How Long Does Fire Protection Plan Review Take by State?
General guidance, not a code determination for any project. Confirm the adopted code and local amendments with the authority having jurisdiction.
Fire protection plan review takes as long as the reviewer’s legal clock allows, and as of November 2026 New Jersey, Pennsylvania and New York City each set one by law: New Jersey requires a decision on a permit application within 20 business days, Pennsylvania within 30 business days for commercial work, and New York City within 40 calendar days at both the Department of Buildings (DOB) and the Fire Department of the City of New York (FDNY). New York State sets no statewide deadline, and the Maryland and Delaware State Fire Marshals publish none, so in those places the reviewing office sets the pace. A clock measures one review decision, not the whole approval, so the number of resubmission rounds often decides the real schedule.
The sections below set out who owns the clock in each jurisdiction, each deadline with its section, the steps and documents that start a clock, what restarts it, and what inspections and closeout add after approval. Turnaround figures appear only where the agency itself publishes one.
At a Glance: Fire Protection Plan Review Times
- Who files: the owner or an authorized agent, usually the design professional of record; at FDNY the TM-1 applicant is a Professional Engineer (PE), Registered Architect (RA), owner or building manager, and in Delaware a licensed fire protection company signs the system applications.
- Where it is filed: the local building or construction office in New York State, New Jersey, Pennsylvania and Maryland; DOB NOW: Build (sprinkler, standpipe) and FDNY Business (fire alarm) in New York City; eCLIPSE in Philadelphia; the State Fire Marshal’s three county offices, on paper, in Delaware.
- Documents required: the application forms, sealed construction documents, sprinkler or fire alarm shop drawings, hydraulic calculations with a current water flow test, and proof of any prior approvals.
- Timeline range (as of November 2026): statutory clocks run from 20 business days (New Jersey) to 40 calendar days plus one extension (New York City); New York State, Maryland and Delaware set or publish none.
- Most common rejection: an incomplete or out-of-sequence submission; the New York City DOB clock does not start until the application is complete.
- Approval document: released or approved plans and the construction permit (New Jersey, Pennsylvania, New York State, Maryland), DOB approval and permit or an FDNY Letter of Acceptance (New York City), and State Fire Marshal approved plans (Delaware).
Who Sets the Plan Review Clock in Each Jurisdiction?
A plan review clock exists only where a state regulation or a city code writes one. In New Jersey and Pennsylvania the state rules bind every local code office: N.J.A.C. (New Jersey Administrative Code) 5:23-2.16(a) under the Uniform Construction Code (UCC), and 34 Pa. Code 403.43(a) under the Pennsylvania UCC. New York City writes its own deadlines into Administrative Code 28-104.2.7 for DOB and 2022 NYC Fire Code Sections FC 105.2.4 and FC 105.4.4 for FDNY.
New York State’s minimum standards for local code programs, 19 NYCRR (New York Codes, Rules and Regulations) Part 1203, require building permits but set no number of days for review. The remedy for a stalled application is a petition to the Department of State when a code official fails to act within a reasonable time (19 NYCRR 1205.3(a)(2) and 1205.4(b)). Petitions that go to a regional board of review are decided within 60 days of a complete petition unless there is good cause (19 NYCRR 1205.4(e)).
Maryland and Delaware split fire review between building officials and fire marshals. The Maryland Office of the State Fire Marshal (OSFM) and the Delaware State Fire Marshal (SFM) publish no review time, and the 2026 edition of Delaware Regulation 701 (1 Del. Admin. Code 701) sets none. In both states the code official sets the schedule, and a county or city may publish its own figure.
Federal projects follow a different rule. Under 40 U.S.C. 3312(d), a federal agency gives state or local officials its plans on request for a review of not more than 30 days, but those officials have no power to enforce the result. On General Services Administration (GSA) projects, the regional fire protection engineer acts as the authority having jurisdiction (AHJ) under GSA order PBS 5921.1.
