How Do You Respond to an FDNY Plan Exam Objection?

General guidance, not a code determination for any project. Confirm the adopted code and local amendments with the authority having jurisdiction.

An FDNY plan exam objection is answered by correcting each item on the objection letter, writing a response that answers every item by number, and resubmitting the revised sealed documents on FDNY Business, which is free within six months of the Letter of Deficiency. The Fire Department of the City of New York (FDNY) issues the objection when its plan examiner finds that a fire alarm, in-building auxiliary radio communication system (ARCS), non-water suppression or other FDNY-reviewed submission does not yet show compliance. Under the 2022 New York City Fire Code (FC) Section 105.4, those design documents run on the same clocks as permit applications: FDNY must act within 40 calendar days of each complete submission (FC 105.2.4), and an application not diligently pursued is deemed abandoned 180 calendar days after filing (FC 105.2.3).

An objection is a request for revision, not a rejection of the project. Most objections trace to a small set of document problems that FDNY itself has published, and a specific, complete response gives the examiner what is needed to accept the plans in the next round. This article covers what the objection means, the causes FDNY lists, the response step by step, the deadlines and how to avoid objections on the next filing.

At a Glance: An FDNY Plan Exam Objection

  • What the notice or finding means: FDNY’s plan examiner has marked the application “Revision Required” and issued a Letter of Deficiency (also called an objection letter) listing what must change before FDNY issues a Letter of Acceptance.
  • Top 3 causes: occupancy documents that do not match the drawings (no Certificate of Occupancy or approved Schedule A, or floor designations that differ); drawings that disagree with themselves (riser counts, legend, input/output matrix); and missing supporting approvals (the existing system’s Letter of Approval, variance letters, Construction Code Determinations).
  • Response deadline (cited): resubmission is free within six months of the Letter of Deficiency (FDNY Business, as of November 2026); FC 105.2.3 deems an application abandoned 180 calendar days after filing unless it is diligently pursued, with 90-day extensions available for reasonable cause.
  • Who can fix it: the applicant of record on the TM-1, FDNY’s plan examination application (a Professional Engineer (PE), Registered Architect (RA), owner or building manager), with revised fire alarm plans sealed by a New York State registered design professional and filed by the applicant or an FDNY-registered filing representative.
  • Time to resolve: as of November 2026, FC 105.2.4 gives the department 40 calendar days to act on each submission, so each objection round can add up to 40 calendar days of review, or 80 if the commissioner extends the period for good cause, plus the design team’s revision time.
  • What happens if ignored: the application is treated as abandoned after six months or under FC 105.2.3, a new filing fee may apply, and the system cannot lawfully be installed or altered without approved documents (FC 105.4.3), which holds up the inspection, the FDNY Letter of Approval and the certificate of occupancy.

What Does an FDNY Plan Exam Objection Mean?

An FDNY plan exam objection is the plan examiner’s written finding that a submission cannot be accepted as filed. On FDNY Business, the City’s online filing portal, a fire alarm application comes back with one of four results, and an objection is the second of them. The table lists the four results and what each requires next.

FDNY Business resultWhat it meansNext step
Letter of AcceptanceThe application is approved; FDNY returns a stamped TM-1 and stamped plans.Request a Project Authorization on FDNY Business before work starts.
Revision RequiredThe application is not approved; FDNY issues a Letter of Deficiency with directions. Older FDNY forms call the same document an objection letter.Revise, respond item by item and resubmit; free within six months.
Additional Information RequestFDNY needs more documents or details before it can process the application.Upload what was asked for; no design change may be needed.
Application Not RequiredThe application was filed incorrectly or is not needed.Follow the instructions in FDNY’s email response.

Results as listed on the NYC Business fire alarm application page, as of November 2026. FDNY engineering applications can also end in a Conditional Letter of Acceptance, a Letter of No Objection or a Site Visit Request.

