Water Supply · Process
What happens at a diesel fire pump acceptance test?
Reviewed by a licensed Professional Engineer · NY, NJ, PA, MD, DE, WA, OR, FL · Last reviewed · Code basis: NFPA 20 (2022); NFPA 22; NFPA 25 for the annual test that follows
General guidance, not a code determination for any project. Confirm the adopted code and local amendments with the authority having jurisdiction.

A diesel fire pump acceptance test is the field test under NFPA 20 Chapter 14 that proves a new fire pump installation works before it goes into service: the pump is run at churn, 100 percent and peak flow against the manufacturer’s certified curve, started at least six times automatically and six times manually, and the pump room, suction piping, fuel system, exhaust and controller are checked against the standard with the manufacturers’ representatives present. Under NFPA 20 (2022 edition) the test is required for every new fire pump, and the authority having jurisdiction usually witnesses it.
For building owners, the acceptance test is the single most important quality checkpoint in a fire pump project. This guide walks through what happens before, during and after the test, based on the acceptance checklist DGA uses in the field.
At a Glance: Diesel Fire Pump Acceptance Test
- Who attends: the pump, engine and controller manufacturers or their factory-authorized representatives (NFPA 20 Chapter 14), the installing contractor, the owner’s representative and usually the authority having jurisdiction.
- Where it happens: in the pump room, with water flowing to the test header or flowmeter; the fire pump submittal is approved first by the building or fire official named in the jurisdiction table below.
- Documents required: the certified factory pump curve, gauge calibration records, flow coefficient data for the diffusers and nozzles, and the completed acceptance checklist.
- Timeline: plan a full day on site; deficiencies found at the test typically add 1 to 4 weeks for correction and retest (as of October 2026).
- Most common failure: an incomplete installation, usually unfinished wiring or a missing manufacturer’s representative, which means the test has to be rescheduled.
- Approval document: the field test results compared with the certified curve, kept with the photo record as the baseline for every NFPA 25 annual test that follows.
What a fire pump acceptance test proves
Every fire pump is tested at the factory before it ships, and that test produces the certified pump test curve. The field acceptance test answers a different question: does the complete installation perform as designed, in place, under the conditions it will actually see?
During the acceptance test, water is flowed at several points across the pump’s range and the results are compared against the certified curve. Field results should meet or exceed the curve, or fall within the margin of error of the calibrated test gauges. If they do, the installation is sound. If they do not, something in the installation needs attention before anyone signs off.
Figure 1: The five stages of the test day

How to prepare for a diesel fire pump acceptance test
A smooth acceptance test starts well before water flows. Three things need to be in place: the right people, a finished installation and the right equipment.
Who must be present
NFPA 20 requires the pump manufacturer, the engine manufacturer (for a diesel driver) and the controller manufacturer, or their factory-authorized representatives, to be present for the field acceptance test. Their presence matters because installation problems are cheapest to fix while everyone with authority over the equipment is standing in the pump room.
Electrical work and pump rotation
All electrical wiring must be completed and checked by the electrical contractor before initial startup. That includes wiring to any motors, control interwiring between multiple pumps, normal and alternate power supplies where provided, and the jockey pump. Pump rotation direction is verified at this stage as well.
Acceptance should never be granted on the assumption that an incomplete installation will be finished correctly later.
What to have on hand
- The manufacturer’s certified pump test curve, for comparison against field results.
- Calibrated test equipment capable of measuring net pump pressure, flow rate, volts and amperes, and speed. Ask for calibration documents for the suction, discharge and pitot gauges, and flow coefficient data for the flow diffusers, playpipes and nozzles.
- A camera. Photograph and video the entire pump room, plus every equipment placard: the fire pump, engine, controller, jockey pump and its motor and controller, and pressure relief valves. Take more photos than you think you need.
What is tested during a fire pump acceptance test
The required flow test points depend on whether the fire pump runs at constant speed or uses variable-speed controls.
| Pump configuration | Required test points |
|---|---|
| Constant-speed | Churn (0 percent flow), rated flow (100 percent) and peak load (generally 150 percent of rated flow) |
| Variable-speed, in variable-speed mode | No flow, 25, 50, 75, 100, 125 and 150 percent of rated load |
| Variable-speed, with variable-speed equipment disengaged | Minimum, rated and peak loads at rated speed |
Peak load is the flow rate that requires the most horsepower, and it can occur below 150 percent of rated flow. A factory curve that shows horsepower draw identifies where it falls. For variable-speed pumps, the extra test points confirm that both the pump and the variable-speed pressure limiting control (VSPLC) are operating correctly.
