNY approval of the suppression system and a DOB filing for the ductwork, ventilation and gas valve. A battery energy storage system needs FDNY approval of the equipment in every case, while the installation review goes to DOB or FDNY depending on where the system sits and whether it matches its FDNY approval. Even where DOB reviews an indoor installation, FC 608.6.1 keeps FDNY review of the monitoring, smoke control, explosion mitigation and fire protection features.

Fire alarm work also has an FDNY professional certification route. Under 3 RCNY 104-02, a registered architect (RA) or professional engineer (PE) may professionally certify the design, and FDNY issues a Letter of Approval after it accepts a certified installation, but core components such as the fire alarm control unit, elevator recall devices and stair manual pull stations cannot be professionally certified.

Opens the Project Desk with your sentence. Our licensed PEs review every brief and reply within one business day.

How to Tell Which Agency Owns a Filing

The first test is the system. Fire alarm, emergency alarm, ARCS, fire protection plans and alternative (non-water) automatic extinguishing systems, including commercial cooking systems, go to FDNY under Local Law 195 of 2018. Sprinkler, standpipe and smoke control work goes to DOB through DOB NOW: Build, which has no fire alarm work type.

The second test is the stage. Design, installation and the sign-off of construction work sit with the agency that reviewed the plans. Operation, periodic testing, maintenance, impairments and the people who supervise systems sit with FDNY under the Fire Code, whichever agency approved the installation.

The third test is the filing date. A fire alarm job filed in BIS before June 2, 2019 stays a DOB job through amendment and sign-off. Every fire alarm application since then goes to FDNY, and FDNY has taken fire alarm applications online through FDNY Business since May 2020.

Figure 2: Which Agency for This Work?

Fire protection work in a New York City building
Is the work a fire alarm, emergency alarm, ARCS, fire protection plan or non-water suppression system (range hood, clean agent)?
YesFDNY plan examinationTM-1 or TM-R2 on FDNY Business; FDNY inspection; Letter of Approval
No
Sprinkler, standpipe or smoke controlDOB NOW: BuildSP, SD or MS work type; special inspections on the TR1; permit sign-off
Battery energy storageFDNY equipment approvalDOB reviews indoor installations of approved units; FDNY reviews outdoor, rooftop and mobile systems
Operating, testing or servicing an installed systemFDNY under the Fire CodeFC 901.6 maintenance, Certificates of Fitness, FC 105.6 permits
Local Law 195 of 2018 sends fire alarm, emergency alarm, ARCS, fire protection plan and non-water suppression reviews to FDNY; sprinkler, standpipe and smoke control construction stays in DOB NOW: Build; battery storage splits under FC 608.6; and every installed system is maintained under the 2022 NYC Fire Code, enforced by FDNY.

The filing mechanics differ by agency, and each has its own guide. DGA’s article on how fire protection plan review works at NYC DOB covers the SP and SD filings, and the guide to FDNY TM-1 fire alarm filing covers the FDNY side from application to Letter of Approval.

When a Project Needs Both Agencies

Most new buildings and many alterations need both agencies. A typical sprinklered office or residential building has SP and SD permits at DOB and a fire alarm application at FDNY, with the sprinkler waterflow and valve supervisory devices shown on the fire alarm drawings. The two tracks run in parallel, and neither agency closes the job for the other.

The handoff point is the certificate of occupancy. DOB issues the TCO and CO, but DOB’s Certificate of Occupancy Worksheet requires FDNY documents: a Letter of Approval for the fire protection plan (or FDNY’s filing receipt) and for any fire suppression system, and for fire alarm a Letter of Approval, a Letter of Recommendation, or a Letter of Defect with a sealed affidavit of correction approved by the DOB borough commissioner. An FDNY Notice of Defect left open at the fire alarm inspection therefore holds up a DOB document, which is why DGA’s guide to clearing an FDNY Letter of Defect matters to the whole project schedule.

