Approvals by Jurisdiction · Definition
What Does WSSC Require for Fire Service Connections?
General guidance, not a code determination for any project. Confirm the adopted code and local amendments with the authority having jurisdiction.
WSSC Water (the Washington Suburban Sanitary Commission) requires a new fire service connection to be shown on a site utility plan sealed by a Maryland Professional Engineer (PE), sized from WSSC hydraulic data or a fire flow test, fitted with a WSSC meter or detector check, and protected by a backflow assembly that a WSSC-licensed plumber tests at installation and every year after. WSSC Water is the water utility for most of Montgomery and Prince George’s Counties, Maryland, and its approval runs alongside the county fire protection permit rather than replacing it.
This article defines what WSSC means by a fire service connection, lists what WSSC asks for at each part of the line, shows where WSSC rules sit next to the National Fire Protection Association (NFPA) standards and the county permit, and explains when a project needs WSSC review. Requirements are stated as of November 2026.
At a Glance: WSSC Fire Service Connection
- Definition: the water service pipe from a WSSC main that feeds sprinklers, standpipes or private hydrants, together with the WSSC meter or detector check, the private fire line on the site and the backflow assembly that protects the public supply.
- Governing code and section: 2024 WSSC Plumbing and Fuel Gas Code (based on the 2024 International Plumbing Code, effective December 1, 2025, with Amendment 1 effective February 2, 2026), Section 109.4 (fire service connections and fire hydrants), Section 109.5 (metering) and Section 506.11 (automatic fire sprinkler systems); WSSC Development Services Code for site utility review.
- Who prepares it or who it applies to: a Maryland PE prepares the site utility plan; the sprinkler designer uses the WSSC flow data; WSSC builds the service connection from its main; a WSSC-registered plumbing firm installs and tests the backflow assembly.
- When it is required: a new water service connection 4 inches or larger, new development that increases demand, or new pipe added to an existing private system, anywhere in the WSSC service area.
- Typical output: an approved site utility plan with a Hydraulic Information Sheet (HIS), a WSSC service connection, an outside meter vault or inside meter, and a tested backflow assembly on record.
- Often confused with: the county fire protection permit from Montgomery County or Prince George’s County, which approves the sprinkler system itself, not the utility connection.
What Is a WSSC Fire Service Connection?
A WSSC fire service connection is the part of a building’s water supply that WSSC Water controls or reviews between its public main and the sprinkler riser. WSSC’s Development Services Code defines a service connection as the lateral pipe built by WSSC or its designee from a WSSC main, and a site utility system as privately owned water and sewer mains on private property. A fire line is one of those private mains, and WSSC’s site utility design checklist asks for a water line used only for fire to be labeled “FIRELINE” on the plan.
The fire service therefore changes hands along its length. WSSC is responsible for the main and the service connection, and the property owner owns the private fire line, the private hydrants and the fire department connection (FDC). The metering point, an outside meter vault in a WSSC easement or an inside master meter, is where WSSC’s billing and backflow interests meet the owner’s piping. The underground private main itself is designed and tested under NFPA 24, which DGA’s guide to what a private fire service main is under NFPA 24 covers in detail.
Figure 1: Fire Service From the WSSC Main to the Riser
What WSSC Requires: Connection, Backflow, Metering and Flow Data
WSSC’s requirements fall on four items: the connection to the main, the private fire line and its plan, the meter, and the backflow assembly. The flow data a sprinkler designer needs comes from WSSC as well. The table lists each item, what WSSC asks for and who does the work, as of November 2026.
