How High Can You Store Under Ceiling-Only Sprinklers?

Reviewed by a licensed Professional Engineer · NY, NJ, PA, MD, DE · Last reviewed · Code basis: NFPA 13 (2022; 2019 in PA and MD under the 2021 IBC; 2025 in DE) Ch. 20 to 25; IFC Chapter 32 (2021); FM Global DS 8-9

General guidance, not a code determination for any project. Confirm the adopted code and local amendments with the authority having jurisdiction.

Ceiling-only sprinklers can protect rack storage under ceilings as high as 45 ft when the sprinklers are Early Suppression Fast Response (ESFR) heads with a large K-factor and the commodity is Class I to IV or cartoned unexpanded plastics. NFPA 13 (2022) sets ESFR limits by ceiling height, not by storage height. Control Mode Density/Area (CMDA) standard spray sprinklers top out near 25 ft of rack storage, Control Mode Specific Application (CMSA) sprinklers sit in between, and exposed plastics cut every one of those numbers down. Above the limit for the installed sprinkler type, National Fire Protection Association (NFPA) 13 requires in-rack sprinklers or a different ceiling design, and the fire code requires a new high-piled storage review.

The question usually arrives from a tenant, a broker or an owner looking at a lease: the building has sprinklers, the racks are going to 30 ft, does anything need to change? The answer depends on four numbers that are easy to measure and one classification that is not. This article lays out the ceiling-only height limits by sprinkler type under NFPA 13, how storage and ceiling height are measured, what changes the answer, and what a project owes the fire code official once a limit is crossed.

At a Glance: Storage Height Under Ceiling-Only Sprinklers

  • Thresholds: CMDA ceiling-only designs cover rack storage of Class I to IV up to 25 ft, and the Chapter 21 plastics tables set their own limits; CMSA reaches 20 ft to 35 ft of storage under 30 ft to 40 ft ceilings by K-factor; ESFR is indexed by ceiling height alone, with K-14 reaching a 35 ft ceiling (75 psi), K-16.8 a 40 ft ceiling (52 psi), K-25.2 a 40 ft ceiling at 25 psi, and the 45 ft ceiling as the top of the ESFR range. Minimum clearance from the top of storage to the deflector is 18 in. for standard spray and 36 in. for CMSA and ESFR.
  • Code, edition, section: NFPA 13 (2022) Chapter 20 (general storage rules and clearance), Chapter 21 (CMDA), Chapter 22 (CMSA), Chapter 23 (ESFR), Chapter 24 (alternative designs) and Chapter 25 (in-rack sprinklers). The 2019 edition applies in Pennsylvania and under the Maryland building code; the 2025 edition applies in Delaware. International Fire Code (IFC) Chapter 32 (2021) sets the 12 ft high-piled storage trigger, the 6 ft trigger for certain high-hazard commodities where the fire code official requires it, and the pile limits in Table 3206.2.
  • Main exceptions: in-rack sprinklers under Chapter 25; lowering the storage; changing the packaging so the commodity drops a class; a listed sprinkler with a specific-application design under Chapter 24; an FM Global Data Sheet 8-9 design where the insurer and the authority having jurisdiction (AHJ) accept it.
  • What applies once triggered: a new sprinkler design or in-rack system, hydraulic calculations against the available water supply (often a fire pump), an updated high-piled storage plan, and a sprinkler permit plus the high-piled storage operational permit.
  • Permit or filing: fire sprinkler permit with sealed drawings and calculations; high-piled combustible storage permit under IFC Section 105.5 (2021) or NFPA 1 Section 1.13 (Table 1.13.8) in Maryland and Delaware.
  • Who decides: the fire code official and the building official, with the property insurer’s engineer as a second gate on FM-insured buildings.

What Are the Ceiling-Only Storage Height Limits by Sprinkler Type?

NFPA 13 does not publish one height limit. The standard gives each protection scheme its own chapter, and each chapter lists the conditions that a ceiling-only design has been tested to protect, by commodity class. The CMDA and CMSA criteria pair a storage height with a ceiling height; the ESFR table is indexed by maximum ceiling height alone. If the building’s storage height, ceiling height and commodity all fall inside an entry, ceiling sprinklers alone are permitted; if any one falls outside, the design has to change.

The table below states the structure of those chapters and the headline numbers. It is a summary of the limits, not a reproduction of the tables, and every row needs to be confirmed against the adopted edition and the sprinkler listing before anything is built.

