Approvals by Jurisdiction · Process

How Do You Get a Place of Assembly Certificate in NYC?

General guidance, not a code determination for any project. Confirm the adopted code and local amendments with the authority having jurisdiction.

A Place of Assembly Certificate of Operation (PACO) in New York City is issued by the Department of Buildings (DOB) after a registered design professional files a place of assembly application in DOB NOW: Build, DOB approves the layout, and a DOB inspector confirms the finished space matches it; the certificate is required wherever 75 or more members of the public gather indoors or 200 or more gather outdoors. Within 1 year of the PACO, the same space needs a permit from the Fire Department of the City of New York (FDNY), which FDNY renews every year after its own inspection.

The legal requirement is Section 28-117.1 of the NYC Administrative Code (Title 28, Article 117, Places of Assembly), which makes it unlawful to use a building or outdoor space as a place of assembly without a certificate of operation. This article walks the filing from the threshold check to the annual FDNY permit, with the documents, the review clock, the reasons DOB sends applications back and what an operator must keep doing after the certificate is posted.

At a Glance: NYC Place of Assembly Certificate of Operation

  • Who files: a Registered Architect (RA) or Professional Engineer (PE) files the place of assembly application with DOB as applicant of record; the owner or operator then obtains the FDNY permit.
  • Where it is filed: DOB, through DOB NOW: Build, as a place of assembly (PA) filing that references the New Building or Alteration job for the space; the FDNY Public Assembly Permit is issued by FDNY, which inspects the space.
  • Documents required: PA floor plans showing seating, tables and other movable furnishings, egress paths, occupant loads and emergency lighting; a certificate of occupancy (CO) that authorizes the assembly use; FDNY approvals for the fire alarm and, at 300 or more occupants, the fire protection plan; flame spread letters for finishes and furnishings where they apply.
  • Timeline range (as of November 2026): Administrative Code 28-104.2.7 gives DOB 40 calendar days to approve complete, code-compliant construction documents, extendable once by 20 days for good cause; the FDNY permit is due within 1 year of the PACO; a temporary certificate is filed at least 10 business days before the event.
  • Most common rejection: a layout whose occupant load or use is not authorized by the building’s CO, which DOB cannot approve until the CO is amended.
  • Approval document: the DOB Place of Assembly Certificate of Operation, framed and posted in the space, followed by the FDNY Public Assembly Permit, valid for up to 1 year and renewed after each annual FDNY inspection.

What Is a Place of Assembly Certificate of Operation, and When Is It Required?

A PACO is DOB’s certificate that an assembly space was built to approved plans and may operate at a stated capacity. Administrative Code 28-117.1 bars the use of any building or space, including an outdoor space, as a place of assembly without one. Under the same section, DOB inspects every place of assembly before issuing the certificate and will not issue it unless the space conforms substantially to the approved construction documents and the CO authorizes the use.

DOB’s PACO page sets the trigger: 75 or more members of the public gathering indoors, or 200 or more outdoors, for religious, recreational, educational, political or social purposes, or to eat or drink. The 2022 NYC Building Code (BC) applies the same line to residential rooftops and terraces: footnote d to Table 1004.1.3 requires a PACO under 28-117.1 where a rooftop or terrace accessory to a Group R-2 or R-3 building has a calculated occupant load over 74 persons. DOB’s project guidance also treats rooftop and open spaces 20 ft or more above or below grade as indoor spaces for the threshold.

The count that matters is the occupant load the design professional calculates under BC Chapter 10 and DOB approves, not the number of seats the operator plans to sell. A restaurant, bar, event space, house of worship, gym studio or school auditorium can cross the line with a modest floor area once tables come out and standing space goes in.

Figure 1: When a NYC Assembly Space Needs a Certificate

  1. 300+Assembly occupancy of 300 or morePACO and FDNY permit, plus a fire protection plan under Administrative Code Article 109, approved by FDNY
  2. 200+Outdoor space, 200 or more peoplePACO required for the outdoor place of assembly
  3. 75+Indoor space, 75 or more peoplePACO from DOB, then an FDNY Public Assembly Permit within 1 year
  4. 74Indoor space, 74 or fewerNo PACO; the space operates under its CO
A PACO is required at 75 or more members of the public indoors (including a residential rooftop or terrace with a calculated occupant load over 74) and at 200 or more outdoors, under Administrative Code 28-117.1. At an assembly occupant load of 300 or more, the building also needs a fire protection plan under Administrative Code Article 109, which FDNY approves.

