Sprinkler Systems · Process

How does a sprinkler acceptance test work?

General guidance, not a code determination for any project. Confirm the adopted code and local amendments with the authority having jurisdiction.

A sprinkler acceptance test proves a finished system before the building is occupied: the underground main is flushed and tested, the installing contractor pressure tests the sprinkler piping, runs the valve, alarm and drain tests and signs the contractor’s material and test certificate, and the authority having jurisdiction (AHJ), or the inspector it accepts, witnesses the tests before signing the system off.

The tests come from the National Fire Protection Association (NFPA) standard NFPA 13, in the edition each jurisdiction enforces; who witnesses them and which document closes the job come from local law. This article follows the acceptance sequence in New York City (NYC), New York State, New Jersey, Pennsylvania, Maryland and Delaware as of November 2026. The plan review that comes before it is covered in DGA’s guide to how a sprinkler plan review and approval works.

At a Glance: Sprinkler Acceptance Test

  • Who files: the installing sprinkler contractor runs the tests and signs the certificate; the permit holder requests the inspection with the notice the AHJ sets, and in NYC a special inspection agency registered with the Department of Buildings (DOB) witnesses and certifies the tests.
  • Where it is filed: with the office that issued the sprinkler permit, such as DOB through the job’s TR1 (Technical Report: Statement of Responsibility) in NYC, the fire protection subcode official in New Jersey, the county in Maryland or the State Fire Marshal in Delaware.
  • Documents required: the contractor’s material and test certificates for aboveground and underground piping, the hydraulic design information sign posted at the riser, the approved drawings on site, and local forms such as Pennsylvania’s form UCC-12 or the data New Jersey requires on its form F380 sign.
  • Timeline range (as of November 2026): the hydrostatic test holds for 2 hours (1 hour in NYC) and a dry pipe or double interlock system adds a 24-hour air test; New Jersey inspects within 3 business days of a written request, and Pennsylvania issues the certificate of occupancy within 5 business days of a passing final inspection report.
  • Most common rejection: a pressure drop or visible leak during the hydrostatic test, or piping concealed before the witness has seen it tested.
  • Approval document: the AHJ’s sign-off, such as the DOB Letter of Completion in NYC, a certificate of approval or certificate of occupancy in New Jersey, or the county or city certificate of occupancy after Delaware’s State Fire Marshal accepts the system.

What does a sprinkler acceptance test prove, and who witnesses it?

An acceptance test proves three things the drawings cannot: the piping holds pressure without leaking, the valves, alarms and drains work as installed, and the finished system matches the approved design that its signs and certificate record. NFPA 13 puts the tests on the installing contractor, who tells the AHJ and the owner when testing will happen, performs every required acceptance test, completes and signs the contractor’s material and test certificate, and removes the protective caps and straps from the sprinklers before the system goes into service (Section 29.1 in the 2022 edition).

The building codes decide who has to be present and when the building may open. Section 901.5 of the International Building Code (IBC) has fire protection systems tested at the owner’s expense, in the presence of the building official where the code requires it, and bars occupancy of any part of a structure until the required fire protection systems in that part are tested and approved. The 2022 NYC Building Code keeps the same occupancy bar in its own Section 901.5, with the tests run in the presence of DOB or an approved agency.

Who actually stands at the riser differs by jurisdiction. In NYC a special inspector from a DOB-registered agency that is independent of the installer witnesses the tests and certifies them on the TR1 under Building Code Section 1705.29, as DGA’s article on what a TR1 special inspection for sprinklers covers explains. Elsewhere a code official, fire protection subcode official, county inspector or State Fire Marshal inspects the work, as the table below shows.