Protection schemeClass I to IVCartoned unexpanded plasticsExposed plasticsBasis
CMDA (standard spray, density/area)Rack storage to 25 ft ceiling-only; over 25 ft goes to Chapter 25 in-rack sprinklers. Nonencapsulated solid-piled, palletized and bin box storage to 30 ft; shelf storage to 15 ftIn racks per the Chapter 21 plastics decision tree and tables, which set their own storage and ceiling height limitsExposed unexpanded: covered by the plastics tables at higher demands. Exposed expanded in racks: no ceiling-only CMDA entryNFPA 13 (2022) Ch. 21 (Section 21.4.1 for racks)
CMSA K-11.2 and K-16.8 (upright)Class I and II: 20 ft and 25 ft of storage under a 30 ft ceiling; 30 ft under a 35 ft ceiling needs in-rack sprinklers20 ft under 25 ft or 30 ft ceilings; 25 ft under a 30 ft ceiling with K-16.8 onlyExposed unexpanded to 25 ft under a 30 ft ceiling; no expanded plastic entriesNFPA 13 (2022) Tables 22.4 and 22.5
CMSA K-19.6 (pendent, wet only)To 35 ft of storage under a 40 ft ceiling (15 sprinklers at 30 psi)25 ft or 30 ft under a 35 ft ceiling; 35 ft under a 40 ft ceilingNo exposed plastic entriesNFPA 13 (2022) Tables 22.4 and 22.5
CMSA K-25.2Class I to III: to 35 ft of storage under a 40 ft ceiling (23 psi)35 ft under a 40 ft ceilingNo exposed plastic entriesNFPA 13 (2022) Tables 22.4 and 22.5
ESFR K-14 (pendent and upright)Ceilings to 30 ft at 50 psi and to 35 ft at 75 psi; no entry at a 40 ft ceilingSame row as Class I to IV in the ESFR tableExposed unexpanded: pendent, ceilings to 30 ft. Exposed expanded in racks: Section 23.4 route uses K-25.2NFPA 13 (2022) Table 23.3.1
ESFR K-16.8Ceilings to 30 ft at 35 psi; ceilings of 35 ft and 40 ft at 52 psiSame as Class I to IVExposed unexpanded: pendent, ceilings to 30 ft, no entry at 35 ft. Exposed expanded in racks: Section 23.4 route uses K-25.2NFPA 13 (2022) Table 23.3.1
ESFR K-22.4Ceilings up to 40 ft, and up to the 45 ft ceiling, the top of the ESFR rangeSame as Class I to IVExposed unexpanded at a 40 ft ceiling at 75 psi. Exposed expanded in racks: Section 23.4 route uses K-25.2NFPA 13 (2022) Table 23.3.1
ESFR K-25.2Ceilings to 40 ft at 25 psi, and up to the 45 ft ceiling; no ceiling-only entry above a 45 ft ceilingSame as Class I to IVExposed unexpanded at a 40 ft ceiling at 60 psi. Exposed expanded in single, double and multiple-row racks to 35 ft of storage under a 40 ft ceiling, intermediate-temperature pendent, deflector no more than 14 in. below the ceilingNFPA 13 (2022) Table 23.3.1; Section 23.4
In-rack sprinklers plus ceilingOne or more levels of in-rack sprinklers with a matched ceiling design; limits set by the Chapter 25 schemesSameSame; the usual route for exposed expanded plastics outside the K-25.2 ESFR optionNFPA 13 (2022) Ch. 25

Two patterns in the table matter more than any single number. First, ESFR puts cartoned unexpanded plastics in the same table row as Class I to IV commodities, which is why most modern distribution buildings are designed for that class. CMSA covers cartoned plastics in separate entries, and some of its values differ from Class I to IV. Second, exposed plastics, and exposed expanded plastics above all, lose ceiling-only coverage quickly (exposed expanded plastic in racks has only the K-25.2 ESFR route in Section 23.4), which is why a change in a customer’s packaging can defeat a sprinkler system that was correct the day it was installed. DGA’s guide to commodity classification under NFPA 13 explains how product, packaging and pallet combine into a class.

The 2022 edition tightened some ESFR entries. For uncartoned unexpanded plastics under a 35 ft roof, the K-14 and K-16.8 entries that the 2019 edition allowed were removed, so the design falls to K-22.4 or K-25.2 at the 40 ft roof criteria. Pennsylvania and the Maryland building code still reference the 2019 edition, so the same building can have a different answer across a state line.