Fire Protection Plan Review Times by Jurisdiction, as of November 2026
The table lists each statutory clock with its section, any turnaround figure the agency itself publishes, and what restarts or ends the clock. Business days exclude weekends and holidays, so 20 business days is about 4 calendar weeks, while the New York City clocks run in calendar days.
| Jurisdiction | Reviewer | Statutory clock and section | Agency-published figure | What restarts or ends it |
|---|---|---|---|---|
| New Jersey | Fire protection subcode official in the local construction office; Department of Community Affairs (DCA) Bureau of Construction Project Review for Class 1 and 2 structures the local office is not classified to review | 20 business days to approve or deny an application, in whole or in part, extendable only with the applicant’s consent; 7 business days on resubmitted plans (N.J.A.C. 5:23-2.16(a)) | The Bureau of Construction Project Review publishes 20 business days from a complete submittal and 7 business days for corrections in its own reviews | Failure to act counts as a denial that can be appealed; amended plans after a DCA release are handled as new 20-day projects |
| Pennsylvania | Municipal code official or its third-party agency; the Department of Labor and Industry (L&I) where the municipality opted out, and for state-owned buildings | Commercial: 30 business days from the filing date, extendable by written agreement (34 Pa. Code 403.43(a)). Residential: 15 business days, or 5 with a design professional’s certification (403.63(a)) | Philadelphia Department of Licenses and Inspections (Philadelphia L&I), Fire Suppression Systems Permit: 20 business days with plans; accelerated review of new construction in 5 business days | A denial must be written and cite the code; 403.43 sets no separate period for a resubmission |
| New York City, DOB | Department of Buildings (sprinkler and standpipe work) | 40 calendar days after a complete application to approve complying documents, extendable once by 20 calendar days for good cause (Administrative Code 28-104.2.7) | None beyond the code | An application is deemed abandoned 12 months after submission unless diligently pursued or permitted (28-104.2.3) |
| New York City, FDNY | FDNY Bureau of Fire Prevention (fire alarm, non-water suppression, fire protection plans) | 40 calendar days to approve, deny or preliminarily deny, extendable once by 40 calendar days for good cause (FC 105.4.4 and FC 105.2.4) | Resubmission is free within six months of the Letter of Deficiency | A revised resubmission gets the same 40-day period; after six months a new fee may apply and the application is considered abandoned |
| New York State (outside NYC) | City, town or village building department; county or Department of State where a locality opted out | None: 19 NYCRR Part 1203 sets no review period | None at state level | Failure to act within a reasonable time can be appealed under 19 NYCRR 1205.4(b) |
| Maryland | County permit office, with OSFM or a county fire marshal for fire review | None published | OSFM: none. Prince George’s County Department of Permitting, Inspections and Enforcement (DPIE): most commercial permit applications reviewed within 4 weeks | OSFM stops review when its plan review invoice is unpaid (Code of Maryland Regulations, COMAR 29.06.04.04) |
| Delaware | SFM county offices; the Wilmington Fire Marshal inside the city, and the SFM lists jurisdictional city fire marshals in Dover, Newark and New Castle | None: Regulation 701 (2026) sets no review period | SFM: none. Wilmington Fire Marshal: none | Site plans are approved before building plans, and a new system needs the building plan submitted first |
Two details in the table decide how the deadlines play out. The DOB clock starts only when the application is complete, while Pennsylvania’s runs from the filing date and FDNY’s from submission, so an incomplete DOB filing can sit outside any clock. Each clock is also a maximum for one decision, and that decision can be a denial with comments rather than an approval; the companion article on fire protection plan review under the Pennsylvania UCC covers how the 30-day rule works in practice.
Figure 1: Plan Review Clocks Side by Side
Steps Between a Fire Protection Submission and Approval
The sequence is the same everywhere, even where no clock applies. What changes is which office reviews and which prerequisites have to clear first.
- Confirm the reviewer. In New Jersey, the DCA Bureau of Construction Project Review takes Class 1 and Class 2 structures when the local office is not classified for them (N.J.A.C. 5:23-4.24), as the article on fire protection plan review under the NJ UCC explains. In Pennsylvania, L&I reviews commercial work where a municipality opted out of enforcement (34 Pa. Code 403.141(c)). In New York City, sprinkler and standpipe work goes to DOB and fire alarm work to FDNY.
- Clear the prerequisites. A New Jersey application states that all State, county and local prior approvals are in place; plan review may proceed without them, but no permit issues until they are (N.J.A.C. 5:23-2.15(a)5). Delaware approves the site plan before the building plans and needs the building plan before a new system submittal. Philadelphia issues the building permit before the fire suppression permit on new construction, additions and alterations.
- File a complete package with the fee. The Wilmington Fire Marshal does not process plans until the fee is paid, and the Maryland OSFM stops review when its invoice goes unpaid. A missing form or technical section keeps the DOB clock from starting and gives other reviewers grounds for a denial.
