Approvals by Jurisdiction · Definition
What Is a NYC Letter of No Objection?
General guidance, not a code determination for any project. Confirm the adopted code and local amendments with the authority having jurisdiction.
A New York City (NYC) Letter of No Objection (LNO) is a letter from the Department of Buildings (DOB) that confirms the legal use of a building, or part of one, when no certificate of occupancy (CO) shows that use, usually because the building was built before January 1, 1938, when DOB did not typically require a CO. DOB issues an LNO only where the use stays in the same zoning use group and Building Code occupancy group that DOB’s records show, with the occupancy load and egress substantially unchanged. The letter is not a substitute for a CO, and it cannot cover a change of use group or occupancy group.
DOB’s request form gives a bank, a court, the Department of Consumer Affairs and the Liquor Authority as examples of who asks for the letter. The LNO also turns up in fire protection work, because the Fire Department of the City of New York (FDNY) has asked for one with fire alarm plans for buildings that have no CO.
At a Glance: NYC Letter of No Objection
- Definition: a DOB letter, which DOB’s Code Notes call a statement of accepted use, confirming the legal use of a building or space that has no CO, or whose use differs from its CO but stays in the same zoning use group and occupancy group.
- Governing code and section: the definitions in NYC Administrative Code 28-101.5 do not include the LNO; DOB sets its conditions on the Letter of No Objection or Letter of Verification (LNO/LOV) application form, revision 7/24. The code basis is Administrative Code 28-118.3.5, which lets a building that existed before January 1, 1938 keep a lawful use without a CO while the use is not inconsistent with DOB’s records and its classification does not change.
- Who prepares it or who it applies to: the DOB borough office for the property issues it; the applicant requests it on DOB’s form, which also names the owner. It applies mostly to buildings built before 1938.
- When it’s required: when a lender, court or licensing agency needs proof of legal use and no CO shows it, and, under FDNY’s 2019 Local Law 195 guidance, with fire alarm plans for a building that has no CO or approved Schedule A.
- Typical output: a DOB letter in about 3 weeks, for a fee of $25 (1-, 2- and 3-family homes) or $130 (all other buildings), as of November 2026. It is requested at the borough office, not in DOB NOW: Build.
- Often confused with: the CO; the Letter of Verification (LOV), which verifies an existing CO; the Letter of Completion; FDNY’s own Letter of No Objection; and the NYC Loft Board’s letter of the same name.
What a NYC Letter of No Objection Is
DOB’s Code Notes on the LNO (version 1, 2017) call the letter a statement of accepted use that government agencies accept in lieu of a CO, while stating that an LNO is not a substitute for a CO. DOB decides from the building’s records, adding older proof of use or a field inspection where the file is thin.
The 1938 date explains why the letter exists. DOB’s LNO page says buildings built before 1938 are not required to have a CO unless later alterations changed the use, egress or occupancy. Administrative Code 28-118.3.5 lets a building that existed before January 1, 1938, and was lawfully used without a CO, keep that use without one, as long as the use is not inconsistent with DOB’s records of lawful use, complies with applicable laws and rules, and involves no change in use or occupancy classification.
The LNO is not limited to pre-1938 buildings. DOB’s Buildings Bulletin 2015-026 says DOB typically issues LNOs for buildings built before 1938 but may issue them for later buildings. The LNO/LOV form also allows an LNO where the use differs from the CO or the records, provided it stays in the same zoning use group under the Zoning Resolution and the same occupancy group under the Building Code (the form still names the 2008 edition), with occupancy load and egress substantially unchanged.
What a Letter of No Objection Confirms and What It Does Not
An LNO confirms DOB’s accepted use for the building or space named in the request. The applicant signs a declaration that the information is true and complete and that the letter is not a substitute for a CO, and Buildings Bulletin 2015-026 adds that LNOs do not attest to the ability to operate a code-compliant business.