Who Files and Where: DOB First, Then FDNY

The place of assembly application goes to DOB, not FDNY. A registered design professional files it in DOB NOW: Build as its own application, and DOB’s guidance requires it to reference the New Building or Alteration job that covers the physical work in the space. Sprinkler, standpipe, plumbing, mechanical and other building systems are filed separately under that job, and DOB reviews both the construction and the PA applications for code and zoning compliance.

FDNY comes in at three points. The fire alarm system and, where required, the fire protection plan are reviewed and approved by FDNY, and DOB’s PA guidance lists those FDNY approvals among the documents needed at intake. Before occupancy, 2022 NYC Fire Code (FC) Section 407.4 requires the Building Code seating plan for a Group A space to be submitted electronically to FDNY, with a copy kept on the premises. After the PACO issues, the operator obtains FDNY’s own permit to maintain or operate the place of assembly under FC Section 105.6.

The split between the two agencies is the same one that runs through every NYC fire protection approval, and DGA lays it out in detail in its guide to which approvals sit with DOB and which with FDNY in New York City. DOB’s own PACO page calls the FDNY document a Place of Assembly Permit; FDNY’s permit page calls it a Public Assembly Permit.

Steps to a Place of Assembly Certificate

The sequence below follows DOB’s PACO and design professional guidance. The PA application can be filed during the construction job or after it, but the certificate cannot issue until the space is built, inspected and covered by a CO that allows the use.

  1. Confirm the threshold and the CO. The design professional calculates the occupant load under BC Chapter 10 and checks the building’s CO or Schedule of Occupancy. If the CO does not authorize assembly use at that load, an Alteration-CO job (DOB’s job type for a change of use or occupancy) comes first, because 28-117.1 ties the PACO to a CO that authorizes the use.
  2. File the construction work. Physical work in the space is filed as a New Building or Alteration job in DOB NOW: Build, with the sprinkler and standpipe work filed as their own work types. DGA’s article on how DOB reviews sprinkler and standpipe filings covers that track.
  3. Obtain the FDNY approvals. The fire alarm filing goes to FDNY, and a building with an assembly occupancy of 300 or more needs a fire protection plan under Administrative Code Article 109, which FDNY approves. DOB’s PA guidance lists these approvals among the documents needed at intake.
  4. File the PA application. The RA or PE files the place of assembly application in DOB NOW: Build, referencing the construction job, with the PA plan set described in the documents table below. The applicant may have DOB examine the plans or may professionally certify that the design complies, and certified applications can be audited.
  5. Clear objections and get approval. DOB’s plan examiner either approves the layout or issues objections, which the applicant answers with revised drawings. Changes are bubbled, numbered and dated so the examiner can find them.
  6. Build, sign off and pass the PA inspection. When the PA application is filed during the construction job, DOB can hold the final construction inspection and the PA inspection together; when it is filed later, DOB runs a separate PA inspection. The inspector checks the built space against the approved PA plans.
  7. Post the certificate and send the seating plan to FDNY. DOB issues the PACO after the PA inspection passes. Administrative Code 28-117.1.1 requires the certificate, which states the number of persons who may legally occupy the space, to be framed and mounted where it is conspicuous to anyone entering, and DOB requires the Building Code capacity sign to be posted before the space operates. The seating plan goes to FDNY under FC 407.4 before occupancy.
  8. Obtain the FDNY Public Assembly Permit. DOB’s PACO page requires the FDNY permit within 1 year of the PACO issuance date. FDNY’s permit page lists the PACO, the DOB-approved floor or seating plans and copies of the required Certificates of Fitness as the documents for the permit inspection.

Figure 2: From PA Filing to FDNY Permit

PA filingRA or PE files the place of assembly application in DOB NOW: Build, referencing the New Building or Alteration job; FDNY fire alarm and fire protection plan approvals in hand where required.
Plan approvalDOB plan examination or professional certification; 40 calendar days for complete, compliant documents under Administrative Code 28-104.2.7, extendable by 20 days.
InspectionConstruction signed off; DOB PA inspection, combined with the final construction inspection or run separately, checks the space against the approved PA plans.
CertificateDOB issues the PACO; certificate framed and posted, capacity sign up, seating plan submitted to FDNY under FC 407.4.
FDNY permitFDNY Public Assembly Permit within 1 year of the PACO, valid for up to 1 year and renewed after each annual FDNY inspection.
A NYC place of assembly moves through 5 stages: the DOB filing, DOB plan approval (40 calendar days for complete documents under Administrative Code 28-104.2.7), the DOB inspection, issuance and posting of the PACO, and the FDNY Public Assembly Permit, which must follow within 1 year and is renewed annually.

