How does a sprinkler plan review and approval work?
General guidance, not a code determination for any project. Confirm the adopted code and local amendments with the authority having jurisdiction.
A sprinkler plan review and approval works in one order: the design team files the sprinkler drawings, hydraulic calculations and current water supply data with the authority having jurisdiction (AHJ), the reviewer checks them against the adopted code and the National Fire Protection Association (NFPA) 13 edition that jurisdiction enforces, and installation starts only after the drawings are approved and the permit is issued. After installation the work is inspected and tested, and the AHJ closes the permit with its sign-off document.
The sections below follow that sequence across New York City (NYC), New York State, New Jersey, Pennsylvania, Maryland and Delaware, from who reviews to what happens after approval. Local forms, portals and inspection steps are in DGA’s jurisdiction guides, linked from the table near the end.
At a Glance: Sprinkler Plan Review and Approval
- Who files: the engineer or licensed sprinkler contractor who prepared the drawings, for the owner; in NYC the registered design professional files as applicant of record, and in Delaware the licensed sprinkler company’s certificate holder signs.
- Where it is filed: the building department, construction office or fire marshal that enforces the code at the site, such as the NYC Department of Buildings (DOB) through DOB NOW: Build, the municipal construction office in New Jersey, or a State Fire Marshal division in Delaware.
- Documents required: working plans (shop drawings), hydraulic calculations, a current flow test, product data sheets, the owner’s certificate and the local application form, sealed or signed as the jurisdiction requires.
- Timeline range (as of November 2026): review clocks set by law are 20 business days in New Jersey, 30 business days for commercial work in Pennsylvania and 40 calendar days at NYC DOB; New York State, Maryland and Delaware set none. The clocks cover review only.
- Most common rejection: information the reviewer cannot find or that does not agree, such as a flow test older than 12 months, a hazard class that is not stated, or calculations that do not match the pipe sizes drawn.
- Approval document: approved drawings and a permit before installation; at closeout, the jurisdiction’s sign-off, such as the DOB Letter of Completion in NYC or a certificate of approval or certificate of occupancy in New Jersey.
Who reviews sprinkler drawings, and what do reviewers check?
The reviewer is the office the adopted code puts in charge of fire protection construction documents. The model 2021 International Fire Code (IFC) lets the fire code official require construction documents and calculations for every fire protection system and has them reviewed and approved before the system is installed (Section 901.2), and the International Building Code (IBC) makes construction documents part of the permit application (Section 107). Each state then names the office: a building department or code official in NYC, New York State and Pennsylvania, the fire protection subcode official inside the construction office under New Jersey’s Uniform Construction Code (UCC), a county fire protection reviewer or the State Fire Marshal in Maryland, and the State Fire Marshal or a city fire marshal in Delaware.
The reviewer checks the drawings against the NFPA standard and edition the jurisdiction enforces. As of November 2026 that is NFPA 13 (2022) in New York State and New Jersey, NFPA 13 (2016) as modified by Appendix Q of the 2022 NYC Building Code in NYC, NFPA 13 (2019) in Pennsylvania and NFPA 13 (2025) in Delaware. In Maryland, the county building permit reviews sprinklers to NFPA 13 (2019) through the 2021 IBC, while the State Fire Prevention Code (NFPA 1, 2024) references NFPA 13 (2022).
Within that standard, the review covers the hazard classification of each area, the sprinkler types and spacing, the pipe sizes and hydraulic calculations, and the water supply data the calculations rest on. Local rules add items, such as the content list for sprinkler construction documents in Section 903.1.2 of the 2022 NYC Building Code. In NYC the Fire Department of the City of New York (FDNY) also reviews sprinkler systems for hazardous and combustible material storage (NYC Administrative Code Section 28-104.1.1), while DOB reviews ordinary sprinkler work.
What are the steps from design to an approved sprinkler permit?
