How Do You Check a Warehouse’s Sprinklers for a New Tenant?
Reviewed by a licensed Professional Engineer · NY, NJ, PA, MD, DE · Last reviewed · Code basis: NFPA 13 (2022; 2019 in PA and MD; 2025 in DE), NFPA 25 (2023), NFPA 291 (2022), 2021 IFC Ch. 32, 2022 NYC Fire Code Ch. 32, NJ UCC and UFC, NFPA 1 (2024) Ch. 34
General guidance, not a code determination for any project. Confirm the adopted code and local amendments with the authority having jurisdiction.
A warehouse sprinkler system is checked for a new tenant by comparing what the system was designed to protect, as recorded on the hydraulic design information sign and in the hydraulic calculations, with what the new tenant plans to store, classified under National Fire Protection Association (NFPA) 13. The comparison covers the commodity class, the storage height and arrangement, the sprinkler type and design density or pressure, the water supply, and the physical condition of the system on the floor. The result is a sealed evaluation letter or gap report that says the system is adequate as is, adequate within stated operating limits, or in need of modification before move-in.
The evaluation is an owner’s duty, not an option. NFPA 25 (2023), the inspection, testing and maintenance standard adopted in every state DGA works in, makes the property owner responsible for having the system evaluated before the occupancy, use, process or materials change, and promptly when such a change is found (Sections 4.1.6 and 4.1.7), and the fire codes require updated construction documents and permits when high-piled storage changes. This article sets out the 8 steps, the documents, the timeline, the findings that most often stop a move-in, and what each jurisdiction expects to be filed.
At a Glance: Sprinkler Evaluation for a New Warehouse Tenant
- Who files: the landlord or tenant as owner’s representative, with a fire protection engineer (FPE) preparing the evaluation; the sprinkler contractor files any modification permit.
- Where it is filed: the evaluation itself stays with the owner’s NFPA 25 records and the lease. What it triggers is filed with the building department (sprinkler modification permit), the fire code official (updated high-piled storage plan or operational permit) and, in New York City, the Fire Department of New York (FDNY) for the high-piled storage permit.
- Documents required: hydraulic design information sign (placard) photo, sprinkler as-builts and hydraulic calculations, a hydrant flow test not more than 12 months old, the last NFPA 25 reports, the prior high-piled storage plan, and the tenant’s commodity, packaging, height and layout data.
- Timeline range (as of October 2026): 2 to 6 weeks for the evaluation when records exist; 6 to 10 weeks when a flow test has to be scheduled or the calculations have to be rebuilt from field measurements.
- Most common rejection or failure finding: a placard that lists a Class I to IV commodity at a stated height while the tenant plans cartoned Group A plastics stored higher, so the ceiling design no longer covers the hazard.
- Approval document: the sealed evaluation letter or gap report, plus the permit sign-off and the updated high-piled storage permit where modifications or a new storage plan are required.
The 8 Steps of a Tenant Sprinkler Evaluation
The sequence runs from the existing records to the filings, and it applies whether the system is a control mode density area (CMDA) design, a control mode specific application (CMSA) design, or an early suppression fast response (ESFR) design.
- Gather the existing records. The landlord provides a photo of the hydraulic design information sign at each riser, the sprinkler as-built drawings, the hydraulic calculations, the last hydrant flow test, the most recent NFPA 25 inspection and test reports, and the prior tenant’s high-piled storage plan or permit. NFPA 13 (2022) requires the sign to state the design area location and size, the discharge density, the required flow and pressure at the base of the riser, the occupancy or commodity class with the maximum storage height and configuration, the hose stream allowance and the installing contractor’s name (Section 29.4; Section 28.5 in the 2019 edition adopted in Pennsylvania and Maryland). NFPA 25 (2023) Chapter 4 requires the owner to keep the as-builts, acceptance tests and calculations for the life of the system.
- Define the new tenant’s storage. The tenant supplies the product list, the packaging (cartoned, exposed, encapsulated, on wood or plastic pallets), the storage method, the maximum storage height, rack depth, flue spaces, aisle widths and the floor area each product will occupy. The worst case the tenant may reach is what gets evaluated, not the opening-day layout.
- Classify the commodity under NFPA 13 Chapter 20. The FPE assigns each storage area a class: Class I to IV, cartoned or exposed Group A plastics, expanded or unexpanded, or a high-hazard commodity that falls outside Chapters 20 to 25. The classification method and the plastic content thresholds are set out in NFPA 13 (2022) Chapter 20 (Class IV in Section 20.4.4, Group A plastics in Section 20.4.5), and DGA’s article on commodity classification under NFPA 13 explains how the call is made when the plastic share is close to a threshold.