Opens the Project Desk with your sentence. Our licensed PEs review every brief and reply within one business day.

Which Drawings and Documents Does a PA Filing Need?

DOB’s design professional requirements for places of assembly ask for a dedicated PA plan set, with “PA” as the sheet designator for the place of assembly floor plans. The establishment layout shows a primary arrangement for the largest expected occupant load and up to two alternate arrangements, each with every fixed and movable seat, table and chair, the accessible seating count and locations, travel paths to the required exits and the maximum travel distances.

The floor plans also carry room names and areas, occupant loads, egress widths and calculations, emergency lighting with fixture spacing, door tags and a code analysis. The table lists the documents a complete application carries and who prepares each one.

DocumentWho prepares it
PA floor plans: primary layout and up to 2 alternates, with seating, tables, movable furnishings and accessible seatingRA or PE of record
Life safety information: occupant loads, egress widths and calculations, travel distances, exits and door tagsRA or PE of record, often with a fire protection engineer
Emergency lighting layout and exit signsRA or PE of record, coordinated with the electrical engineer
CO or Schedule of Occupancy that authorizes the assembly use and occupant load (Administrative Code 28-117.1)Owner, from DOB records; applicant checks it before filing
Reference to the New Building or Alteration job for the spaceRA or PE of record, in DOB NOW: Build
FDNY fire alarm approvalFire alarm designer files with FDNY; FDNY issues the approval
FDNY-approved fire protection plan (assembly occupancy of 300 or more)Registered design professional under Administrative Code Article 109; FDNY approves
Manufacturer flame spread letters for carpet, window treatments, wall coverings, foam and upholsteryOwner or interior designer, from the manufacturers
Seating plan submitted to FDNY before occupancy (FC 407.4)Owner or applicant, from the DOB-approved plan

How Long Does a PA Certificate Take, and What Delays It?

As of November 2026, Administrative Code 28-104.2.7 requires DOB to approve complete, code-compliant construction documents and notify the applicant no later than 40 calendar days after a complete application is submitted, with one 20-day extension for good cause. The clock runs on complete applications only. Under 28-104.2.3, an application is deemed abandoned 12 months after submission unless it is pursued after rejection, and DOB can treat an incomplete application as abandoned 90 days after notifying the applicant.

The PA review is only one part of the schedule. The certificate also waits for the construction job to be signed off, for the DOB inspection, and for FDNY’s fire alarm and fire protection plan approvals. As of November 2026, FC 105.2.4 and FC 105.4 give FDNY 40 calendar days from each submission to approve the fire alarm documents or to deny or preliminarily deny them with written grounds, and the commissioner may extend the approval period once by 40 days for good cause. A CO that does not authorize the assembly use adds an entire Alteration-CO job ahead of the PACO.

Three other things commonly add weeks: a layout changed in the field after approval needs a post-approval amendment before the inspection can pass, missing flame spread letters or FDNY approvals stall intake, and an inspection requested before the construction work is signed off is wasted. The Fire Protection Project Timeline Estimator gives a dated range for a NYC project with these steps.

Why Are PA Applications Rejected?

The rejection reasons below follow from DOB’s PACO and design professional requirements, and most involve documents that do not agree with each other or with the building’s records. Each fix brings the filing back in line with those requirements.

Rejection reasonFix
Occupant load or use on the PA plans is not authorized by the COAmend the CO first through an Alteration-CO job, or reduce the layout to the load the CO allows; 28-117.1 bars a PACO unless the CO authorizes the use.
PA application does not reference the New Building or Alteration jobLink the PA filing to the construction job number in DOB NOW: Build, as DOB’s guidance requires.
Layout shows a single arrangement, or omits movable furnishings or accessible seatingShow the primary layout for the largest expected load and each alternate, with every seat, table and chair and the accessible seating count and locations.
Egress widths, travel distances or occupant loads missing from the plansAdd the life safety information to the PA floor plans: occupant load per room, egress capacity calculations, travel paths and maximum distances.
FDNY fire alarm or fire protection plan approval not on fileObtain the FDNY approval and upload it; for an assembly occupancy of 300 or more, the fire protection plan under Administrative Code Article 109 is part of the package.
Built space differs from the approved PA plans at inspectionFile a post-approval amendment for the change before reinspection; DOB treats seating rearrangements, egress changes and occupant load increases as substantive changes.