| Item | WSSC requirement | Who designs or does it |
|---|---|---|
| Service connection | Lateral from the WSSC main, built by WSSC or its designee. A new water service connection 4 inches or larger needs a standard site utility plan whatever its length (WSSC site utility design checklist, item 2). | WSSC builds it; the site engineer shows it on the site utility plan |
| Site utility plan | Plan of the private water and sewer mains on the property, filed through WSSC ePlan review as a standard or minor site utility plan. Every sheet carries a Maryland PE’s certification statement and seal. Fire-only lines are labeled “FIRELINE” and the FDC is shown. | Civil or site engineer licensed in Maryland |
| Hydraulic Information Sheet | The applicant completes Part 1 with the on-site hydrant, sprinkler and standpipe flows; WSSC calculates Part 2 at the connection point to the main, not at the property line. A new HIS is needed for each new project. The checklist does not allow more than 1,500 gpm for any one of the three flows. | Applicant’s engineer (Part 1); WSSC (Part 2) |
| Fire flow test and hydraulic grades | Since September 2, 2026, fire flow test requests and payment go only through WSSC’s online Fire Flow Test Application. High and low hydraulic grades, in feet above mean sea level, are free from WSSC Permit Services by phone or through WSSC’s online engineering records application. | Sprinkler designer or engineer requests; WSSC supplies the data |
| Meter or detector check | An outside meter vault with a bypass and 3 valves in a WSSC easement, or an inside master meter where water is routed back outside. The meter is sized on the total domestic and fire flow on the HIS, and compound meters are not allowed for fire flow. WSSC’s fee schedule for fiscal year 2027 (effective July 1, 2026) lists detector checks from 2 to 12 inches and fire service meters from 4 to 12 inches. | WSSC supplies the meter; the site engineer sizes and shows it |
| Backflow assembly | Containment and isolation protection, required of all WSSC customers since 2007. Installing or relocating a testable assembly needs a WSSC plumbing permit. Testable assemblies are tested at installation and every year after (Plumbing and Fuel Gas Code Section 508.2). | A WSSC-registered plumbing firm; the tester is a licensed plumber certified as a cross-connection technician |
The 1,500 gpm limits are checklist items, so an HIS that lists more sprinkler, standpipe or combined hydrant flow than that does not pass WSSC review as filed. Where the WSSC supply falls short of the demand, the fix sits on the owner’s side of the meter, such as a fire pump or a tank, and DGA’s article on how current a flow test must be and who can perform one covers the data rules that apply next.
WSSC’s site utility design checklist, revised November 15, 2022, steps meter size with flow. It shows a 4-inch meter up to 700 gpm (only where no hydrant is on the line), a 6-inch meter from 700 to 1,600 gpm, an 8-inch meter from 1,600 to 2,800 gpm and a 10-inch meter from 2,800 to 4,400 gpm.
Where WSSC Rules Sit Relative to NFPA 24 and the County Permit
WSSC Water enforces its own Plumbing and Fuel Gas Code across its service area. The 2024 edition adopts the 2024 International Plumbing Code with WSSC amendments, took effect December 1, 2025, and was amended effective February 2, 2026. WSSC states that the Maryland State Plumbing Code and the WSSC code both regulate cross-connection control, and the WSSC code addresses fire service connections in Section 109.4, metering in Section 109.5, automatic fire sprinkler systems in Section 506.11, and retrofits and existing commercial fire sprinkler systems in Section 506.12.
The fire protection design sits under a different set of rules. In Maryland, the county building permit reviews sprinklers to NFPA 13 (2019) through the 2021 International Building Code (IBC), while the State Fire Prevention Code (NFPA 1, 2024) references NFPA 13 (2022). Montgomery County’s Department of Permitting Services (DPS) adopts NFPA 13 (2019) by Executive Regulation 14-24, effective December 10, 2024. The private underground main between the WSSC meter and the riser is built and tested under NFPA 24, which the sprinkler and fire codes reference.
The handoff point matters for the hydraulic calculation. WSSC calculates HIS Part 2 at the connection to its main, so the sprinkler designer carries the supply from that point through the service connection, the meter, the backflow assembly and the private main to the base of the riser. WSSC itself warns that HIS data is a theoretical estimate, that results from either a flow test or an HIS can overstate the supply where mains or service connections are heavily tuberculated, and that a system designed on overstated data may fail the county’s test and hold up the occupancy permit. The method for reading a field test is set out in DGA’s guide to how a hydrant flow test is run and read under NFPA 291, and the Hydrant Flow Test Calculator projects a test to 20 psi.
DGA analyzes water supplies and designs fire pumps where a WSSC service cannot meet the sprinkler or standpipe demand, across New York, New Jersey, Pennsylvania, Maryland and Delaware. Project briefs get confirmation and preliminary code feedback within one business day. See where DGA works →
WSSC Approval vs County Fire Protection Approval
WSSC approval and the county fire protection permit are two separate approvals on the same water line. WSSC decides whether the building may connect, how the connection is metered and how the public water is protected from backflow. The county decides whether the sprinkler, standpipe and fire alarm design meets the fire and building codes. A WSSC-approved site utility plan does not approve the sprinkler system, and a county sprinkler permit does not authorize a connection to the WSSC main.