Figure 1: What an LNO Confirms, and What It Leaves Open
- DOB’s accepted use for the building or space named in the request
- That the use matches DOB’s records in zoning use group and occupancy group
- That the occupancy load and egress are substantially unchanged
- Replace a certificate of occupancy
- Allow a change of use group or occupancy group
- Permit or sign off construction work or a fire protection system
- Attest that a business can operate in compliance with the codes
- Exempt the building from retroactive fire safety requirements
An LNO is not a permit or a sign-off. Construction work still needs its own DOB permit or FDNY approval where the codes require one, and finished work closes with a Letter of Completion (LOC) or with a new or amended CO.
Where DOB Policy Provides for the Letter of No Objection
Administrative Code Section 28-101.5 defines a letter of completion but not a letter of no objection, so the LNO’s conditions come from DOB’s own documents: its LNO web page, the LNO/LOV form, the 2017 Code Notes, and Buildings Bulletin 2015-026. The code provisions underneath are Section 28-102.4, which lets the lawful use of an existing building continue unless a retroactive change is specifically required, and Section 28-118.3.5.
The form cites its change-of-use limit to Section 28-118.3.4, an earlier number for the pre-1938 provision; the current code numbers that provision 28-118.3.5, and 28-118.3.4 now covers changes to exits. The rule itself is plain: no LNO for a change of zoning use group or occupancy group, which needs an Alteration Type 1 (ALT-1) application, now the Alteration-CO job type in DOB NOW: Build, and a new CO.
DOB lists the LNO among requests that cannot currently be submitted in DOB NOW: Build. The request goes on the form to the DOB borough office for the property, and DOB’s LNO page points applicants to the DOB NOW Public Portal and the Building Information System (BIS) to check the building’s history first.
| Part of the request | What the LNO/LOV form asks for |
|---|---|
| Request type | LNO, or LOV where a CO exists and needs verification |
| Premises and parties | Address, block, lot and Building Identification Number (BIN), with owner and applicant details |
| Use | The current use, the proposed or actual use, and the agency requesting the letter |
| Use group test | Same zoning use group and occupancy group as the records, with occupancy load and egress substantially unchanged |
| Records | A Property Profile and list of job filings; block and lot folder plans or microfilm for a building without a CO; for 3 or more families or mixed use, a Department of Housing Preservation and Development (HPD) printout of the unit count and multiple dwelling registration number |
| Further proof of use | Department of Finance, Sanborn land-book or City archive records where proof of legal use is thin; for a non-conforming use, leases or utility bills showing it was not discontinued for more than 2 years |
| Child-related occupancies | Hours and dates of operation, the number of children under and over 2 years old, and a layout drawing of floors, exits and accessory spaces; a DOB field inspection may be needed |
| Bars to issuance | An open ALT-1, or an open application related to life safety, hazardous or work-without-a-permit violations |
| Fee and time | $25 for 1-, 2- and 3-family homes or $130 for all other buildings; about 3 weeks |
Source: DOB Letter of No Objection or Letter of Verification application form, revision 7/24, as of November 2026.
The form still notes one limited exception, Buildings Bulletin 2009-025 (December 1, 2009), which let a small ground-floor establishment of 74 persons or fewer switch between mercantile and business occupancy within the same zoning use group without a new or amended CO. DOB rescinded that bulletin in Buildings Bulletin 2023-012 (September 20, 2023), which lists it among documents no longer applicable under current codes and local laws.
DGA prepares FDNY fire alarm filings and DOB sprinkler and standpipe filings for existing New York City buildings, including buildings whose legal use rests on an LNO, and works across New York, New Jersey, Pennsylvania, Maryland and Delaware. Project briefs get confirmation and preliminary code feedback within one business day. See where DGA works →
Letter of No Objection vs Certificate of Occupancy vs Letter of Verification
The three documents fit different records. Administrative Code 28-118.3.1 bars occupying a building altered to another occupancy group or zoning use group until DOB issues a CO for the new use, and Section 28-118.3.2 requires a new or amended CO before any change inconsistent with the last CO. The LOV verifies a CO that exists, while the LNO covers a building with no CO or a use that differs from the CO within the same groups.