- Compare the placard design basis with the new hazard. The FPE lays the new class, height and arrangement against the design the placard records: density and area for a CMDA system, minimum pressure and sprinkler count for CMSA and ESFR, sprinkler K-factor and temperature rating, whether in-rack sprinklers are required at the new height, and the clearance from the top of storage to the deflector. The design criteria come from NFPA 13 (2022) Chapters 20 to 25, and the article on how high storage can go under ceiling-only sprinklers gives the height limits by sprinkler type.
- Verify the water supply and re-run the calculation. A hydrant flow test run to NFPA 291 and not more than 12 months old (the limit NFPA 13 (2022) Section 4.5.1.1 sets for working plan submittals unless the AHJ approves otherwise) is plotted against the new demand plus the hose stream allowance. Where the existing calculation cannot be found, the system is re-calculated from the as-builts. A supply that falls short at the new demand raises the fire pump question, covered in DGA’s article on how engineers decide whether a fire pump is needed.
- Walk the floor. The FPE or the inspecting engineer checks the field against the drawings: obstructions under ESFR sprinklers from new ducts, lights or conveyors; solid shelving in racks; open-top containers; missing, painted or loaded sprinklers; corrosion and microbiologically influenced corrosion on exposed pipe; and the condition of the control valves and the fire department connection. DGA’s article on why open-top bins defeat rack sprinklers covers the finding that most often surprises tenants.
- Write the gap report. The report states one of three outcomes for each storage area: compliant as is; compliant with operating limits (a maximum height, a commodity ceiling, an aisle width or an arrangement the tenant must hold); or needs modification, with the scope of the sprinkler work. The report is sealed by a licensed Professional Engineer (PE) and names the code editions it was evaluated against.
- File what the change triggers, before move-in. Where modification is needed, the sprinkler contractor files a permit with sealed shop drawings and calculations under NFPA 13 (2022) Chapter 30, existing system modifications (Chapter 29 in the 2019 edition). Where the storage changes, the FPE files an updated high-piled storage plan under 2021 International Fire Code (IFC) Section 3201.3 and the operational permit under Section 3201.2 where the jurisdiction issues one. In New York City the tenant applies for the FDNY high-piled storage permit in its own name.
Figure 1: From Records to Filing in 8 Steps
Which Documents the Evaluation Needs, and Who Prepares Each
Six parties hold the records a sprinkler evaluation depends on, and the evaluation stalls when any one of them is assumed to be someone else’s job. The table lists each document, the code basis and the party that normally prepares it.
| Document | What it must show | Basis | Prepared by |
|---|---|---|---|
| Lease exhibit of the storage plan | Products, packaging, storage method, maximum height, rack layout, aisle widths, areas; the worst case the tenant may reach | Input to NFPA 13 (2022) Chapter 20 classification; 2021 IFC Section 3201.3 items | Tenant |
| Hydraulic design information sign (placard) photo | Design area location and size, density or pressure, flow and pressure at the riser, commodity class, storage height and configuration, hose allowance, installing contractor | NFPA 13 (2022) Section 29.4; 2019 edition Section 28.5 | Landlord or property manager |
| Sprinkler as-builts and hydraulic calculations | Sprinkler type, K-factor, temperature rating, spacing, pipe sizes, design area and the supply curve the design was accepted on | NFPA 13 (2022) Chapter 28 working plans and calculations (Chapter 27 in 2019); NFPA 25 (2023) Chapter 4 records | Landlord, from the original installing contractor |
| NFPA 25 inspection and test reports | Last annual, 5-year internal pipe inspection, main drain, valve and alarm tests, open deficiencies | NFPA 25 (2023) Chapters 4, 5, 13 and 14 | Sprinkler service contractor |
| Hydrant flow test | Static, residual and pitot readings, date, hydrant locations, projected flow at 20 psi; not more than 12 months old | NFPA 291 (2022) Chapter 4 for the test; NFPA 13 (2022) Section 4.5.1.1 for the 12-month age | Water purveyor or sprinkler contractor, witnessed where the authority having jurisdiction (AHJ) requires |
| Commodity classification letter and gap report | Class per area with reasoning; comparison to the design basis; one of three outcomes per area; operating limits or modification scope | NFPA 13 (2022) Chapters 20 to 25; NFPA 25 (2023) Chapter 4 | Fire protection engineer, sealed |
| Filings | Sprinkler modification permit with shop drawings and calcs; updated high-piled storage plan; FDNY permit application in NYC | NFPA 13 (2022) Chapter 30; 2021 IFC Sections 3201.2 and 3201.3; 2022 NYC Fire Code Chapter 32 | Fire protection engineer and sprinkler contractor |
Figure 2: Records to Gather Before the Evaluation Starts
DGA evaluates existing warehouse sprinkler systems against new tenants’ storage, classifies commodities and files the resulting plans and permits across New York, New Jersey, Pennsylvania, Maryland and Delaware. Project briefs get confirmation and preliminary code feedback within one business day. See where DGA works →
How Long the Evaluation Takes and What Drives Delays
As of October 2026, a sprinkler evaluation for a new warehouse tenant takes 2 to 6 weeks when the placard, the as-builts, the calculations and a current flow test all exist. The classification and comparison take 1 to 2 weeks once the tenant’s product data arrives; the site walk takes a day; the report takes about a week. Review time for any filing runs on top of that on the jurisdiction’s clock.