After Approval: Annual FDNY Permit and Changes in Layout

Administrative Code 28-117.1 requires seating and other movable furnishings to be kept in line with the approved plan at all times during occupancy, and any amendment of that plan needs DOB’s prior approval. DOB’s PACO page sets two levels of change. A change of zoning use group or of assembly occupancy group (A-1 to A-5) needs a new PACO; a change to the seating and furnishings plan or to the establishment’s name needs an amended PACO. For a certificate issued before DOB’s Buildings Information System (BIS), DOB’s page requires a new PACO for any of those changes.

FDNY’s side is annual. FDNY’s permit page lists the Public Assembly Permit under FC Section 105.6 with a term not to exceed 1 year and a fee that varies with the number of occupants, and DOB’s page says the permit expires annually and is renewed based on FDNY’s annual inspection. The approved PA plans should be on site for that inspection.

FDNY’s permit page also lists the Certificates of Fitness it expects to see, such as F-03 (Indoor Place of Assembly Safety Personnel), F-04 (Temporary Indoor/Outdoor Place of Assembly Safety Personnel), S-95 (Supervision of Fire Alarm Systems) and F-01 (Citywide Fire Guard for Impairment) where required. When the building later seeks a new or amended CO, DOB’s CO worksheet expects the place of assembly inspection to show Final-Passed, and DGA’s guide to how a NYC temporary or final certificate of occupancy gets its fire protection sign-offs covers the rest of that list.

Restaurants, bars, event venues and hotel function rooms are typical places of assembly, and DGA’s work in that sector is described on its hospitality and entertainment page.

Key Takeaway: A NYC Place of Assembly Certificate of Operation is a DOB approval under Administrative Code 28-117.1 for any space where 75 or more members of the public gather indoors or 200 or more outdoors. A registered design professional files it in DOB NOW: Build against the construction job, DOB approves the layout and inspects the space, and the CO must already authorize the use. Within 1 year the operator needs an FDNY Public Assembly Permit, renewed every year after FDNY’s inspection.

Frequently Asked Questions

How many people make a space a place of assembly in NYC?

75 or more members of the public gathering indoors, or 200 or more outdoors, per DOB’s Place of Assembly Certificate of Operation page. A rooftop or terrace accessory to a Group R-2 or R-3 building with a calculated occupant load over 74 also needs a certificate under 2022 NYC Building Code Table 1004.1.3, footnote d.

Is a PA certificate the same as a certificate of occupancy?

No. The certificate of occupancy authorizes the use and occupancy of the building, and Administrative Code 28-117.1 bars a PA certificate unless the certificate of occupancy already authorizes the assembly use. DOB’s certificate of occupancy worksheet expects the place of assembly inspection to show Final-Passed, and occupancy stays limited to 74 until it does.

Does a restaurant need one?

Conditional: a restaurant needs a PA certificate when 75 or more members of the public gather indoors to eat or drink, or 200 or more outdoors. A restaurant whose approved occupant load is 74 or fewer indoors operates under its certificate of occupancy without one.

What is a temporary place of assembly?

A temporary place of assembly is an event space, such as a trade show, concert or private event, that uses the same 75 indoor and 200 outdoor thresholds and needs a Temporary Place of Assembly Certificate of Operation from DOB. As of November 2026 it is filed in DOB NOW: Build at least 10 business days before the event, with a $250 base fee and $100 per day extra if filed late; filings 3 business days or less before the event are not guaranteed.

This article is general information, not a substitute for a project-specific code analysis. Code editions, local amendments and reviewer practice change; confirm the adopted code and the authority having jurisdiction for the project.

Need a Place of Assembly Certificate in New York City?

Send the address, the certificate of occupancy, the floor plan and the planned seating. DGA checks the occupant load against the threshold and the CO, prepares the egress and seating layouts, and coordinates the FDNY approvals the DOB filing depends on. Project briefs get confirmation and preliminary code feedback within one business day.

Send a Project Brief → View Related Services

Leave a Reply

Your email address will not be published. Required fields are marked *

Quick inquiry

Ready when you are.

Your name, a way to reach you, and where the project is. One of our licensed PEs replies within one business day. Every inquiry is confidential.

Prefer to describe it first? Open the Project Desk