JurisdictionCode and NFPA 13 editionLocal acceptance ruleWho inspects or witnessesSign-off document
New York City2022 NYC Construction Codes; NFPA 13 (2016) as modified by Building Code Appendix QAppendix Q (Section Q102) has the installing contractor inspect and test the system before an inspection is scheduled, and shortens the hydrostatic test from 2 hours to 1 hourA special inspector from a DOB-registered agency, who certifies the tests on the TR1 (Building Code Section 1705.29); DOB then signs off the permitSprinkler (SP) permit sign-off, then the DOB Letter of Completion (Administrative Code Section 28-116.2.4.2), or the certificate of occupancy where the job changes it
New York State (outside NYC)2025 Uniform Code, based on the 2024 I-Codes; NFPA 13 (2022)Work stays accessible and exposed until the code enforcement official inspects and accepts it (Title 19 of the New York Codes, Rules and Regulations, 19 NYCRR 1203.3(b)); each local program sets its own test and notice rulesThe local code enforcement program (city, town, village, county or Department of State), which must inspect fire protection systems and make a final inspectionCertificate of occupancy or certificate of compliance (19 NYCRR 1203.3(d))
New JerseyUniform Construction Code (UCC) on the 2024 I-Codes, effective August 17, 2026; NFPA 13 (2022)IBC Section 903.5 as amended (New Jersey Administrative Code, N.J.A.C. 5:23-3.14(b)8): NFPA 13 tests, waterflow devices and alarm circuits proved at the test pipe, and water at a dry pipe system’s test pipe within 60 secondsFire protection subcode official or inspector; fire suppression is a mandatory inspection, and the final inspection covers the subcode tests and the posted design sign (N.J.A.C. 5:23-2.18)Certificate of approval for work in an existing building; certificate of occupancy for a new building (N.J.A.C. 5:23-2.23)
PennsylvaniaUCC on the 2021 I-Codes since January 1, 2026; NFPA 13 (2019)The permit holder gives notice when work is ready and keeps it exposed until inspected (Title 34 of the Pennsylvania Code, 34 Pa. Code 403.45); where the Department of Labor and Industry (L&I) is the code official, the installer signs form UCC-12The municipal code official or its third-party agency, or L&I; Philadelphia’s Department of Licenses and Inspections; Pittsburgh’s Department of Permits, Licenses, and Inspections (PLI)UCC certificate of occupancy (34 Pa. Code 403.46); a Certificate of Approval closes a Philadelphia Fire Suppression Systems Permit
Maryland2021 IBC through the county permit, NFPA 13 (2019); the State Fire Prevention Code (NFPA 1, 2024) references NFPA 13 (2022)Baltimore County inspects every sprinkler installation visually, witnesses a hydrostatic test when more than 20 sprinklers are installed, wants the piping exposed and unpainted until approval, and fails any pressure loss or visible leakThe county fire marshal or inspector, such as the Baltimore County Fire Marshal; a third-party Fire Protection Systems Inspector of Record on Prince George’s County Third-Party Inspection Program projects; Office of the State Fire Marshal inspectors where the state reviewsCounty use and occupancy permit after the fire protection inspections; Baltimore City calls it an occupancy permit
DelawareState Fire Prevention Regulations, Regulation 701 (2026 edition); NFPA 13 (2025); IBC by countyThe hydrostatic test is witnessed before close-in, the acceptance test comes before the building or tenant space is occupied, and the aboveground certificate is completed at the acceptance testOffice of the State Fire Marshal, New Castle, Kent and Sussex divisionsState Fire Marshal acceptance test and final inspection, then the county or city certificate of occupancy

As of November 2026. In Maryland, the county building permit reviews sprinklers to NFPA 13 (2019) through the 2021 IBC, while the State Fire Prevention Code (NFPA 1, 2024) references NFPA 13 (2022). In Wilmington, Dover, Newark and the City of New Castle the city fire marshal reviews sprinkler work instead of the State Fire Marshal and may set its own steps.

Which sprinkler acceptance tests are run, and in what order?

NFPA 13 collects the acceptance tests in its systems acceptance chapter: Chapter 29 of the 2022 and 2025 editions, Chapter 28 of the 2019 edition, and Chapter 25 of the 2016 edition that NYC modifies through Appendix Q. The order below keeps a failed test from undoing work that has already passed, and the table after it gives what each test has to show.

  1. Pre-test and book the inspection. The installing contractor runs the tests once without the witness, then requests the inspection with the notice the AHJ sets. NYC’s Appendix Q makes the pre-test a rule, and New Jersey wants the request in writing at least 24 hours ahead (N.J.A.C. 5:23-2.18(c)).
  2. Flush and test the underground main. The private fire service main and every lead-in are flushed until the water runs clear and hydrostatically tested under NFPA 24, the private fire service main standard, and only then is the lead-in bolted to the riser. DGA’s guide to how underground fire mains are flushed and tested covers the flushing rates and the makeup water allowance.
  3. Hydrostatic test before close-in. The aboveground piping is filled, vented and held at the test pressure while the witness watches the gauge and walks the piping. The test runs before walls and ceilings close, and in Delaware the State Fire Marshal witnesses it at that stage.
  4. Air test on dry pipe and double interlock preaction systems. These systems also hold air pressure for 24 hours, because they spend their service life holding air rather than water.
  5. Operating tests. Water flows through the inspector’s test connection to prove the waterflow alarm; dry pipe, preaction and deluge valves are tripped; every control valve is cycled; the main drain is opened full; and a backflow preventer is forward flow tested.
  6. Certificate and signs. The contractor completes and signs the material and test certificate, posts the hydraulic design information sign and the general information sign, and takes the protective caps and straps off the sprinklers.
  7. Final inspection and sign-off. The AHJ checks the paperwork and the installation against the approved drawings and issues its closing document.