Figure 1: The Ceiling-Only Height Ladder

010 ft20 ft30 ft40 ft50 ft 45 ft ceiling cap CMDA (racks) CMSA K-11.2, K-16.8 CMSA K-19.6, K-25.2 ESFR K-14 ESFR K-16.8 ESFR K-22.4 ESFR K-25.2 25 ft, then in-rack 25 ft under 30 ft 35 ft under 40 ft ceiling 35 ft ceiling 40 ft 45 ft 45 ft
For Class I to IV commodities and cartoned unexpanded plastics, the CMDA and CMSA bars show maximum ceiling-only storage height: about 25 ft for CMDA rack designs and CMSA K-11.2 and K-16.8, and 35 ft under a 40 ft ceiling for CMSA K-19.6 and K-25.2. The ESFR bars show maximum ceiling height, because NFPA 13 (2022) Table 23.3.1 is indexed by ceiling height alone: 35 ft for K-14, 40 ft for K-16.8 and 45 ft for K-22.4 and K-25.2. Exposed plastics sit lower on every rung.

How Are Storage Height, Ceiling Height and Clearance Measured?

Storage height is measured from the floor to the top of the highest stored commodity, including the pallet it sits on and any load that overhangs the top beam. The top of the rack upright does not count; the top of the product does. Ceiling height is measured from the floor to the underside of the roof deck or ceiling, not to the bottom of the joists or the sprinkler deflector. Clearance is the vertical distance from the top of storage to the sprinkler deflector.

NFPA 13 (2022) sets the minimum clearance from the top of storage to the deflector at 18 in. for standard spray sprinklers (Section 20.9.6.1 for storage), 36 in. for CMSA sprinklers (Section 13.2.9) and 36 in. for ESFR sprinklers (Section 14.2.12). The 36 in. figure exists because suppression-mode sprinklers need room to develop their spray pattern before it reaches the top of the array. A tenant who stacks one more pallet on the top beam can violate the clearance rule without coming anywhere near the storage height limit in the table above.

Three storage conditions change the answer even when the heights are fine. Encapsulated commodities, meaning pallet loads wrapped in plastic over the top as well as the sides, shed sprinkler water and carry a higher density in the CMDA criteria of Chapter 21. The CMSA and ESFR tables make no encapsulation distinction. Solid shelves wider than the open-rack limits block water from reaching the levels below and generally force in-rack sprinklers or a specific-application design. Open-top containers on upper levels catch the ceiling water meant for the storage beneath them; DGA’s article on why open-top bins defeat rack sprinklers covers the fix.

Figure 2: The Three Heights on a Rack Section

Underside of roof deck: 32 ft Deflector line Top of storage: 25 ft Ceiling height floor to deck: 32 ft Storage height 25 ft Clearance 7 ft Minimum clearance to deflector: 18 in. for standard spray, 36 in. for CMSA and ESFR (NFPA 13). Storage height is to the top of the load, not the top of the rack. Ceiling height is to the underside of the deck.
Storage height runs from the floor to the top of the stored load, ceiling height from the floor to the underside of the roof deck, and clearance from the top of storage to the sprinkler deflector. NFPA 13 (2022) requires at least 18 in. of clearance under standard spray sprinklers (Section 20.9.6.1) and 36 in. under CMSA (Section 13.2.9) and ESFR (Section 14.2.12) sprinklers. In this 32 ft building with 25 ft of storage the clearance is 7 ft, so the storage height table, not the clearance rule, governs.

Opens the Project Desk with your sentence. Our licensed PEs review every brief and reply within one business day.

Can the Existing Ceiling Sprinklers Protect the New Storage?

The design check runs in a fixed order, and the first three steps need no engineer, only a tape measure and the product list. The decision tree below is the sequence DGA’s engineers follow when a rack fit-out brief comes in. Each “no” has a cost, and the cheapest fixes sit at the top.

Figure 3: Can the Ceiling Sprinklers Carry the New Racks?