Figure 2: Which DOB Document Shows the Legal Use?
| Document | Issued by | What it confirms | When it applies |
|---|---|---|---|
| Letter of No Objection (LNO) | DOB borough office | DOB’s accepted legal use, without a CO | No CO is available, typically in a pre-1938 building, or the use differs from the CO or records within the same zoning use group and occupancy group (28-118.3.5; DOB form) |
| Certificate of occupancy (CO) | DOB | The lawful use and occupancy of the building or space | New buildings; a change of occupancy group or zoning use group (28-118.3.1); any change inconsistent with the last CO (28-118.3.2); a major alteration to existing exits (28-118.3.4) |
| Letter of Verification (LOV) | DOB borough office | That the existing CO is verified | A CO is available and an agency needs it verified (DOB form) |
| Letter of Completion (LOC) | DOB | Permitted work completed, including a satisfactory final inspection | Work that does not need a new or amended CO (28-101.5) |
| FDNY Letter of No Objection | FDNY | Requirements met, with conditions, where FDNY is not the main authority | A City agency asks FDNY to decide a matter outside the NYC Fire Code, on FDNY’s TM-1 plan examination application |
| Loft Board Letter of No Objection (LONO) | NYC Loft Board | That the Loft Board does not object to proposed work | DOB requires it for proposed work in the parts of an interim multiple dwelling (IMD) building that are not IMD spaces |
Section numbers are NYC Administrative Code Title 28, as of November 2026.
An owner of a pre-1938 building who wants a CO instead can apply under Administrative Code Article 118. The commissioner issues it if the building meets all applicable retroactive requirements of the 1968 Building Code, no notices of violation or orders are pending before DOB, and DOB establishes after inspection and investigation that the use has legally existed. Those retroactive requirements include fire safety systems (Section 28-102.4.1), so the CO route can raise fire protection work that an LNO request does not.
The FDNY and Loft Board letters share the name but not the job. FDNY’s letter is the outcome of a TM-1 review of a matter outside the NYC Fire Code that a City agency asked FDNY to decide, and the Loft Board’s letter clears proposed work in an IMD building; neither confirms legal use the way a DOB LNO does.
When Fire Protection Questions Come Up in a Letter of No Objection Request
Fire alarm work is one place the LNO comes up. Local Law 195 of 2018 moved fire alarm plan review from DOB to FDNY for filings on or after June 2, 2019, and FDNY’s 2019 frequently asked questions (FAQ) on Local Law 195 say fire alarm plans need a CO, an approved Schedule A (the occupancy schedule of a DOB job) or a DOB LNO, and add that the LNO will be required where the job’s address has no CO. DGA’s article on how FDNY TM-1 fire alarm filing works covers the rest of that application.
Occupancy classification is the second point. The 2022 NYC Building Code sets sprinkler requirements occupancy group by occupancy group in Sections 903.2.1 to 903.2.10, and Section 907.2 follows the same pattern for fire alarm systems, so the occupancy group an LNO holds steady is the input those sections turn on. A use that would move a space into another group, such as assembly, cannot rest on an LNO; it needs an Alteration-CO filing, and DGA’s guide to how NYC alteration types affect fire protection filings explains how that job carries the sprinkler and standpipe work.
For prior code buildings, Administrative Code 28-101.4.3 lets the owner use the 1968 Building Code for work on the building, but its exception 2 keeps fire protection systems for alterations and changes of use or occupancy under Building Code Chapter 9. The 1968 code option ends on July 17, 2027, when the NYC Existing Building Code (Local Law 33 of 2026) takes effect. Sprinkler and standpipe work on an Alteration-CO job goes through fire protection plan review at NYC DOB, and the new CO waits on the items in how a NYC temporary certificate of occupancy (TCO) or CO gets fire protection sign-offs.
Place of assembly use is a related limit. DOB requires a Place of Assembly Certificate of Operation (PACO) under Administrative Code 28-117.1 where 75 or more members of the public gather indoors or 200 or more outdoors, and Buildings Bulletin 2015-026 notes that a catering establishment with 75 or more persons becomes Group A-2 with its occupant load listed on a Certificate of Operation. An LNO is not a substitute for the PACO.