Figure 2: Field results against the certified curve

Diesel pumps with a pressure limiting driver (PLD)
Many diesel fire pumps use a pressure limiting driver, which slows the engine at low flows so discharge pressure stays below the system’s pressure rating, commonly 175 psi for sprinkler systems. As flow increases, the PLD brings the engine back up to rated speed. Where a PLD is installed, the review also confirms its 1/2 in. sensing line, which is typically connected between the discharge flange and the discharge check valve.
Full-load start
The pump is brought from a standstill to rated speed without interruption while discharging at peak load.
Six automatic and six manual starts
NFPA 20 calls for no fewer than six automatic and six manual operations during the acceptance test, proving the starting systems work repeatedly, not just once. For diesel engines, a 5-minute run at full speed between successive starts is not required until cumulative cranking time reaches 45 seconds.
Post-test installation review: What gets checked
Passing the flow test is necessary but not sufficient. The post-test review walks the installation against NFPA 20, and diesel drivers bring their own list. These are the items owners most often ask about.
Pump room
- Fire separation: indoor pump rooms need 2-hour separation without sprinklers or 1-hour separation with sprinklers, except in high-rise buildings, which need 2-hour separation either way. Outdoor pumps need 50 ft of clearance.
- Sprinkler protection: designed per NFPA 13 as an Extra Hazard Group 2 occupancy. DGA recommends high-temperature (286 degree F) sprinklers because of engine exhaust heat, although NFPA does not require them.
- Room conditions: heat, artificial lighting, battery-operated emergency lighting, ventilation, floors sloped to drains, and guards on shaft couplings. Room temperature must stay at or above the engine manufacturer’s recommended minimum.
- Ventilation: coordinated with the engine so it operates whenever the engine runs. Motor-operated dampers should spring open and motor closed. In cold climates, keep water-filled piping out from in front of ventilation louvers.
Pressure gauges
The discharge gauge needs a 3.5 in. dial, a 1/4 in. gauge valve, and a range of at least twice the pump’s working pressure, but not less than 200 psi. The suction gauge is a 3.5 in. compound pressure and vacuum gauge with a range of twice the pump’s rated maximum suction pressure.
Suction piping
- A listed OS&Y gate valve in the suction pipe, with no other valve within 50 ft of the suction flange.
- No elbows or tees with a centerline parallel to the pump shaft within 10 pipe diameters of the suction flange.
- An eccentric reducer, properly oriented, wherever a reducer is needed on the suction side.
- Backflow preventers at least 10 pipe diameters from the suction flange, or at least 50 ft if the assembly incorporates butterfly valves.
- Suction and bypass piping sized per NFPA 20 Table 4.28(a).
- Strain relief where the pump and the suction supply sit on separate foundations.
Figure 3: Suction piping rules in plan

Discharge piping, test header and valve supervision
- A listed check valve or backflow preventer in the discharge assembly, with a listed indicating gate or butterfly valve on the system side of the check valve.
- Suction, discharge, bypass and backflow isolation valves supervised open. Test outlet valves supervised closed.
- Where a flowmeter is installed, it must be capable of at least 175 percent of rated pump capacity.
- Listed hose valves on the test header, sized per Table 4.28(a), with an automatic ball drip at the low point of the header supply line.
- Hose header supply piping longer than 15 ft goes up one pipe size from Table 4.28(a), unless it is hydraulically calculated for 150 percent of rated capacity and proven by a full flow test.
- Flowmeter piping kept within 100 ft of equivalent length, or the next larger meter size is required.
Jockey pump, relief valves and pipe supports
- Jockey pump: steel pipe only for its suction and discharge lines, with a check valve and an isolation valve in the discharge line. If its shutoff pressure exceeds the working pressure rating of the system, typically 175 psi, it needs a relief valve on its discharge.