Three things push the work past 6 weeks. A flow test older than 12 months has to be rerun, and water purveyors in the region schedule tests 1 to 4 weeks out, longer in winter when some utilities suspend testing. A missing hydraulic calculation adds 1 to 3 weeks of field measurement and re-calculation, and a tenant who cannot yet state the product mix or the final rack height delays the classification and everything after it.
Where the outcome is “needs modification”, the schedule becomes a sprinkler permit schedule. In-rack sprinklers, a density upgrade or a fire pump add months, not weeks, and the move-in date usually moves with them. The industrial and high-hazard sector page describes how DGA sequences that work for warehouse and distribution operators.
| Stage | Typical duration (as of October 2026) | What controls it |
|---|---|---|
| Records gathered | 1 day to 3 weeks | Whether the placard, as-builts and calcs were kept; whether the original contractor still exists |
| Tenant storage data and classification | 1 to 2 weeks | How fast the tenant commits to products, packaging and height; whether plastics sit near a threshold |
| Flow test | Same week to 4 weeks | Purveyor scheduling; winter suspensions; whether a test under 12 months old already exists |
| Comparison and hydraulic re-run | 3 to 5 days, or 1 to 3 weeks if calcs are missing | Whether the original calculation exists; complexity of the storage arrangement |
| Site walk | 1 day | Access with racks empty or partly loaded; lift availability for ceiling inspection |
| Gap report | About 1 week | Number of storage areas and outcomes; whether operating limits need lease language |
| Filings and review | Jurisdiction’s clock; weeks to months if modification is needed | See the jurisdiction table below |
What Filing a Tenant Change Triggers in Each State
The evaluation report is the same in every state. What it triggers differs, because the sprinkler permit sits with the building department, the storage plan and operational permit sit with the fire code official, and New York City adds a separate FDNY permit. The table lists the filings a tenant change normally triggers and the AHJ for each; local amendments and the exact permit names should be confirmed before filing.
| Jurisdiction | Adopted code and edition | What a tenant change triggers | AHJ |
|---|---|---|---|
| New York State (outside NYC) | 2025 Uniform Code (2024 I-Codes); Fire Code of New York State Chapter 32; NFPA 13 (2022) and NFPA 25 (2023) as referenced | Building permit for any sprinkler modification; updated construction documents under Section 3201.3 and an operational permit for high-piled storage where the municipality issues them | Local code enforcement official; local fire official where operational permits are issued |
| New York City | 2022 NYC Construction Codes; 2022 NYC Fire Code Chapter 32; NFPA 13 and 25 as modified by the NYC codes | Department of Buildings (DOB) sprinkler work filing by a PE or Registered Architect (RA) for any modification; FDNY high-piled storage permit, issued per occupant and renewed annually, so the new tenant applies in its own name | DOB for the sprinkler filing; FDNY Bureau of Fire Prevention for the storage permit |
| New Jersey | Uniform Construction Code (UCC), 2024 I-Codes since August 17, 2026; Uniform Fire Code on a 2018 IFC basis | UCC permit with the Fire Protection Subcode Technical Section (F140) for any sprinkler change; updated high-piled storage plan reviewed with that permit; no standalone fire permit, with enforcement at the local fire official’s inspection under 2018 IFC Chapter 32 | Municipal construction official and fire protection subcode official; local fire official |
| Pennsylvania | UCC, 2021 I-Codes since January 1, 2026, referencing NFPA 13 (2019); no statewide fire code | UCC permit for sprinkler modification; fire code filings only where the municipality adopts the IFC; in Philadelphia, a fire code permit for high-piled storage with the plan set | Municipal or third-party code official; Philadelphia Department of Licenses and Inspections (L&I) and Fire Code Unit |
| Maryland | 2021 International Building Code (IBC) for the building permit, referencing NFPA 13 (2019); State Fire Prevention Code, NFPA 1 (2024) Chapter 34 and NFPA 25 (2023) | County building permit for sprinkler modification; fire marshal plan review of the storage change under NFPA 1 Chapter 34 and a high-piled storage permit for areas over 500 sq ft under NFPA 1 Section 1.13 (Table 1.13.8) | County building official; Office of the State Fire Marshal or county fire marshal |