Places of assembly follow the same pattern. DOB issues the Place of Assembly Certificate of Operation (PACO) where 75 or more members of the public gather indoors (200 or more outdoors) and performs the initial inspection, and within one year the space needs an FDNY Place of Assembly Permit, which FDNY renews annually after its own inspection.

Construction sites also answer to both codes. The Building Code’s Chapter 33 sets the construction standpipe and keeps existing sprinklers in service during alteration, and BC 3301.1.2 requires conformance with the Fire Code, whose Chapter 33 adds the construction site fire safety manager under FC 3308.1. DOB’s sprinkler guidance for design professionals also notes that a sprinkler impairment of five stories or more needs FDNY approval.

Where Each Agency Has No Role

DOB has no role in fire alarm plan review for applications filed since June 2, 2019. DOB also does not issue Certificates of Fitness, Fire Code permits or the FDNY Place of Assembly Permit, and DOB does not enforce routine inspection, testing and maintenance of systems in occupied buildings.

FDNY does not review sprinkler or standpipe drawings for the construction permit; that work is filed with DOB, not on the TM-1. FDNY does not issue a Letter of Completion, a TCO or a CO, and DGA’s article on whether FDNY issues a sprinkler Letter of Completion explains why that closeout always comes from DOB. For fire alarm work filed with FDNY since June 2, 2019, no Letter of Completion is issued either, because FDNY’s inspection approval closes the job.

Document names cause their own confusion. A DOB Letter of No Objection confirms the legal use of a building that has no certificate of occupancy, typically one built before 1938. An FDNY Letter of No Objection is a different result of an FDNY engineering review, issued when the requirements are met but FDNY is not the main approving authority.

Key Takeaway: In New York City, DOB approves and signs off sprinkler, standpipe and smoke control construction and issues the Letter of Completion, TCO and certificate of occupancy. FDNY approves fire alarm, emergency alarm, ARCS, fire protection plans and non-water suppression, approves battery storage equipment, and governs every system once the building is occupied.

Frequently Asked Questions

Does FDNY approve sprinkler plans?

No. Sprinkler drawings are filed with DOB as the sprinkler (SP) work type in DOB NOW: Build, and DOB permits, inspects and signs off the work. FDNY’s role with sprinklers is the Fire Code inspection, testing and maintenance of the system once it is in service.

Who issues the fire alarm Letter of Approval?

FDNY. After FDNY accepts the TM-1 plans and the installation passes the FDNY inspection, or a professionally certified installation is accepted under 3 RCNY 104-02, FDNY issues the Letter of Approval. That approval closes the fire alarm job; no Letter of Completion is issued for fire alarm work filed with FDNY.

Does FDNY inspect standpipes?

Conditional: during construction, standpipe work is inspected for DOB by the special inspector named on the TR1 under BC 1705.30. Once the building is occupied, the Fire Code requires inspection, testing and maintenance by Certificate of Fitness holders, including a fire department connection hydrostatic test at least every 5 years (FC 912.6), and FDNY enforces those requirements.

Which agency issues the certificate of occupancy?

DOB issues both the temporary and the final certificate of occupancy under Article 118 of the Administrative Code. DOB’s Certificate of Occupancy Worksheet requires FDNY documents first, including a fire alarm Letter of Approval or one of the alternatives the worksheet accepts.

This article is general information, not a code determination for any project. DOB and FDNY procedures, forms and fees change; confirm the current requirements with the agency for each job.

Not Sure Which Agency Owns the Filing?

Send the scope, the building and the systems involved. DGA sorts the DOB and FDNY filings, prepares the submissions and tracks both to sign-off. Project briefs get confirmation and preliminary code feedback within one business day.

Send a Project Brief → View Related Services

Leave a Reply

Your email address will not be published. Required fields are marked *

Quick inquiry

Ready when you are.

Your name, a way to reach you, and where the project is. One of our licensed PEs replies within one business day. Every inquiry is confidential.

Prefer to describe it first? Open the Project Desk