Figure 1: From underground flush to sign-off

1. Underground flush and testFlushed until clear and pressure tested to NFPA 24 before the riser tie-in
2. Hydrostatic test before close-in200 psi for 2 hours, or 50 psi above a working pressure over 150 psi; 1 hour in New York City
3. Air test for dry and double interlock systems40 psi for 24 hours, losing no more than 1.5 psi
4. Operating testsWaterflow alarm, valve trips, control valves, main drain and backflow preventer
5. Certificate and signsCertificate signed, design and information signs posted, sprinkler caps and straps off
6. Final inspection and sign-offThe AHJ’s closing document, such as a Letter of Completion, certificate of approval or certificate of occupancy
NFPA 13 holds the aboveground piping at 200 psi for 2 hours before it is concealed, or 1 hour in New York City under Building Code Appendix Q, adds a 24-hour air test at 40 psi for dry pipe and double interlock preaction systems, and has the installing contractor sign the material and test certificate before the AHJ signs the system off.
TestWhenWhat has to pass (paraphrased)Where it sits
Underground flush and hydrostatic testBefore the lead-in is connected to the riserWater runs clear at the flushing rate for the pipe size; the test pressure holds with makeup water inside the allowanceNFPA 24, Chapter 10 (2022 edition)
Aboveground hydrostatic testPiping complete, before walls and ceilings close200 psi held for 2 hours, or 50 psi above the maximum system working pressure where that pressure exceeds 150 psi, with no drop on the gauge and no visible leakageNFPA 13 (2022) Sections 29.2.1.1 and 29.2.1.3 (28.2.1.1 in 2019; 25.2.1.1 in 2016); 1 hour in NYC (Appendix Q, Section Q102)
Air pressure testDry pipe and double interlock preaction systems, in addition to the hydrostatic test40 psi held for 24 hours, losing no more than 1.5 psiNFPA 13 (2022) Section 29.2.2.1
Waterflow alarm testAlarm devices and their connections completeFlow through the inspector’s test connection starts the alarm; NFPA 72, the fire alarm code, has the waterflow device activate within 90 secondsNFPA 13 (2022) Section 29.2.3.1; NFPA 72 (2022) Section 17.13.2; IBC Section 903.5.1 as amended in New Jersey
Dry pipe valve trip testAfter the air testThe valve trips with the inspector’s test connection fully open; trip and water delivery times are recorded and stay within any delivery limit the design relied on; 60 seconds in New JerseyNFPA 13 (2022) Section 29.2.3.2; delivery limits in Section 8.2.3
Preaction and deluge valve testDetection and release system completeAutomatic operation through the detection and release system, plus any manual or remote releaseNFPA 13 (2022) Section 29.2.3.3
Main drain testControl valves fully openStatic and residual pressures recorded as the baseline for later testsNFPA 13 (2022) Section 29.2.3.4
Control valves and backflow preventerBefore the system goes into serviceEach control valve closed fully and reopened under system pressure; the backflow preventer forward flow tested at the system demandNFPA 13 (2022) Section 29.2.3.5 for the control valves; Section 16.14.5.1 for the backflow test connection
Signs and certificateEnd of testingHydraulic design information sign and general information sign posted; material and test certificate completed and signedSections 29.4 and 29.6 (2022), with the certificate form in annex Figure A.29.1; Sections 28.5 and 28.6 (2019); Section 29.4 (2025)

Pass criteria are paraphrased from NFPA 13 and NFPA 72. The edition the AHJ enforces and its test procedure govern on the job.