| Delaware | Regulation 701 (2026), NFPA 1 (2024) Chapter 34, NFPA 13 (2025), NFPA 25 (2023); IBC by county (New Castle and Sussex 2021, Kent and Wilmington 2018) | State Fire Marshal plan review of the sprinkler modification and the storage change before the county permit; operational permit per Regulation 701 | Office of the State Fire Marshal, Technical Services; Wilmington Fire Marshal inside the city; county building official |
Editions as listed in DGA’s Fire Code Cheat Sheet for NY, NJ, PA, MD and DE. Local amendments are not shown.
Why Tenant Sprinkler Evaluations Fail, and the Fix for Each
Most findings are not design errors in the original system. The system was built for a tenant who has since left, and the building is being asked to protect something it was never designed for. The pairs below are the findings DGA sees most often on warehouse tenant evaluations, each with the fix.
No placard, so the design basis is unknown. The sign is missing, painted over or illegible. Fix: locate the calculations or the acceptance documents; failing that, measure the system in the field, re-calculate it, and install a new sign that meets NFPA 13 (2022) Section 29.4.
The hydraulic calculation cannot be found. The installing contractor is gone and the landlord’s file holds only the drawings. Fix: re-calculate from the as-builts and a current flow test, and keep the result with the NFPA 25 records as the new design basis.
Plastics creep. The placard says Class III or IV and the tenant’s product is cartoned Group A plastics, or the pallets are plastic, or the loads are stretch-wrapped over the top. Fix: classify under NFPA 13 (2022) Chapter 20 using the actual plastic share, then limit the plastics to areas the design covers or upgrade the protection.
Racks taller than the design. The placard states 20 ft and the racks are 28 ft. Fix: hold storage at the placard height with the top beam level left empty and written into the lease, or add in-rack sprinklers or an ESFR design rated for the new height.
Solid shelving. Plywood or sheet steel decking blocks water from reaching the lower tiers. Fix: swap to decking that is more than 50 percent open with flues maintained (NFPA 13 (2022) Section 20.5.3.1.1), or add in-rack sprinklers below the solid shelves (Section 20.19.3, with the in-rack design in Chapter 25).
ESFR obstructed by new work. Ducts, high-bay lights, conveyors or a mezzanine sit inside the obstruction zones ESFR sprinklers need. Fix: relocate the obstruction or add sprinklers below it under the NFPA 13 (2022) Chapter 14 obstruction rules.
Old flow test. The supply curve on the calculation dates from the original construction. Fix: run a new test to NFPA 291 and re-plot; supplies in older industrial areas often drop 10 to 20 psi over a decade.
Dry system with no accelerator. A dry pipe system over an unheated dock or freezer delivers water late, and storage designs assume wet-pipe delivery unless the design accounts for the delay. Fix: check the water delivery time against the limit NFPA 13 sets for dry systems protecting storage, add a quick-opening device, or convert the area to a wet or preaction system.
Red flag: a landlord’s statement that the building is “fully sprinklered” or “ESFR protected” is not an evaluation. ESFR sprinklers have height and commodity limits of their own, and a K-14.0 ESFR system designed for 30 ft of Class IV under a 35 ft ceiling does not protect exposed plastics or a 40 ft ceiling. The placard and the calculation, not the brochure, state what the system covers.
Figure 3: Three Outcomes of the Evaluation
What Happens After the Evaluation Is Approved
An evaluation that ends in outcome A or B is only as good as the limits the tenant keeps. The operating limits, such as a maximum storage height, a ban on exposed plastics or a minimum aisle width, are written into the lease as a storage exhibit and into the high-piled storage plan on file with the fire code official. Fire inspectors measure against the plan on file, and a tenant who stacks one beam level higher than the plan has created a violation even when the racks were never touched.