| Question | WSSC Water | County fire protection review |
|---|---|---|
| What is approved | Service connection, site utility plan, meter or detector check, backflow assembly | Sprinkler, standpipe and fire alarm design and installation |
| Code basis | 2024 WSSC Plumbing and Fuel Gas Code; WSSC Development Services Code | 2021 IBC with NFPA 13 (2019) through the county permit; Montgomery County fire code (NFPA 1 and NFPA 101, 2021); State Fire Prevention Code (NFPA 1 and NFPA 101, 2024) |
| Who reviews | WSSC Development Services and Permit Services | Montgomery County DPS; in Prince George’s County, the Department of Permitting, Inspections and Enforcement (DPIE), with sprinkler shop drawings reviewed through its Third-Party Review Program |
| Filing system | WSSC ePlan review; online Fire Flow Test Application; WSSC ePermitting | Montgomery DPS ePlans and eServices; Prince George’s DPIE Momentum |
| Field check | WSSC inspection of utility work; backflow test at installation and every year | County inspection and acceptance testing of the fire protection system |
How each county files, reviews and inspects the fire protection side is set out in DGA’s guide to how Montgomery and Prince George’s Counties approve fire plans. Montgomery County issues separate Fire Protection System and Fire Alarm System permits, and Prince George’s County requires sprinkler and fire alarm shop drawings to pass an owner-paid third-party review before DPIE accepts them.
When a Project Needs WSSC Review
WSSC review is needed whenever a project in the WSSC service area creates or changes a water service that feeds fire protection. WSSC’s site utility design checklist requires a standard site utility plan for a new water service connection 4 inches or larger, for new development or redevelopment that increases demand, and for new pipe added to an existing private system. Where an existing building on the site gets a new meter, the plan shows it with a meter note inside the building footprint.
Smaller jobs follow a lighter path. WSSC issues an HIS only through a standard or minor site utility review where the connection is at least 4 inches, and a minor site utility system is exempt from the HIS where the flow is under 200 gpm on an 8-inch main or under 300 gpm on a main 10 inches or larger. In those cases WSSC tells sprinkler designers to start from the low hydraulic grade.
Homes have their own backflow rules. WSSC says homes built from 2007 to 2009 had to install a testable double check assembly on the sprinkler supply, and an owner may replace one with a non-testable dual check valve that is rebuilt or replaced every 5 years, with proof of coordination with a certified fire sprinkler contractor. The county fire marshal may add requirements.
Figure 2: From Flow Data to a Tested Fire Line
Key Takeaway: A WSSC fire service connection needs four things from WSSC Water: a site utility plan sealed by a Maryland PE, flow data from an HIS or a fire flow test, a WSSC meter or detector check sized on domestic plus fire flow, and a backflow assembly tested at installation and every year. That approval is separate from the Montgomery or Prince George’s County fire protection permit, and both are needed before the system serves the building.
Frequently Asked Questions
Who runs flow tests on WSSC mains?
WSSC Water takes the requests. Since September 2, 2026, fire flow test requests and payment go only through WSSC’s online Fire Flow Test Application, and hydraulic grades for a first check are free from WSSC Permit Services.
Does WSSC require a backflow preventer on fire lines?
Yes. WSSC has required containment backflow protection of all customers since 2007, and its Plumbing and Fuel Gas Code addresses automatic fire sprinkler systems in Section 506.11. Testable assemblies are tested at installation and every year after by a WSSC-licensed plumber certified as a cross-connection technician.
Is WSSC approval separate from the county permit?
Yes. WSSC Water approves the site utility plan, the meter and the backflow assembly, while Montgomery County DPS or Prince George’s County DPIE permits the sprinkler system. Neither approval replaces the other.
How old can a WSSC flow test be?
WSSC Water publishes no age limit for its flow data. NFPA 13 (2022) Section 4.5.1.1, which the State Fire Prevention Code references, calls for a test no more than 12 months before the working plans are submitted unless the authority having jurisdiction accepts an older one, and the county reviewer makes that call.
More in Approvals by Jurisdiction
- How Does AHJ Review Work in NYC, NJ and Philadelphia?
- How Do Pittsburgh Fire Protection Approvals Work?
- How Do Federal Agencies Review Leased-Space Fire Protection?
- What Is Maryland’s Sprinkler Law for New Homes?
- Does the Pennsylvania Fire and Panic Act Still Apply?
- What Does NYC Require for Construction Site Fire Safety?
This article is general information, not a substitute for a project-specific design or code analysis. Utility rules, code editions and reviewer practice change; confirm current requirements with WSSC Water and the authority having jurisdiction for the project.
Planning a Fire Service in the WSSC Area?
Send the site plan, the sprinkler demand and any WSSC flow data on hand. DGA checks the supply against the demand from the WSSC main to the riser and designs a fire pump where the service falls short. Project briefs get confirmation and preliminary code feedback within one business day.