Additions to an existing system are tested the same way, scaled to the work. NFPA 13 lets a modification affecting 20 or fewer sprinklers be tested at system working pressure instead of the full hydrostatic pressure, while a larger addition is isolated and given the full hydrostatic test (NFPA 13 (2022) Sections 30.8.1 and 30.8.1.1; Section 30.7.1.1 in 2025). A modified dry pipe or double interlock preaction system gets a shorter air test than a new one: 40 psi for 2 hours with no more than 3 psi lost, or 4 hours with the air supply shut off and no low air alarm (2022 Section 30.8.2). Local rules draw their own lines: Baltimore County witnesses a hydrostatic test when more than 20 sprinklers are installed, and New Jersey tests a limited area system that is not connected to a standpipe for at least 15 minutes at its working pressure with no visible leakage (IBC Section 903.5.2 as amended).

Opens the Project Desk with your sentence. Our licensed PEs review every brief and reply within one business day.

Which documents are signed at sprinkler acceptance, and who prepares each?

Acceptance ends in paper as much as in water. Each document below records a test result or a design fact that the AHJ checks before sign-off and the owner keeps afterward, and which ones a job needs depends on its scope and jurisdiction.

DocumentWho prepares and signs itWhenWhere it goes
Contractor’s Material and Test Certificate for Aboveground PipingThe installing contractor completes and signs it, and the owner’s representative signs as witnessAt the acceptance testThe AHJ and the owner: completed at the acceptance test in Delaware, due before the final inspection in Pittsburgh, and on site for Baltimore County’s inspector
Contractor’s Material and Test Certificate for Underground PipingThe underground or sprinkler contractor, with the owner’s representative; Delaware uses its own Material and Test Certificate for Underground PipeAfter the underground flush and hydrostatic test, before the riser tie-inThe AHJ before the final inspection, and the owner
Hydraulic design information signThe installing contractorBefore the final inspectionAt each system riser, floor control valve assembly and valve that supplies the hydraulically designed area (NFPA 13 (2022) Section 29.4); in New Jersey it carries the data on New Jersey Department of Community Affairs (DCA) form F380 (N.J.A.C. 5:23-3.5(d))
Contractors’ Installation Certification, form UCC-12 (Pennsylvania)The installing contractor, where L&I is the code officialBy the L&I inspectionKept on site for the L&I inspector
Statement of Compliance and Hydrant Flow Test Report (Pittsburgh)The permit holder submits bothBefore the final inspectionPLI; the flow test report covers new sprinkler systems, underground fire mains and private hydrants
As-built drawings, hydraulic calculations and device data sheetsThe installing contractor, with the design team for the calculationsAt turnoverThe owner, kept for the life of the system (NFPA 25 (2023) Section 4.3.4)

The aboveground certificate is the central record, because it puts the test pressures and durations, the valve trip and water delivery times and the main drain readings in one place, with the signatures of the people who saw them. A missing signature, or a new underground main with no signed underground certificate, leaves the AHJ without the record it signs off against.

What is the hydraulic design information sign, and what goes on it?

The hydraulic design information sign is the permanent sign the installing contractor attaches to a hydraulically designed sprinkler system. NFPA 13 (2022) places it at every system riser, floor control valve assembly and alarm, dry pipe, preaction or deluge valve that supplies the design area, unless the AHJ approves another location. NFPA 13 requires it in Section 29.4 of the 2022 and 2025 editions and Section 28.5 of the 2019 edition, and it is checked at acceptance because it is the system’s own record of what it was designed to protect. In paraphrase, the sign gives six items:

  • where each design area is, and in the 2022 edition its size or the number of sprinklers in it
  • the discharge density over each design area
  • the flow and residual pressure the system needs at the base of the riser
  • the occupancy or commodity classification, with the maximum storage height and arrangement the design allows
  • whether a hose stream allowance is included in the demand
  • the name of the installing contractor

New Jersey writes the sign into its own rule: the fire sprinkler contractor identifies a hydraulically designed system with a permanent weatherproof metal or rigid plastic sign at the alarm valve, carrying the design information on DCA form F380 in place of the NFPA nameplate, and the final inspection checks that it is posted (N.J.A.C. 5:23-3.5(d) and 5:23-2.18). Baltimore County’s Fire Marshal expects a hydraulic data plate in the riser room on inspection day.

NFPA 13 also calls for a general information sign with basic data about the system (Section 29.6 in 2022; Section 28.6 in 2019). After acceptance the hydraulic sign does its longest work: NFPA 25 (2023), the Standard for the Inspection, Testing and Maintenance of Water-Based Fire Protection Systems, has the owner evaluate the system before changing the use, process or materials stored (Section 4.1.6), and the sign shows the hazard, density and storage height that evaluation starts from.