The evaluation is re-checked whenever the tenant’s product mix changes, since NFPA 25 (2023) Chapter 4 requires the owner to evaluate the system before such a change. NFPA 25 sets no annual building review, but many owners re-check once a year. In New York City the FDNY high-piled storage permit renews each year after inspection, which makes that a natural date. Where DGA provides the annual look, it runs as a PE site inspection under the firm’s fire protection inspection service, separate from the contractor’s NFPA 25 testing.
The sealed evaluation, the classification letter, the flow test and any re-calculated hydraulics stay with the sprinkler records for the life of the system. The next tenant’s evaluation then starts from a known design basis, which is the difference between a 2 week evaluation and a 6 week one.
Field Note
The finding DGA’s engineers meet most often on a warehouse tenant change is a placard that reads Class III at 20 ft while the incoming tenant plans cartoned unexpanded plastics at 28 ft in double-row racks. The second most common is no placard at all, with the calculations gone when the installing contractor closed. In both cases the tenant has usually signed the lease before anyone looked at the riser, so the operating limits end up negotiated after the fact instead of written in at signing.
Key Takeaway: Checking a warehouse’s sprinklers for a new tenant means comparing the design basis on the hydraulic design information sign (NFPA 13 (2022) Section 29.4) and in the calculations with the tenant’s commodity, height and arrangement classified under NFPA 13 Chapter 20, verifying the water supply with a flow test under 12 months old, and walking the floor. The sealed result is one of three outcomes, and NFPA 25 (2023) Chapter 4 makes the owner responsible for getting it done before the use changes. As of October 2026 the evaluation takes 2 to 6 weeks when the records exist.
Frequently Asked Questions
Does a new tenant require a sprinkler evaluation if the racks and sprinklers are not changing?
Yes. NFPA 25 (2023) Chapter 4 makes the owner responsible for evaluating the system whenever the occupancy, use, process or materials change, and a new tenant’s commodity, packaging or height can exceed the design basis without a single sprinkler or rack moving. The fire code official also expects an updated high-piled storage plan when the storage changes.
What does the hydraulic design information sign on the riser tell an engineer?
The sign states what the system was designed to protect: the design area location and size, the discharge density or pressure, the flow and pressure required at the base of the riser, the occupancy or commodity class with the maximum storage height and configuration, the hose stream allowance and the installing contractor’s name, under NFPA 13 (2022) Section 29.4 (Section 28.5 in the 2019 edition). It is the starting point of every tenant evaluation.
How old can the hydrant flow test be for a sprinkler evaluation?
Conditional: NFPA 13 (2022) Section 4.5.1.1 limits the flow test to 12 months before the working plans are submitted unless the AHJ approves otherwise, and most reviewers in the region apply the same 12 months to an evaluation, with the test run to NFPA 291. Water supplies in older industrial areas commonly lose 10 to 20 psi over a decade, so an old test can hide a shortfall at the new demand.
Who pays for the sprinkler evaluation, the landlord or the tenant?
Conditional: the lease decides. The owner holds the NFPA 25 duty to evaluate, but many industrial leases assign the cost of any change driven by the tenant’s storage to the tenant, including the evaluation, the storage plan and any sprinkler modification. The records themselves, the placard, as-builts and calculations, are the landlord’s to provide.
Can a tenant move in before the sprinkler modification is complete?
No, not with the storage that triggered the modification. The fire code official can allow occupancy with storage held to the limits the existing system covers, documented in an interim storage plan, until the permit work is accepted. In New York City the FDNY high-piled storage permit is not issued until the inspection passes.
More in Storage and Commodities
- When Does IFC Chapter 32 Apply to High-Piled Storage?
- Why Do Freezer Sprinkler Pipes Get Ice Plugs?
- What Fire Protection Does a Warehouse Need?
- What Fire Protection Do Cold Storage and Food Plants Need?
- What Rules Apply to Carpet, Mattress and Furniture Storage?
- What Fire Protection Does a Retail Store Need?
This article is general information, not a code determination for any project. Code editions, local amendments and reviewer practice change; confirm the adopted code and the authority having jurisdiction for the building before relying on an existing sprinkler system for a new use.
Taking a New Tenant Into an Existing Warehouse?
Send the placard photo, the sprinkler drawings and the tenant’s product list and rack layout. DGA classifies the commodity, compares it with the design basis and issues the sealed gap report before the lease is signed. Project briefs get confirmation and preliminary code feedback within one business day.