FDNY reviews these documents because Local Law 195 of 2018 moved review of fire alarm, emergency alarm, ARCS, fire protection plan and non-water extinguishing system documents, including commercial cooking systems, from the Department of Buildings (DOB) to FDNY for filings from June 2, 2019. The filing form is the TM-1, FDNY’s application for plan examination and document review. Sprinkler and standpipe work stays with DOB, so an objection on a sprinkler filing is a DOB objection handled under DOB’s process; DGA’s guide to how fire protection plan review works at NYC DOB covers that side, and the split between the two agencies is laid out in DOB or FDNY: who approves what in New York City.

The legal footing for the objection is FC 105.4. Design and installation documents that FDNY must review are checked for compliance with the Fire Code, its rules and the construction codes, and FC 105.4.4 has the department approve, deny or preliminarily deny them on the FC 105.2.4 timetable. For fire alarm work the design standard behind most objections is 2022 NYC Building Code (BC) Section 907, which requires design and installation to National Fire Protection Association (NFPA) 72, the National Fire Alarm and Signaling Code, 2016 edition, as modified by Appendix Q of the Building Code.

What Causes Most FDNY Plan Exam Objections?

FDNY published its own list of the errors that draw objections. Its October 2020 guide, Tips for Successful Approval of a Fire Alarm System in NYC, includes a section titled How To Avoid Fire Alarm Plan Review Objections, and most items in it concern documents rather than engineering. The table groups the recurring causes, how each shows up on the objection letter, and the fix.

ObjectionHow to tellFix
No Certificate of Occupancy (CO) or approved Schedule A, or the use on the drawings differs from itThe letter asks for the CO or Schedule A, or notes that a space shown on the plans is not the use on file.Upload the CO or approved Schedule A; where neither exists, obtain a DOB Letter of No Objection (LNO) and upload it.
Floor designations do not matchFloor numbers on the TM-1, riser diagram and floor plans differ from the CO, often because the building uses marketing floor numbers.List construction floors from the CO on the TM-1, state how they map to marketing floors in the job description, and show both on the plans, per FDNY Technology Management Bulletin 11/2011.
TM-1 job description does not match the drawingsThe scope on the TM-1 is narrower or broader than the work shown.Rewrite the job description to match the drawings exactly, and file a new signed TM-1 with the resubmission.
Existing system approval missingThe filing adds to or modifies an existing system, and the letter asks for its Letter of Approval.Upload the FDNY Letter of Approval for the existing or base building system the new devices connect to.
Riser and floor plans disagreeDevice counts on the riser differ from the plans, symbols are missing from the legend, or panels and power supplies are not located.Reconcile counts floor by floor, define every symbol, and show the control panel or fire command station, data gathering panels, power supplies and every device.
Input/output matrix is genericThe matrix lists functions the system does not have or leaves out the ones it does.Replace it with a matrix written for the actual system, with only the functions it performs.
Variances and code determinations not in the setThe design relies on an FDNY variance or a DOB Construction Code Determination (CCD1) that the examiner cannot see.Embed the variance letter or CCD1 in the drawings and cite it where it applies.
Area data missingA requirement depends on floor or room area (for example smoke detection in electrical rooms) and no square footage is given.Add room and floor areas, or fire area totals, to the plans so the examiner can check the threshold.
Seal, legibility or supporting formsPlans are unreadable, the digital seal is missing or defective, or asbestos (ACP-5) or landmark documents are absent.Reissue legible plans with a compliant digital seal and signature, and add the Department of Environmental Protection (DEP) asbestos form or landmark approval that applies.

Causes summarized from FDNY’s Tips for Successful Approval of a Fire Alarm System in NYC (10/2020), section How To Avoid Fire Alarm Plan Review Objections. The guide states that it does not cover every filing requirement.

FDNY’s plan review items fall into three groups. Occupancy documents come first because FDNY reviews the fire alarm against the legal use of the building, so a plan that does not match the CO cannot be checked. Internal disagreement within the set is the second group, and missing supporting approvals the third. The guide’s separate list, General Tips to Avoid Defects, covers inspection items such as fan shutdown and elevator recall on alarm, but most plan review items concern documents.