The order below holds in all six jurisdictions; the forms, seals and clocks change, the sequence does not. Each step feeds the next, so the design basis and flow test are settled before the drawings are final.
- Set the design basis. The designer confirms the occupancy hazard classification of every area, the standard (NFPA 13, 13R or 13D) and its edition, and what the owner will store and how high. NFPA 13 (2022) Section 4.2 has the owner state the intended use, the materials stored and the storage heights in an owner’s certificate.
- Get current water supply data. A hydrant flow test supplies the static pressure, residual pressure and flow the calculations start from. NFPA 13 requires the test to be no more than 12 months old when the working plans are submitted, unless the AHJ approves an older one, in every edition in use (Section 4.5.1.1 in 2022 and 2025, 4.6.1.1 in 2019 and 23.2.1.1 in 2016), and the Delaware State Fire Marshal asks for a test from the past 12 months on the water utility’s letterhead.
- Prepare the working plans and hydraulic calculations. NFPA 13 sets out what the working plans and calculations must show in Chapter 28 of the 2022 and 2025 editions and Chapter 27 of the 2019 edition. DGA’s guide to what a sealed sprinkler shop drawing set contains covers each sheet.
- Seal, sign and assemble the submittal. The drawings carry the seal, signature or license data the jurisdiction requires, and the package adds the application form, calculations, flow test, product data sheets and owner’s certificate. Where the sprinkler contractor drew the system, New Jersey and Pennsylvania also want the design professional’s review, as the documents table below shows.
- File with the reviewing office. The package goes to the office named in the jurisdiction table below, with the fee. In NYC a registered design professional may file for full plan examination or professionally certify the documents, which DOB accepts with less than full examination and may audit (Administrative Code 28-104.2.1).
- Answer the comments and resubmit. The reviewer approves the documents or returns written comments, such as a Notice of Objections from NYC DOB or a written denial in Pennsylvania that identifies each noncompliant element and cites the code (Title 34 of the Pennsylvania Code, 34 Pa. Code 403.43(a)). The design team revises the sheets, answers each item and resubmits.
- Receive the approved drawings and the permit. Installation starts only at this point. The 2021 IFC requires fire protection shop drawings to be approved before installation starts (Section 106.2.2), Pennsylvania puts the same rule in 34 Pa. Code 403.42a(f)(3), and NYC DOB issues no permit until it approves the required construction documents (Administrative Code 28-104.1).
Figure 1: From design basis to sign-off
Which documents go in a sprinkler submittal, and who prepares each?
Each piece of a sprinkler submittal answers a different question the reviewer has to close. The table lists the usual contents, who prepares each and what the reviewer checks; the application form and the seal rule change by jurisdiction.
| Document | Who prepares it | What the reviewer checks |
|---|---|---|
| Application form | The owner or the applicant of record, on the jurisdiction’s own form: the sprinkler (SP) work type in DOB NOW: Build in NYC, forms F100 and F140 in New Jersey, the Water Based Fire Suppression System Application in Delaware | Scope, address, system type, contractor license data and fee |
| Working plans (shop drawings) | The sprinkler contractor’s layout technician or the engineer, sealed or signed as the jurisdiction requires | Sprinkler locations, spacing, types and temperature ratings, pipe sizes, hangers and the riser, against the hazard class of each area and the NFPA 13 edition enforced |
| Hydraulic calculations | The preparer of the working plans | The design area and density, pipe sizes and lengths that match the drawings, and the water supply against the demand |
| Water supply (flow test) data | The water utility or a qualified tester, as the purveyor and reviewer allow; in NYC, also a Department of Environmental Protection statement of the minimum pressure in the main for systems on street pressure or a fire pump (2022 NYC Building Code Section 903.1.2) | The test date (no more than 12 months old unless the AHJ accepts an older test; NFPA 13 (2022) Section 4.5.1.1, and the same in 2016, 2019 and 2025), the test location, and the static pressure, residual pressure and flow |