How long does sprinkler acceptance take, and what delays it?

The tests set part of the schedule themselves. The hydrostatic test holds for 2 hours under NFPA 13, or 1 hour in NYC under Appendix Q, and a dry pipe or double interlock preaction system adds a 24-hour air test before its trip test.

A few jurisdictions put inspections and certificates on a clock, as of November 2026. In New Jersey the agency inspects within 3 business days of a written request made at least 24 hours ahead, or at an agreed time up to 30 days, and the certificate issues within 10 business days of a written application (N.J.A.C. 5:23-2.18(c) and 5:23-2.23(j)).

Pennsylvania’s code official issues the certificate of occupancy within 5 business days of receiving a final inspection report that shows compliance (34 Pa. Code 403.46). Baltimore County takes inspection requests by email from the permit holder at least 3 working days ahead. New York State leaves scheduling to each local program.

Delays come from tests that have to be run twice and from work outside the sprinkler permit. A failed hydrostatic or air test means a repair and a full rerun, and in freezing weather NFPA 13 (2022) Section 29.2.1.5 allows an interim air test until the hydrostatic test can be run, without excusing the hydrostatic test itself. The waterflow alarm test needs the fire alarm system ready to receive the signal, and that work runs on its own permit and inspection.

Fire pumps add their own acceptance test under NFPA 20, the fire pump standard, and in Delaware the State Fire Marshal’s acceptance test of an electric fire pump waits for the electrical inspection agency’s final inspection sticker on the controller (Regulation 702, Chapter 4). For the engineering and review stages that come before acceptance, DGA’s Fire Protection Project Timeline Estimator gives a general planning range.

Why do sprinkler acceptance tests fail?

Sprinkler acceptance tests fail on leaks, on sequence and on paperwork, and each failure has a fix that closes it. The table pairs the common reasons with those fixes.

ReasonFix
Pressure drop or visible leak in the hydrostatic testFind and remake the joint or fitting, refill and vent the system, and rerun the full duration; NFPA 13 allows no pressure loss in aboveground piping, and Baltimore County fails any loss or visible leak.
Piping concealed before the witness saw it testedOpen the ceiling or wall over the untested piping; New York State and Pennsylvania keep work exposed until it is inspected (19 NYCRR 1203.3(b); 34 Pa. Code 403.45), and Delaware’s hydrostatic test comes before close-in.
Air test loses more than 1.5 psi in 24 hoursLeak-test the joints, drains and valve trim, repair, and restart the 24-hour test.
Water reaches a dry system’s test connection too slowlyCheck the air pressure, the quick-opening device and the system volume against the design, then retest; New Jersey allows no more than 60 seconds for any dry pipe system.
Waterflow alarm silent or not reaching the fire alarm systemCheck the flow switch, its retard setting and the alarm circuit; NFPA 72 gives the device 90 seconds to activate.
Hydraulic sign missing or not matching the approved calculationsMake the sign from the approved hydraulic calculations and post it at the riser, floor control valve assemblies and supplying valves before the final inspection.
Installed layout differs from the approved drawingsRevise the drawings and have the change approved before the final inspection, because the witness checks against the approved set.

Many of these failures are settled before the witness arrives. The checklist below covers what has to be in place on test day.

Figure 2: Ready for the witness: Test-day checklist

Paperwork on site
  • Approved drawings with the reviewer’s stamp, and the plan review comment letters
  • The permit, and in NYC the TR1 naming the special inspection agency
  • Signed underground certificate where a new main feeds the riser
  • Material and test certificate ready to complete and sign
  • Calibrated test gauges; Baltimore County asks for listed gauges
At the riser and in the field
  • Piping complete, exposed and reachable, with no ceiling closed over untested pipe
  • Painting finished first in NYC where Building Code Section 903.6 calls for it; piping left unpainted in Baltimore County
  • Inspector’s test connection, main drain and alarm devices reachable, with a safe place to discharge
  • Fire alarm ready to receive the waterflow and valve signals
  • Hydraulic design information sign made from the approved calculations
  • Test blanks out, and sprinkler caps and straps ready to come off
Baltimore County’s Fire Marshal fails a sprinkler test on any pressure loss or visible leak and expects the stamped approved plans, the plan comment letters, the aboveground material and test certificate, listed gauges, the permit and a hydraulic data plate in the riser room on inspection day.