How to Respond to an FDNY Objection, Step by Step

The response to an FDNY objection works best as one complete package. FDNY’s guide says to address every objection before resubmitting, and to contact the plan examiner first where the design team disagrees with one. The steps below follow that order.

  1. Read the whole letter and number every item. Note the issue date on the Letter of Deficiency, since the six-month free resubmission window runs from it, and record the plan examiner’s name and phone number, which FDNY prints on fire alarm objection letters.
  2. Sort each item: comply, clarify or contest. Many items are straight corrections. Some ask for information already in the set, and a few ask for something the design team believes the code does not require. The decision tree below shows how to sort them.
  3. Call the plan examiner on any item in dispute. A short call before resubmitting settles misreadings and confirms what the examiner needs, which lowers the risk of a second objection on the same item.
  4. Revise the drawings and cloud every change. Revised fire alarm plans are resealed and signed by the New York State registered design professional, with revision clouds and a revision number so the examiner can find each change.
  5. Write the response matrix. List every objection by number with the response and the sheet revised (example below), and send it as the cover or transmittal letter that explains the revised sections.
  6. Assemble the supporting documents. Add whatever the objections asked for: CO or Schedule A, DOB LNO, prior Letter of Approval, variance letter, CCD1, DEP asbestos form or landmark approval, plus a new signed TM-1 if the job description changed.
  7. Resubmit on FDNY Business. Upload the revised plans, the response letter and the supporting documents inside the six-month window.

The response matrix carries the whole response in one page. The example below shows the format for a hypothetical tenant fit-out filing; the objection numbers and sheet numbers are placeholders.

Objection no.Objection (paraphrased)ResponseSheet revised
1Provide CO or approved Schedule A for the floors in scope.Approved Schedule A uploaded as a supporting document; use on floors 10 and 11 matches the plans.None (document added)
2Floor numbers on the riser do not match the CO.Riser and plans now show construction floors 10 and 11 with marketing floors 12 and 14 in brackets; TM-1 job description revised to state the mapping.FA-001, FA-101, FA-102; new TM-1
3Device count on the riser does not match floor 11.Two missing strobes added to the floor 11 plan; riser quantities reconciled for both floors.FA-001, FA-102
4Provide the Letter of Approval for the base building system.Base building Letter of Approval uploaded; connection point to the existing data gathering panel noted on the riser.FA-001
5Input/output matrix lists stair pressurization, which the building does not have.Matrix rewritten for the installed functions only (fan shutdown, elevator recall, door release).FA-201

The filing steps that come before the objection, and the Project Authorization and inspection that come after acceptance, are covered in DGA’s guide to how FDNY TM-1 fire alarm filing works.

Figure 1: Comply, Clarify or Contest?

One item on the FDNY Letter of Deficiency
Is the objection correct on the code and on the drawings as filed?
YesComplyRevise and cloud the sheet, reseal, and list the change in the response matrix
No or unsureGo to the next questionCall the plan examiner named on the letter before resubmitting
Is the requested information already in the set, or did the examiner read the scope differently?
YesClarifyPoint to the sheet and note in the response matrix; add a note or detail if it helps
NoThe design departs from the codeDecide whether to comply or to seek relief
Is there a code basis for the departure?
Fire Code itemRequest a modificationWritten request under FC 104.8 or an alternative system under FC 104.9, filed on FDNY Business as a Fire Code Modification (Variance); fire alarm and ARCS relief is requested as a Fire Alarm Variance (Form TM-4)
Building Code itemRequest a DOB CCD1Embed the determination in the drawings once issued
Final denialAppealBoard of Standards and Appeals under Charter Section 666
FDNY’s guide to avoiding fire alarm plan review objections (10/2020) asks applicants to address every objection before resubmitting and to contact the plan examiner first on any item they dispute. Relief from a Fire Code requirement is a written modification request under 2022 NYC Fire Code Section 104.8, and the Board of Standards and Appeals hears appeals from determinations of the fire commissioner under New York City Charter Section 666.