- Receive the decision. The reviewer approves, approves with conditions, or returns comments. FDNY answers with a Letter of Acceptance, a Revision Required notice (a Letter of Deficiency), an Additional Information Request or Application Not Required, and a Pennsylvania denial must list each noncompliant element with its code citation.
- Respond and resubmit. The response answers every comment and is filed with the revised sheets and a transmittal letter naming the changes, as FDNY requires on FDNY Business. New Jersey must act on resubmitted plans within 7 business days, and FDNY reviews a revised filing under the same 40 calendar days.
- Obtain the approval and the permit. DCA stamps conforming plans “released” and the municipality issues the permit and inspects. In Pennsylvania the code official marks the documents approved and returns a set that stays on site (34 Pa. Code 403.43(c)), and FDNY fire alarm work starts under a Project Authorization after the Letter of Acceptance.
Figure 2: One Review Round, Then the Next
Documents That Make a Submission Complete on Day One
A complete package is what starts the DOB clock in New York City, and it is what avoids a first round of comments everywhere else. The table lists the documents a fire protection submission usually needs and who prepares each one.
| Document | Who prepares it | Where the requirement sits (examples) |
|---|---|---|
| Permit application and fire protection technical section | Owner or authorized agent, with the design professional completing the technical data | New Jersey forms F100 and F140; FDNY TM-1 through FDNY Business; Delaware SFM New Building, Water Based Fire Suppression System and Fire Alarm Installation applications |
| Sealed construction documents (plans and specifications) | Licensed architect or professional engineer | 19 NYCRR 1203.3(a)(3)(ix) and Education Law 7209 (New York State); N.J.A.C. 5:23-2.15(f)1ix; 34 Pa. Code 403.42a(c) |
| Sprinkler and fire alarm shop drawings | Installing contractor, reviewed by the design professional; in Delaware, the licensed company’s certificate holder or a Delaware-registered PE | 34 Pa. Code 403.42a(f)(3) (approved before installation); N.J.A.C. 5:23-2.15(f)1xi(1) (design professional’s conformance letter); Delaware SFM application forms |
| Hydraulic calculations and water flow test | Fire protection engineer or sprinkler contractor | National Fire Protection Association (NFPA) 13 (2022) Section 4.5.1.1: test no more than 12 months before working plan submittal unless the reviewer approves otherwise; Delaware Preliminary Sprinkler Form; Philadelphia Water Flow Test Data Form |
| Fire alarm riser, floor plans, input/output matrix and calculations | Design professional (sealed by a New York State registered design professional for FDNY); licensed fire alarm company in Delaware | FDNY fire alarm application; Delaware SFM fire alarm submittal (battery and voltage drop calculations) |
| Statement of prior approvals | Applicant | N.J.A.C. 5:23-2.15(a)5 |
| Special inspection list | Design professional | N.J.A.C. 5:23-2.15(a)6 (Class 1 structures and smoke control); the TR1 technical report in DOB NOW: Build |
| Building records for an existing system | Owner, through the design professional | FDNY fire alarm filing: certificate of occupancy or approved Schedule A, the prior Letter of Approval when modifying a system, asbestos compliance |
DGA prepares fire protection submissions and tracks them through plan review across New York, New Jersey, Pennsylvania, Maryland and Delaware. Project briefs get confirmation and preliminary code feedback within one business day. See where DGA works →
What Drives Delays in Fire Protection Plan Review
Most delay sits outside the statutory clock. Time spent assembling a complete package, waiting on a prerequisite approval or answering comments does not count against the reviewer, and in New York State, Maryland and Delaware there is no clock to count against at all.
Sequence is the first driver. Delaware requires approval of the electrical plans for a new electric fire pump by a licensed electrical inspection agency before the fire pump plans go to the SFM, and FDNY needs proof of the mechanical approval before it approves the electrical filing for a clean agent system. Every prerequisite adds its own review period in front of the fire protection one, a point the article on Delaware State Fire Marshal plan review covers for site, building and system submittals.
The number of reviewers is the second driver. In New Jersey, DCA can release the plans while the municipal office issues the permit, and the fire and electrical subcode officials share plan review of fire alarm wiring under N.J.A.C. 5:23-3.4. A code edition in transition adds questions: New Jersey lets a complete application filed through February 17, 2027 use the codes in force before August 17, 2026, and the application should say which edition it uses.
Review rounds are the third driver, because each round runs its own period. Two rounds of comments in New Jersey can add up to 14 business days of review on top of the first 20, before counting the design team’s response time. DGA’s Fire Protection Project Timeline Estimator returns a planning schedule range in two phases: engineering, then the expected filing and plan review cycle.