Proposed storage: height to top of load, ceiling height, commodity class, rack type
Is the top of storage over 12 ft (over 5 ft for Group A plastics)?
NoMiscellaneous storageOrdinary or extra hazard design under NFPA 13 Ch. 4 and 20; no high-piled storage permit
Yes
Is the commodity Class I to IV or cartoned unexpanded plastic?Check the table for the installed sprinklerStorage height, ceiling height and K-factor must all fall inside one entry in Ch. 21, 22 or 23
Exposed or expanded plastic, solid shelves, open-top binsCeiling-only is usually outIn-rack sprinklers under Ch. 25, or a listed alternative under Ch. 24
Does the installed design fall inside an entry, with 18 in. or 36 in. of clearance?
YesCeiling-only worksUpdate the high-piled storage plan and confirm the water supply still meets the demand
NoSomething has to changeLower the storage, change the packaging, replace the ceiling sprinklers, or add in-rack sprinklers and a permit
Ceiling-only protection works only when the storage height, the ceiling height, the commodity class and the installed sprinkler K-factor all fall inside one entry of NFPA 13 (2022) Chapter 21, 22 or 23 and the clearance to the deflector is at least 18 in. (CMDA) or 36 in. (CMSA and ESFR). Exposed expanded plastics, solid shelves and open-top containers usually push the design to in-rack sprinklers under Chapter 25.

What Are the Exceptions and Alternatives When the Limit Is Exceeded?

The first alternative is the one NFPA 13 names: in-rack sprinklers. NFPA 13 (2022) Chapter 25 consolidates every in-rack design, with one or more levels of sprinklers inside the rack and a matched ceiling design, and it covers storage heights that ceiling-only designs cannot. In-rack systems add piping inside the racks, a risk of forklift damage, and a maintenance burden, which is why owners of speculative buildings avoid them, but for exposed expanded plastics they are often the only path outside the K-25.2 ESFR option in Section 23.4.

The second alternative is to change the storage rather than the sprinklers. Dropping the top beam so the load tops out at 25 ft instead of 30 ft can move a building from “in-rack required” to “ceiling-only permitted” under the same sprinklers. Changing from exposed to cartoned product, or from plastic to wood pallets, can drop the commodity a class. Both are operational commitments that belong in the lease and on the high-piled storage plan, because the fire code official will hold the tenant to them.

The third alternative is a different ceiling sprinkler. Replacing CMSA or older ESFR heads with K-25.2 ESFR sprinklers can extend ceiling-only protection to ceilings up to 45 ft without touching the racks, provided the pipe sizes, the pressure and the water supply can carry the new demand. DGA’s comparison of ESFR and CMSA sprinklers for warehouses covers that trade in detail.

The fourth path is a design outside the NFPA 13 tables. Chapter 24 permits alternative sprinkler system designs based on a sprinkler’s specific listing, and some manufacturers hold listings that go beyond the NFPA 13 tables. FM Global Data Sheet 8-9 publishes its own protection tables by commodity, storage height and ceiling height, which differ from NFPA 13 in places and are often stricter. An FM-insured building has to satisfy both, and the AHJ has to accept the FM design under the alternative-methods provision of the adopted building or fire code.

What Applies Once the Ceiling-Only Limit Is Crossed?

Crossing a height limit triggers four things, and a project usually meets all of them together. First, a new sprinkler design, meaning sealed drawings and hydraulic calculations for the ceiling system, the in-rack system or both, filed under a sprinkler permit. Second, an updated high-piled storage plan: the IFC’s 12 ft and 6 ft triggers and the pile limits in Table 3206.2 are explained in DGA’s article on when IFC Chapter 32 applies to high-piled storage, and once the plan on file no longer matches the racks, the operational permit is no longer valid.

Third, a water supply check. ESFR demands of 1,500 gpm to 2,200 gpm at 50 psi to 75 psi at the top of the riser are common, far above what most municipal mains deliver at the required pressure, so a fire pump, a larger service or a tank often arrives with the new design. Fourth, the insurer’s sign-off, since a carrier that rated the building for 25 ft of Class III will re-underwrite it for 40 ft of plastics.

How Do the Editions Differ Across NY, NJ, PA, MD and DE?

The height limits come from NFPA 13, so they differ across the region only by edition. The 2019 and 2022 editions share the same chapter numbering for storage (Chapters 20 through 25); the 2025 edition that Delaware adopted keeps Chapters 20 through 25 but revises several storage tables, so citations for Delaware projects should be checked against the 2025 text. New York City’s building code references an earlier edition of NFPA 13 as modified by Appendix Q, where the storage chapters carry different numbers again.