Open filings can hold up the letter. The form bars an LNO or LOV while an open ALT-1, or any open application related to life safety, hazardous or work-without-a-permit violations, is on record, and lets DOB deny a request until related applications are signed off. Open sprinkler and standpipe jobs appear in the building’s DOB job list, as do fire alarm jobs filed in BIS before June 2, 2019, which stayed with DOB for sign-off.
Retroactive requirements are the last point. Administrative Code 28-102.4 lets an existing lawful use continue unless a retroactive change is specifically required, and Section 28-102.4.1 holds prior code buildings to the applicable retroactive requirements of the 1968 Building Code, including fire safety and building safety systems and their verifying reports. An LNO changes neither duty.
Key Takeaway: A NYC Letter of No Objection is DOB’s statement of accepted use for a building or space with no CO, typically one built before January 1, 1938, or with a use that differs from its CO within the same zoning use group and occupancy group. It is requested from the DOB borough office, takes about 3 weeks as of November 2026, is not a substitute for a CO, and neither approves fire protection work nor removes a retroactive requirement.
Frequently Asked Questions
Does an LNO replace a certificate of occupancy?
No. The applicant signs a statement on DOB’s form that the letter is not a substitute for a CO, and DOB’s Code Notes say the same. The owner of a pre-1938 building who needs a CO applies for one under Administrative Code Article 118, which requires compliance with the applicable retroactive requirements of the 1968 Building Code.
Can an LNO allow a change of use?
Conditional: only where the new use stays in the same zoning use group and the same Building Code occupancy group, with the occupancy load and egress substantially unchanged. A change of use group or occupancy group needs an Alteration-CO filing and a new CO under Administrative Code 28-118.3.1. DOB’s form still mentions a limited exception under Buildings Bulletin 2009-025, but DOB rescinded that bulletin in 2023.
Does an LNO require sprinklers?
No. The LNO itself adds no sprinkler requirement, because it confirms a use that is not changing. Sprinklers come from the codes that already apply to the building, such as the retroactive requirements under Administrative Code 28-102.4.1, and from Building Code Chapter 9 when an alteration or change of occupancy is filed. DOB’s Buildings Bulletin 2015-026 states that LNOs do not attest to the ability to operate a code-compliant business.
Does FDNY accept a DOB LNO with a fire alarm filing?
Yes. FDNY’s 2019 Local Law 195 FAQ says fire alarm plans need a CO, an approved Schedule A or a DOB Letter of No Objection, and that the LNO is required where the job’s address has no CO. The letter is submitted with the TM-1 fire alarm application.
How long does a DOB Letter of No Objection take?
About 3 weeks, according to DOB’s LNO/LOV form (revision 7/24), as of November 2026. The fee on the form is $25 for 1-, 2- and 3-family homes and $130 for all other buildings, and the request goes to the DOB borough office rather than DOB NOW: Build. DOB may ask for more proof of use, and child-related occupancies may need a field inspection.
More in Approvals by Jurisdiction
- How Does AHJ Review Work in NYC, NJ and Philadelphia?
- How Do Pittsburgh Fire Protection Approvals Work?
- How Do Federal Agencies Review Leased-Space Fire Protection?
- What Is Maryland’s Sprinkler Law for New Homes?
- Does the Pennsylvania Fire and Panic Act Still Apply?
- What Does NYC Require for Construction Site Fire Safety?
This article is general information, not a substitute for a project-specific code analysis. DOB forms, bulletins and agency practice change; confirm the current requirements with DOB and FDNY for the building.
Proving Legal Use Before a Fire Protection Filing?
Send the address, the use the agency or FDNY is asking about, and any CO or job history on record. DGA reviews the building’s records against the LNO conditions and sets out what an LNO or an Alteration-CO path means for the sprinkler, standpipe and fire alarm filings. Project briefs get confirmation and preliminary code feedback within one business day.