Why Submissions Are Returned and the Clock Restarts
Returned submissions tend to share a short list of causes, and most are paperwork rather than design. The table pairs each reason with its fix.
| Reason | Fix |
|---|---|
| Application incomplete: a missing form, technical section, seal or fee, so the DOB clock never starts and other reviewers return or deny the filing | Check the package against the agency’s own list before filing: F100 with F140 in New Jersey; the TM-1 with the sealed riser, floor plans and input/output matrix at FDNY; the SFM application plus the Preliminary Sprinkler Form for a new sprinklered building in Delaware. |
| Seal or license data missing from the sheets | In New York State show the seal, signature, license number, registration expiration date and firm name (19 NYCRR 1203.3(a)(3)(ix)); in Delaware put the company name, SFM license number and certificate holder’s name, number and signature on every plan page. |
| Water flow test older than 12 months | Run a new test before the hydraulic calculations are finalized, since NFPA 13 (2022) Section 4.5.1.1 and Delaware’s Preliminary Sprinkler Form both look for a test within the past 12 months. |
| Contractor shop drawings filed without the design professional’s review (New Jersey) | Have the design professional review them and submit a letter stating they conform, as N.J.A.C. 5:23-2.15(f)1xi(1) requires. |
| Filed out of sequence | Hold the system submittal until its prerequisite is approved: the Delaware building plan, the Philadelphia building permit, the Delaware fire pump electrical approval, or the FDNY mechanical approval for a clean agent system. |
| Code edition not stated during the New Jersey grace period | State on the application whether the 2024 codes or the prior edition apply; the choice is open only to complete applications filed through February 17, 2027. |
| Plans amended after release or approval | Settle the design before filing and bundle changes: the DCA Bureau of Construction Project Review treats amended plans after release as a new 20-day project, and the Wilmington Fire Marshal treats addenda and change orders as new projects with a new fee. |
| FDNY response sent more than six months after the Letter of Deficiency | Respond inside six months, while resubmission is free; after that a new filing fee may apply and FDNY considers the application abandoned. |
After Approval: Inspections and Closeout
Plan approval starts the second half of the schedule, and none of the review clocks cover it. Inspections are booked on the inspector’s calendar, acceptance tests need the system complete, and the final certificate follows its own procedure.
In New Jersey the municipal office inspects the work even when DCA released the plans, and a certificate of occupancy issues within 10 business days of a written application once the building is entitled to one (N.J.A.C. 5:23-2.23(j)). In Pennsylvania a permit becomes invalid if work does not start within 180 days or stops for 180 days, with written extensions for cause up to a 5-year limit (34 Pa. Code 403.43(g)). In New York State a temporary certificate of occupancy issues only when the required fire protection systems are operational (19 NYCRR 1203.3(d)).
In New York City each DOB permit, including sprinkler (SP) and standpipe (SD), is signed off by a passed final inspection or a certified final technical report, and DOB issues the Letter of Completion once every work type is signed off; the article on fire protection plan review at NYC DOB walks through that closeout. FDNY fire alarm work ends with a Letter of Approval (LOA) after an inspection requested on Form B-45, and items on a Notice of Defect are certified corrected on Form FA-26 within 90 days. A DOB temporary certificate of occupancy (TCO) typically expires 90 days after issuance and may be renewed.
In Delaware the SFM witnesses the hydrostatic test before the work is closed in and performs an acceptance test before the building or tenant space is occupied, with the contractor’s material and test certificates in hand. In Maryland, the Baltimore County Fire Marshal’s Office witnesses sprinkler, standpipe, fire pump and fire main tests and asks for inspection requests at least 3 working days ahead.