JurisdictionNFPA 13 edition and how it is adoptedAHJFiling or permit
New York State (outside NYC)NFPA 13 (2022), referenced by the 2024 International Building Code (IBC) under the 2025 Uniform CodeLocal code enforcement officialBuilding permit with sprinkler drawings; high-piled storage operational permit under the Fire Code of New York State
New York CityNFPA 13 as modified by 2022 NYC Building Code Appendix Q (the referenced edition is earlier than 2022, and its storage chapters are numbered differently in that edition)Department of Buildings (DOB) for the sprinkler filing; Fire Department of New York (FDNY) for the high-piled storage permit under 2022 Fire Code Chapter 32DOB NOW sprinkler work type; FDNY permit
New JerseyNFPA 13 (2022), referenced by the 2024 I-Codes under the Uniform Construction Code (effective August 17, 2026)Municipal construction official and fire protection subcode official; local fire official enforces IFC Chapter 32 at inspectionFire protection subcode permit under the UCC; no separate fire permit for high-piled storage
PennsylvaniaNFPA 13 (2019), referenced by the 2021 IBC under the Uniform Construction Code (effective January 1, 2026); no statewide fire codeMunicipal or third-party code official; Philadelphia Department of Licenses and Inspections (L&I) in the cityUCC building permit with sprinkler drawings; municipal fire code permit where adopted
MarylandNFPA 13 (2022), referenced by NFPA 1 (2024) under the State Fire Prevention Code; the 2021 IBC references the 2019 editionCounty building official; State or local fire marshalCounty sprinkler permit; fire marshal plan review under NFPA 1 Chapter 34; high-piled storage permit under NFPA 1 Section 1.13 (Table 1.13.8)
DelawareNFPA 13 (2025), adopted by State Fire Prevention Regulation 701 (2026)Office of the State Fire Marshal (Wilmington Fire Marshal inside the city); county building officialState Fire Marshal plan review and permit; county building permit

Editions as listed in DGA’s Fire Code Cheat Sheet for NY, NJ, PA, MD and DE. Local amendments are not shown.

Worked Example: 25 ft of Cartoned Plastics Under a 32 ft Deck

A tenant proposes double-row racks holding cartoned unexpanded Group A plastics to 25 ft in a warehouse with a 32 ft clear height to the underside of the deck. The clearance is 7 ft, so both the 18 in. and 36 in. rules are satisfied. The storage is over 12 ft, so IFC Chapter 32 applies and the high-piled storage plan has to show the new arrangement. What remains is whether the installed ceiling sprinklers have an entry for 25 ft of cartoned unexpanded plastics under a ceiling that reads as 35 ft in the tables, since common practice is to use the next ceiling height listed rather than interpolate.

Installed ceiling sprinklerDoes it work for 25 ft of cartoned unexpanded plastics under 32 ft?Why
CMDA, Ordinary Hazard Group 2 design (0.2 gpm per sq ft over 1,500 sq ft)NoThe building was designed as a miscellaneous storage occupancy; it has no Chapter 21 storage design for 25 ft of plastics in racks (NFPA 13 (2022) Ch. 21). In-rack sprinklers or a ceiling replacement.
CMSA K-16.8NoThe K-16.8 CMSA entries for cartoned unexpanded plastics stop at 25 ft of storage under a 30 ft ceiling; a 32 ft ceiling falls outside them (NFPA 13 (2022) Ch. 22).
ESFR K-14 pendentConditionalThe 35 ft ceiling entry requires 75 psi at the sprinkler. Whether the supply can deliver 12 sprinklers at that pressure decides it (NFPA 13 (2022) Table 23.3.1).
ESFR K-16.8YesThe 35 ft ceiling entry requires 52 psi, and the same pressure covers ceilings up to 40 ft, so the building has margin (NFPA 13 (2022) Table 23.3.1).
ESFR K-25.2YesK-25.2 entries run to a 40 ft ceiling at 25 psi and up to the 45 ft ceiling, so the building could even go taller later (NFPA 13 (2022) Table 23.3.1).

The water supply decides the last two rows. Twelve K-16.8 sprinklers at 52 psi flow about 121 gpm each, or about 1,450 gpm, plus 250 gpm of hose allowance for 60 minutes, for a demand near 1,700 gpm at the riser before pipe friction. Twelve K-25.2 sprinklers at 25 psi, the 40 ft ceiling entry, flow about 126 gpm each, or about 1,510 gpm plus hose, near 1,760 gpm. A supply curve from a recent hydrant flow test can be plotted against either demand in DGA’s sprinkler water supply analysis tool; if the curve falls short, a fire pump joins the project.