- Pressure relief valves, where provided: located between the pump and the discharge check valve, discharging into an open pipe or cone so flow is visible, with no shutoff valve in the supply or discharge piping. If the discharge pipe has more than one elbow, it goes up one pipe size.
- Pipe stands: stands under 4 ft tall can be 2 in. pipe. Each stand is anchored to the floor with at least two anchors, or four if it is over 4 ft tall.
- Seismic bracing: per NFPA 13 where required, with a flexible coupling at the base of any riser that is part of the pump discharge.
Pressure sensing line
The sensing line must be 1/2 in. nominal brass, copper or stainless steel, with two ground-face unions at least 5 ft apart drilled with 3/32 in. orifices. Where the water is not clean, check valves with a 3/32 in. hole drilled in the clapper are required instead. No shutoff valves are permitted in the line.
Diesel fuel system
Each engine needs its own fuel tank and fuel line. Under NFPA 20 (2022), the tank must hold at least 12 hours of engine run time based on the engine’s fuel consumption rate, plus 5 percent volume for expansion and 5 percent for sump. If the consumption rate is not known, the tank should hold at least 1 gallon per horsepower, plus the same 5 percent allowances.
Figure 4: Fuel tank sizing under NFPA 20

- Double-walled tanks: the space between the walls must be monitored for fuel leakage.
- Vents: a 2 in. normal vent and a 4 in. emergency vent, with outlets at least 5 ft from building openings and at least 12 ft above finished grade.
- Level indicator: activates at the two-thirds tank level.
- Tank elevation: the fuel supply outlet can be no lower than the centerline of the engine’s fuel transfer pump.
- Fuel piping: no galvanized steel or copper (black steel is preferred), listed flame-resistant flexible hoses at the engine, and guards on any line exposed to mechanical damage.
- Valves: the fuel supply valve is locked open, and no other valve is allowed in the supply line. No shutoff valve is allowed in the return line.
- Labeling: the fuel grade is marked on the tank in 2 in. letters.
Exhaust system
- An independent exhaust system for each engine.
- A stainless steel corrugated flexible connector, at least 12 in. long, between the engine exhaust outlet and the exhaust pipe.
- High-temperature insulation, with the exhaust pipe and muffler supported independently of the flexible connector.
- At least 9 in. of clearance to combustible materials.
- Discharge to a safe location outside the pump room, arranged to exclude water.
Figure 5: Exhaust, batteries and controller in elevation

Starting batteries and engine controller
- Batteries rack-supported above the floor, secured against movement, with current-carrying parts at least 12 in. above the floor, and not located in front of the engine-mounted instruments and controls.
- The controller located as close as practical to the engine and within sight of it, in a minimum NEMA Type 2 drip-proof enclosure.
- Neither the controller enclosure nor the engine control panel used as a junction box for other equipment or AC supply.
- Where the pump supplies deluge or dry pipe valves, the controller starts the engine when that equipment activates.
- Where multiple pumps are installed, controllers start them in sequence at 5- to 10-second intervals.
Suction tanks, where provided
Where a suction tank supplies the pump, NFPA 22 and related standards add their own checks:
- Heaters where the design requires them for cold weather, with a thermometer, plus a low water temperature supervisory switch.
- Water level supervisory switches.
- Fill valve supervision: the manual fill valve and automatic fill bypass supervised closed, automatic fill isolation valves supervised open, and the automatic fill solenoid controlled by a fire alarm control module.
- Confined-space entry signage at each manway.
- Grounding lugs connected to a grounding rod, and finished grade at least 6 in. below the top of the ring wall foundation.
Documentation owners should keep after the test
When the acceptance test is done, the owner should walk away with the manufacturer’s certified pump test curve, the field test results, the gauge calibration records and flow coefficient data, the completed acceptance checklist, and the photo and video record. Together, these form the baseline that every future annual fire pump test under NFPA 25 will be measured against.
When a fire pump fails the acceptance test, the deficiencies are documented and corrected, and the affected portions of the test are repeated. Acceptance is granted only when the installation demonstrates compliance.