| Owner’s certificate | The owner | The intended use, the materials stored and the storage heights the design relies on (NFPA 13 (2022) Section 4.2) |
| Product data sheets | The sprinkler contractor | That the sprinklers, valves and devices are listed for the use shown, and that pipe, fittings and hangers are listed or meet the standards NFPA 13 accepts without a listing |
| Design professional’s review | The architect or engineer of record | That contractor-prepared drawings conform to the design: a conformance letter in New Jersey (New Jersey Administrative Code, N.J.A.C. 5:23-2.15(f)) and a general conformance review of deferred submittals in Pennsylvania (34 Pa. Code 403.43(k)) |
Who may prepare and seal the drawings depends on the state. New Jersey requires the seal and signature of a registered architect or licensed engineer on each plan sheet (N.J.A.C. 5:23-2.15(f)), and New York State requires a New York licensed architect’s or professional engineer’s seal on construction documents (Title 19 of the New York Codes, Rules and Regulations, 19 NYCRR 1203.3(a); Education Law Section 7209). In NYC the registered design professional who prepared the documents is the applicant of record (Administrative Code 28-104.6), and DOB accepts shop drawings sealed by a registered design professional or stamped approved by the applicant of record.
Maryland lets a National Institute for Certification in Engineering Technologies (NICET) Level III technician of a licensed sprinkler contractor sign commercial sprinkler layouts, with a Maryland professional engineer’s seal as the alternative (Code of Maryland Regulations, COMAR 29.06.05.04L). The Delaware State Fire Marshal’s water-based application is signed by the licensed sprinkler company’s certificate holder, and the Preliminary Sprinkler Form may instead be signed by a Delaware registered professional engineer. In Pennsylvania a licensed architect or engineer prepares commercial construction documents (34 Pa. Code 403.42a(c)), and Pittsburgh also accepts suppression drawings from a NICET Level III holder.
Figure 2: Sprinkler submittal checklist
- Hazard class marked on every area; commodity and storage height where storage is present
- The standard and edition the reviewing office enforces
- Sprinkler type, K-factor and temperature rating for each sprinkler shown
- Pipe sizes, lengths and fittings that match the hydraulic calculations
- Flow test date, location, static and residual pressure, and flow
- The seal, signature or license and certificate numbers the jurisdiction requires
- Application form and fee for the reviewing office
- Hydraulic calculations with the supply and demand comparison
- Flow test report, on the water utility’s letterhead in Delaware
- Owner’s certificate (NFPA 13 (2022) Section 4.2)
- Product data sheets for sprinklers, pipe, fittings, valves and hangers
- Design professional’s conformance letter where the contractor drew the system (New Jersey)
DGA prepares sprinkler shop drawings and hydraulic calculations for plan review across New York, New Jersey, Pennsylvania, Maryland, Delaware, Washington, Oregon and Florida. Project briefs get confirmation and preliminary code feedback within one business day. See where DGA works →
How long does sprinkler plan review take, and what delays it?
Three of the six jurisdictions set a first review clock in law, as of November 2026. New Jersey’s construction official must grant or deny an application within 20 business days and act on resubmitted plans within 7 business days (N.J.A.C. 5:23-2.16(a)), and a missed deadline counts as a denial that can be appealed, not as an approval.
Pennsylvania’s code official has 30 business days to act on a commercial application, extendable by written agreement (34 Pa. Code 403.43(a)). NYC DOB has 40 calendar days after a complete application, extendable once by 20 days for good cause, and 20 calendar days to act on a resubmission (Administrative Code 28-104.2.7 and 28-104.2.9).
New York State sets no statewide clock, and an applicant whose code official does not act within a reasonable time can appeal to a regional board of review (19 NYCRR 1205.3(a)(2)). Maryland sets none statewide, and the Delaware State Fire Marshal publishes none. Agency-published targets are in DGA’s guide to how long fire protection plan review takes by state.