What happens after a sprinkler system is accepted?

Sign-off follows the last witnessed test and the paperwork review, and the closing document is the one listed in the jurisdiction table above. In NYC that is the DOB Letter of Completion, or a certificate of occupancy where the job changes it, after the sprinkler permit is signed off; DGA’s article on why the sprinkler Letter of Completion comes from DOB, not the Fire Department of the City of New York (FDNY) walks through that closeout.

The records outlive the permit. NFPA 25 (2023) has the owner keep the as-built drawings, hydraulic calculations, original acceptance test records and device data sheets for the life of the system (Section 4.3.4), and the main drain readings taken at acceptance become the baseline that later main drain tests are compared with.

Inspection, testing and maintenance begin once the system is in service, under the fire code rather than the building permit. In NYC the 2022 Fire Code adds a monthly inspection by a certificate of fitness holder employed by the owner (Fire Code Section 903.5), and in Delaware each system needs an annual Certificate of Inspection filed through a licensed vendor (Regulation 703).

Key Takeaway: A sprinkler acceptance test runs in a fixed order: flush and test the underground, hold the aboveground piping at 200 psi for 2 hours before it is concealed (1 hour in NYC), air test dry pipe and double interlock systems at 40 psi for 24 hours, then prove the alarms, valves and drains and sign the material and test certificate. NFPA 13 sets the tests, and the jurisdiction sets the witness and the sign-off, from a TR1 special inspector and the DOB Letter of Completion in NYC to the State Fire Marshal and a county or city certificate of occupancy in Delaware.

Frequently asked questions

What pressure is used for a sprinkler hydrostatic test?

200 psi for 2 hours under NFPA 13, or 50 psi above the maximum system working pressure where that pressure exceeds 150 psi, with no drop on the gauge and no visible leakage. New York City’s Building Code Appendix Q shortens the test to 1 hour.

Who witnesses a sprinkler acceptance test in New York City?

A special inspector from an agency registered with the Department of Buildings (DOB) and independent of the installer witnesses the hydrostatic and other required tests and certifies them on the job’s TR1 technical report (2022 New York City Building Code Section 1705.29). DOB then signs off the sprinkler permit, and the job closes with a DOB Letter of Completion or a certificate of occupancy.

Does a dry pipe system need an air test?

Yes. Under NFPA 13 a dry pipe system, like a double interlock preaction system, holds 40 psi of air for 24 hours in addition to the hydrostatic test, and a loss of more than 1.5 psi has to be found and corrected. The dry pipe valve is then trip tested and its water delivery time recorded.

What goes on a hydraulic design information sign?

The basis of the hydraulic design: where each design area is (and, in the 2022 edition, its size or the number of sprinklers in it), the discharge density over it, the flow and residual pressure needed at the base of the riser, the occupancy or commodity classification with the maximum storage height and arrangement, whether a hose stream allowance is included, and the installing contractor’s name. NFPA 13 requires the sign in Section 29.4 of the 2022 and 2025 editions and Section 28.5 of the 2019 edition.

Can a building be occupied before the sprinkler acceptance test?

No. The International Building Code and the 2022 New York City Building Code (Section 901.5 in each) bar occupancy of any part of a building until the required fire protection systems in that part are tested and approved, and the Delaware State Fire Marshal’s acceptance test comes before the building or tenant space is occupied. In New York State even a temporary certificate of occupancy needs the required fire protection equipment installed and operational (19 NYCRR 1203.3(d)).

This article is general information, not a code determination for any project. Code editions, local amendments and inspector practice change; confirm the adopted code, the NFPA 13 edition and the test procedure with the authority having jurisdiction for the project.

Getting a Sprinkler System Ready for Acceptance?

Send the address, the permit, the system type and the planned test date. DGA checks the test procedure and the paperwork against the enforced NFPA 13 edition and the AHJ’s rules before test day, and can witness the tests for the owner. Project briefs get confirmation and preliminary code feedback within one business day.

Send a project brief → View related services

Leave a reply

Your email address will not be published. Required fields are marked *

Quick inquiry

Ready when you are.

Your name, a way to reach you, and where the project is. A licensed PE replies within one business day. Every inquiry is confidential.

Prefer to describe it first? Open the Project Desk