Who witnesses the test in each jurisdiction
NFPA 20 is the same everywhere DGA works, and the diesel pump rules above do not change by state. What changes is who approves the fire pump submittal and who comes to witness the acceptance test. Confirm the witness and the notice period with the authority having jurisdiction before scheduling the manufacturers’ representatives.
| Jurisdiction | Code and NFPA 20 edition | Who reviews and witnesses |
|---|---|---|
| New York City | 2022 NYC Building Code and Fire Code; NFPA 20 as referenced | Department of Buildings for the sprinkler or standpipe job that includes the pump, with the special inspector on the TR1; FDNY for fire department connection and standpipe aspects |
| New York State (outside NYC) | 2025 Uniform Code (2024 I-Codes); NFPA 20 as referenced | Local code enforcement official |
| New Jersey | Uniform Construction Code, 2024 I-Codes; NFPA 20 as referenced | Municipal fire protection subcode official |
| Pennsylvania | Uniform Construction Code, 2021 I-Codes; NFPA 20 as referenced | Municipal or third-party code official; Philadelphia L&I in the city |
| Maryland | 2021 IBC; State Fire Prevention Code, NFPA 1 and 101 (2024) | County building official and the State or local fire marshal |
| Delaware | State Fire Prevention Regulations 2026, NFPA 20 (2025 edition listed) | Office of the State Fire Marshal; Wilmington Fire Marshal inside the city |
Editions as listed in DGA’s Fire Code Cheat Sheet for NY, NJ, PA, MD and DE. The NFPA 20 edition that governs is the one referenced by the adopted code, not the newest.
DGA’s fire protection engineers witness and document fire pump acceptance tests, review installations against NFPA 20 and help owners resolve deficiencies before final acceptance across New York, New Jersey, Pennsylvania, Maryland, Delaware, Washington, Oregon and Florida. Project briefs get confirmation and preliminary code feedback within one business day. See Fire Pump Design →
Key Takeaway: never accept a fire pump installation on promises. The acceptance test exists so that every claim about the installation is verified with water flowing and instruments reading. If the manufacturer’s representatives are not in the room, the wiring is not finished or the gauges are not calibrated, reschedule.
Frequently asked questions
When is a fire pump acceptance test required?
After every new fire pump installation and before the pump is placed in service. NFPA 20 Chapter 14 requires the field acceptance test, and the authority having jurisdiction typically witnesses it.
Who needs to be present at a fire pump acceptance test?
At minimum, the pump, engine and controller manufacturers or their factory-authorized representatives (NFPA 20 Chapter 14). The installing contractor and the owner’s representative typically attend, and the authority having jurisdiction is often present as well.
What is a churn test on a fire pump?
Churn is the pump running at zero flow, with no water leaving the system. It establishes the maximum pressure the pump can develop, which NFPA 20 limits to 140 percent of rated pressure, and it is one of the three standard test points for constant-speed pumps.
How big does a diesel fire pump fuel tank need to be?
At least 12 hours of engine run time at the engine’s fuel consumption rate, plus 5 percent for expansion and 5 percent for sump, under NFPA 20 (2022) Chapter 11. If the consumption rate is not known, at least 1 gallon per horsepower plus the same allowances. Each engine needs its own tank.
Is an acceptance test the same as the annual fire pump test?
No. The acceptance test under NFPA 20 happens once, before the pump is placed in service. After that, NFPA 25 governs ongoing inspection, testing and maintenance, including an annual flow test whose results are compared against the acceptance test baseline.
More in Water Supply
- Do You Need a Fire Pump? How Engineers Decide (NFPA 20)
- Water Supply for Fire Protection: The Complete Guide
- What Is a Fire Pump Controller and Transfer Switch?
- When Can a Well or Private Source Supply Fire Protection?
- What Is Backflow Preventer Pressure Loss in Sprinkler Calcs?
- Split-Case vs In-Line vs Vertical Turbine: Which Fire Pump?
This article is general information, not a substitute for a project-specific evaluation. Confirm the adopted code edition, the referenced NFPA 20 edition and the witnessing requirements with the authority having jurisdiction.
Fire Pump Acceptance Test Coming Up?
Send the pump submittal, the certified curve and the test date. DGA reviews the installation against NFPA 20, witnesses the test and documents the baseline. Project briefs get confirmation and preliminary code feedback within one business day.