Codes and Fire Protection Filings by Jurisdiction
| Jurisdiction | Adopted code (as of November 2026) | Where fire protection plans are filed | Filing or permit name |
|---|---|---|---|
| New York State (outside NYC) | 2025 Uniform Code (2024 I-Codes), in effect since December 31, 2025 | City, town or village building department | Building permit under 19 NYCRR 1203.3(a) |
| New York City | 2022 NYC Construction Codes and 2022 NYC Fire Code | DOB for sprinkler and standpipe; FDNY for fire alarm, non-water suppression and fire protection plans | DOB NOW: Build, SP and SD work types; FDNY TM-1 through FDNY Business |
| New Jersey | UCC on the 2024 I-Codes, effective August 17, 2026; Uniform Fire Code on the 2018 International Fire Code (IFC) | Local construction office; DCA through ePlans for state-reviewed projects | Construction permit, forms F100 and F140 |
| Pennsylvania | UCC on the 2021 I-Codes since January 1, 2026; no statewide fire code | Municipal code office or third-party agency; L&I in opt-out municipalities | Commercial building permit (34 Pa. Code 403.42a); in Philadelphia, the Fire Suppression Systems Permit in eCLIPSE |
| Maryland | Maryland Building Performance Standards on the 2021 International Building Code (IBC); State Fire Prevention Code, NFPA 1 and NFPA 101 (2024) | County permit office, with OSFM or a county fire marshal | County permit with the Fire Marshal Plan Review form; Fire Protection System and Fire Alarm System permits in Montgomery County |
| Delaware | State Fire Prevention Regulations (Regulation 701, 2026 edition) on NFPA 1 and NFPA 101 (2024); IBC by county | SFM offices in New Castle, Dover and Georgetown, on paper; the Wilmington Fire Marshal inside the city | SFM building, site and system applications |
Local amendments are not shown.
Key Takeaway: As of November 2026, New Jersey (20 business days, N.J.A.C. 5:23-2.16(a)), Pennsylvania (30 business days for commercial permits, 34 Pa. Code 403.43(a)) and New York City (40 calendar days at DOB and at FDNY, each extendable once) put a deadline on fire protection plan review. New York State sets none, and the Maryland and Delaware State Fire Marshals publish none. Each clock covers one decision, so a complete first submission and item-by-item responses do more for the schedule than any deadline.
Frequently Asked Questions
Which state has the fastest fire protection plan review?
New Jersey has the shortest statutory clock in the region for commercial work: a construction official must approve or deny a permit application within 20 business days and act on resubmitted plans within 7 business days (N.J.A.C. 5:23-2.16(a)). Pennsylvania allows 30 business days for commercial permits and New York City allows 40 calendar days at DOB and at FDNY, while New York State sets no deadline and the Maryland and Delaware State Fire Marshals publish none, as of November 2026.
Does the review clock include resubmissions?
Conditional: in New Jersey a resubmission gets its own 7 business day clock (N.J.A.C. 5:23-2.16(a)), and FDNY reviews a revised application under the same 40 calendar day period (2022 NYC Fire Code FC 105.2.4). Pennsylvania’s 34 Pa. Code 403.43 sets no separate period for a resubmission.
Can fire protection plan review be expedited?
Conditional: some reviewers offer a faster path. Philadelphia L&I offers accelerated review of fire suppression permits for new construction with plans in 5 business days, for a fee of $1,050 as of November 2026, and the Baltimore City Fire Department accepts third-party review of small fire protection scopes, which it states takes about 7 business days.
How long does FDNY fire alarm review take?
FDNY must approve, deny or preliminarily deny fire alarm design documents within 40 calendar days of submission, and may extend that once by 40 calendar days for good cause (2022 NYC Fire Code FC 105.4.4 and FC 105.2.4). A revised resubmission gets the same 40-day period, and resubmission is free within six months of the Letter of Deficiency.
What happens if the reviewer misses the deadline?
Conditional: in New Jersey a construction official’s failure to act within 20 business days counts as a denial that can be appealed to the construction board of appeals, with no appeal fee (N.J.A.C. 5:23-2.16(a) and 5:23A-2.1). In New York State, failure to act within a reasonable time can be appealed to the Department of State under 19 NYCRR 1205.4(b). Pennsylvania deems a residential application approved after its deadline (34 Pa. Code 403.63(a)), but 403.43 has no deemed approval for commercial work.
More in Approvals by Jurisdiction
- How Does AHJ Review Work in NYC, NJ and Philadelphia?
- How Do Pittsburgh Fire Protection Approvals Work?
- How Do Federal Agencies Review Leased-Space Fire Protection?
- What Is Maryland’s Sprinkler Law for New Homes?
- Does the Pennsylvania Fire and Panic Act Still Apply?
- What Does NYC Require for Construction Site Fire Safety?
This article is general information, not a substitute for a project-specific code analysis. Review periods, fees and reviewer practice change; confirm the current rules with the authority having jurisdiction for the project.
Need a Fire Protection Submission That Clears the First Review?
Send the jurisdiction, the scope and the drawings that exist. DGA identifies the reviewer and the clock that applies, assembles a complete package and answers comments item by item. Project briefs get confirmation and preliminary code feedback within one business day.