Opens the Project Desk with your sentence. Our licensed PEs review every brief and reply within one business day.

Can an FDNY Objection Be Appealed?

An FDNY objection can be contested, but the routes are formal and slower than a revised drawing. The first route is the plan examiner: FDNY’s own guidance is to call the examiner on any item in dispute, and the call can settle a misreading once the examiner sees the sheet or the code section the design relies on.

The second route is a modification. Under FC 104.8, the fire commissioner may waive or modify a Fire Code provision where unusual conditions make full compliance impracticable, on a written request that states the grounds, and FC 104.9 lets the commissioner approve an alternative device, equipment or system that is at least equivalent. On FDNY Business a Fire Code modification is filed as a Fire Code Modification (Variance), which FDNY limits to the Fire Code and its rules; fire alarm and ARCS relief is requested as a Fire Alarm Variance on Form TM-4, and a Building Code departure that needs DOB approval goes to DOB as a CCD1. A modification request does not stay enforcement of the provision while it is pending (FC 104.8.1.3).

The third route is the Board of Standards and Appeals (BSA). New York City Charter Section 666 gives the BSA authority to hear appeals from any order, requirement, decision or determination of the fire commissioner. A BSA appeal is a separate proceeding with its own filing and schedule, so it suits a final denial on a point of real consequence, not a routine objection.

What Are the Deadlines, and What Happens If the Application Lapses?

Two sets of deadlines apply to an FDNY objection. The first is FDNY’s fee rule: the NYC Business application pages say resubmission is free within six months of the Letter of Deficiency, a new filing fee may be required after six months, and FDNY’s engineering application page treats the application as abandoned after that point. As of November 2026 the plan examination fee is $420 per application.

The second set comes from the Fire Code. FC 105.4 applies FC 105.2.3 and 105.2.4 to design and installation documents. FC 105.2.3 deems an application abandoned 180 calendar days after filing unless it has been diligently pursued or an approval has been issued, and the commissioner may grant extensions of up to 90 calendar days each for reasonable cause. FC 105.2.4 requires the department to approve, or to deny or preliminarily deny with written grounds, within 40 calendar days of each submission, and lets the commissioner extend the approval period once by 40 days for good cause.

Figure 2: From Objection to Letter of Acceptance

Day 0: Letter of DeficiencyFDNY Business shows Revision Required with the Letter of Deficiency; the six-month free window starts on the letter’s issue date.
First days: Sort and callEach item is sorted into comply, clarify or contest, and disputed items go to the plan examiner by phone.
Revision: Plans and responseChanges are clouded and resealed, and the response matrix answers every item by number.
Resubmission: FDNY BusinessRevised plans, response letter and supporting documents go up together, inside six months to avoid a new fee.
Up to 40 calendar days: FDNY actsFC 105.2.4 gives the department 40 calendar days to accept or object again with written grounds.
Acceptance: Letter of AcceptanceFDNY returns the stamped TM-1 and plans, and a Project Authorization can be requested.
Resubmission is free within six months of the Letter of Deficiency, FDNY has 40 calendar days to act on each submission under 2022 NYC Fire Code Section 105.2.4, and Section 105.2.3 deems an application abandoned 180 calendar days after filing unless it is diligently pursued.

An application that lapses costs more than a fee. FC 105.4.3 makes it unlawful to install, alter or remove a system whose documents FDNY must review before those documents are approved, so work cannot start on an unanswered objection. Without the Letter of Acceptance there is no Project Authorization, no inspection and no FDNY Letter of Approval, and DOB’s certificate of occupancy worksheet lists FDNY fire alarm approval among its required items. For a schedule estimate that includes review rounds, DGA’s Fire Protection Project Timeline Estimator gives a starting range.