The lease matters as much as the hydraulics. If the building is marketed as “ESFR” but the heads are K-14 on a 30 ft design, the tenant’s 25 ft of plastics is marginal and 30 ft is out. Owners, tenants and brokers negotiating industrial space in the region can read the sprinkler data plate and the installed K-factor before signing; DGA reviews those on the industrial and high-hazard projects it serves and the finding often changes the deal.

Who Needs to Act

WhoOne action
OwnerKeep the sprinkler design basis (K-factor, pressure, storage height and commodity on the hydraulic data plate) in the building file and give it to every prospective tenant.
TenantState the real top-of-load height and the worst commodity, including packaging and pallets, before the rack order is placed.
BrokerAsk for the hydraulic data plate and the high-piled storage permit, not the word “ESFR” on a flyer.
Rack supplierHold the top beam elevation so the load stays below the storage height the sprinklers were designed for.
InsurerConfirm whether FM Data Sheet 8-9 or NFPA 13 governs the account, since the two give different answers at the margins.

Key Takeaway: Ceiling-only sprinklers protect rack storage to about 25 ft with CMDA and 20 ft to 35 ft with CMSA. ESFR is indexed by ceiling height: K-16.8 reaches a 40 ft ceiling at 52 psi, K-25.2 a 40 ft ceiling at 25 psi, and the 45 ft ceiling is the top of the ESFR range. Those limits apply to Class I to IV commodities and cartoned unexpanded plastics; exposed plastics get far less. Measure to the top of the load and the underside of the deck, keep 18 in. or 36 in. of clearance, and find the installed K-factor before the racks are ordered. Past the limit, the choices are lower storage, different packaging, new ceiling heads or in-rack sprinklers, and every one of them comes with a new high-piled storage plan.

Frequently Asked Questions

Can ESFR sprinklers protect 40 ft of storage without in-rack sprinklers?

Yes, for Class I to IV commodities and cartoned unexpanded plastics, when the sprinklers are K-22.4 or K-25.2 ESFR heads, the ceiling is no higher than 45 ft and the design pressure and water supply match the NFPA 13 (2022) Chapter 23 entry. Exposed expanded plastics are not covered ceiling-only at that height.

How much clearance is required between storage and the sprinklers?

At least 18 in. from the top of storage to the deflector for standard spray sprinklers (NFPA 13 (2022) Section 20.9.6.1) and at least 36 in. for CMSA (Section 13.2.9) and ESFR (Section 14.2.12) sprinklers. Less clearance is a violation even when the storage height is within the design limit.

Does a building with ESFR sprinklers allow any storage height?

No. Each ESFR K-factor has its own maximum ceiling height in NFPA 13 (2022), from 35 ft for K-14 to 45 ft for K-22.4 and K-25.2, and the installed pressure has to match. The hydraulic data plate on the riser states the design basis.

Is storage height measured to the top of the rack or the top of the product?

To the top of the product, including the pallet and any load above the top beam. IFC Chapter 32 measures storage height to the top of the stored commodity, and the same measurement is common practice under NFPA 13. Ceiling height runs to the underside of the roof deck.

What happens if a tenant stores higher than the sprinklers were designed for?

Conditional: the fire code official can order the storage lowered or removed, and the high-piled storage permit is invalid until a new plan is approved. The fix is lower storage, different packaging, replacement ceiling sprinklers or in-rack sprinklers, each with a sprinkler permit and a revised plan.

This article is general information, not a substitute for a project-specific evaluation. Code editions, local amendments, sprinkler listings and insurer requirements change; confirm the adopted edition of NFPA 13 and the authority having jurisdiction for the facility.

Racks Going Higher Than the Sprinklers Were Designed For?

Send the rack layout, the product list, the ceiling height and a photo of the hydraulic data plate. DGA checks the installed design against the proposed storage, lays out the options and prepares the storage plan. Project briefs get confirmation and preliminary code feedback within one business day.

Send a Project Brief → View Related Services

Leave a Reply

Your email address will not be published. Required fields are marked *

Quick inquiry

Ready when you are.

Your name, a way to reach you, and where the project is. One of our licensed PEs replies within one business day. No sales calls.

Prefer to describe it first? Open the Project Desk