A plan exam objection is also different from a Notice of Defect. The objection comes before work is authorized and concerns the documents; a Notice of Defect, formerly called a Letter of Defect, comes after a failed inspection and concerns the installed system. DGA’s article on what an FDNY Letter of Defect is and how it is cleared covers that later stage.

How to Prevent FDNY Objections on the Next Filing

Preventing FDNY objections starts with the occupancy documents. Before the drawings are finished, the design team should have the CO or approved Schedule A in hand, match the floor designations to it, and, where the building has no CO, obtain the DOB LNO early, since it comes from a separate DOB process.

The second habit is a self-check against FDNY’s published list. A reviewer who did not draw the set should compare riser counts with each floor plan, confirm that every symbol appears in the legend, read the input/output matrix against the actual sequence of operation, and check that the TM-1 job description matches the drawings word for word.

The third habit is to put every approval the design relies on into the set: the existing system’s Letter of Approval, any FDNY variance letter, any DOB CCD1, and the asbestos and landmark documents that apply. An examiner who cannot see an approval has to object to the condition it covers.

The fourth habit is to file R-2 residential fire alarm work separately from other occupancy groups and, where the fire alarm was approved at DOB on a PW-1 before Local Law 195 moved review to FDNY, to open a DOB Post-Approval Amendment (PAA) before filing an FDNY amendment. Both points appear in FDNY’s guidance and both produce objections that have nothing to do with the design itself.

Key Takeaway: An FDNY plan exam objection is a Letter of Deficiency asking for revisions before FDNY issues a Letter of Acceptance. The fix is to sort every item into comply, clarify or contest, call the plan examiner on disputed items, revise and reseal the drawings, answer each objection by number in a response matrix, and resubmit on FDNY Business within six months of the letter, when resubmission is free. Under 2022 NYC Fire Code Sections 105.2.3, 105.2.4 and 105.4, FDNY must act within 40 calendar days of each complete submission and an application not diligently pursued is deemed abandoned 180 calendar days after filing.

Frequently Asked Questions

Is an FDNY objection the same as a Letter of Defect?

No. A plan exam objection, issued as a Letter of Deficiency, concerns the documents before FDNY accepts the plans. A Notice of Defect, formerly called a Letter of Defect, is issued after a fire alarm system fails its FDNY inspection, and most items on it are cleared by correcting them and filing Form FA-26 within 90 days.

How long is there to respond to FDNY objections?

Six months for a free resubmission. FDNY’s application pages say resubmission costs nothing within six months of the Letter of Deficiency and that a new filing fee may be required after that. Separately, 2022 NYC Fire Code Section 105.2.3 deems an application abandoned 180 calendar days after filing unless it is diligently pursued, with extensions of up to 90 calendar days each for reasonable cause.

Can an FDNY plan exam objection be appealed?

Conditional: a disputed objection is first raised with the plan examiner named on the letter, and relief from a Fire Code requirement is requested in writing as a modification under 2022 NYC Fire Code Section 104.8. A final determination of the fire commissioner can be appealed to the Board of Standards and Appeals under New York City Charter Section 666.

Who should write the response to an FDNY objection?

The design professional who sealed the plans, on behalf of the applicant of record on the TM-1. Revised fire alarm plans must be sealed and signed by a New York State registered design professional, and the resubmission is filed on FDNY Business by the applicant or an FDNY-registered filing representative.

This article is general information, not a substitute for a project-specific review. FDNY procedures, forms, fees and code requirements change; confirm current requirements with FDNY and the authority having jurisdiction for the project.

Holding an FDNY Objection Letter?

Send the Letter of Deficiency, the filed TM-1 and the plan set. DGA sorts each item, revises and reseals the drawings, writes the response matrix and prepares any modification request the design needs. Project briefs get confirmation and preliminary code feedback within one business day.

Send a Project Brief → View FDNY Approvals

Leave a Reply

Your email address will not be published. Required fields are marked *

Quick inquiry

Ready when you are.

Your name, a way to reach you, and where the project is. One of our licensed PEs replies within one business day. No sales calls.

Prefer to describe it first? Open the Project Desk