The clocks measure only the reviewer’s time. A clock that runs from a complete application does not start on an incomplete one, each round of comments adds a resubmission and a new decision period, and a water supply that cannot meet the demand turns the job into a fire pump or tank design with its own review. Where Pennsylvania’s Department of Labor and Industry (L&I) reviews, its published plan review requirements, as of November 2026, have deferred sprinkler plans and calculations submitted as a plan revision at least 2 weeks before installation. For a project-specific range, DGA’s fire protection project Timeline Estimator gives an engineering and plan review schedule.
Why are sprinkler submittals sent back?
Reviewers return sprinkler submittals for two kinds of problems: information the reviewer needs and cannot find, and design choices that do not meet the enforced edition or a local rule. The table pairs the common reasons with the fix that closes each one.
| Reason given | Fix |
|---|---|
| Flow test missing or too old | Order a new test, or get the AHJ’s written acceptance of the older one. NFPA 13 sets 12 months in every edition from 2016 to 2025 (Section 4.5.1.1 in 2022), and the Delaware State Fire Marshal’s form asks for a test from the past 12 months. |
| Hazard class or storage arrangement not stated | Mark the occupancy hazard class on every area, and add the owner’s certificate with the commodities and storage heights. |
| Calculations that do not match the drawings | Rerun the calculations from the pipe sizes, lengths and fittings actually drawn, with node references that match the plan. |
| Too little margin between supply and demand | NFPA 13 sets no margin, but Delaware requires 10 psi (Regulation 702, Chapter 4, Section 1.3.1.5) and Montgomery County, Maryland, 20 percent on NFPA 13 calculations; elsewhere the AHJ or the insurer may expect one. Resize the piping, or add a pump or tank. |
| Seal, signature or license data missing | Add what the jurisdiction requires on every sheet and on the calculation cover: the seal in New Jersey and New York State, the contractor’s license number and the NICET or engineer’s credentials in Maryland, the license and certificate numbers in Delaware. |
| Wrong standard or edition | Design to the edition the reviewing office enforces, for example NFPA 13 (2016) as modified by Appendix Q in NYC and NFPA 13 (2025) in Delaware. |
| Sprinkler drawings that disagree with the building drawings | Match ceiling heights, walls, room uses and storage areas to the architectural set, and attach the conformance letter or review the jurisdiction requires. |
Reading a comment letter, separating missing information from design errors and building a response that ends the review cycle are covered in DGA’s guide to why sprinkler drawings are rejected. In NYC, DOB sends its Notice of Objections to both the applicant of record and the owner.
What happens after sprinkler plans are approved?
The system has to be built as approved. Pennsylvania requires a revised set to be submitted for approval when work changes during construction (34 Pa. Code 403.43), New York State requires the permit holder to tell the code enforcement official about changes immediately (19 NYCRR 1203.3(a)), and in NYC the approved shop drawings stay on site until the job is signed off.
The piping is inspected and hydrostatically tested before walls and ceilings close, and the finished system gets an acceptance test before the building is occupied. Who witnesses differs: in NYC a special inspection agency independent of the installer witnesses the hydrostatic and flow tests and certifies them on the job’s TR1 (2022 NYC Building Code Section 1705.29), while in Delaware the State Fire Marshal witnesses the hydrostatic test before close-in and performs the acceptance test.
At acceptance the installing contractor completes the contractor’s material and test certificate, and a hydraulically designed system gets a permanent sign giving its design basis (NFPA 13 (2022) Section 29.4; Section 28.5 in the 2019 edition). New Jersey requires the sign to carry the information on Department of Community Affairs (DCA) form F380 (N.J.A.C. 5:23-3.5(d)).
The job closes with the sign-off document listed for each jurisdiction in the table below. In NYC that is the DOB Letter of Completion or certificate of occupancy after the sprinkler permit is signed off (Administrative Code 28-116.2.4.2), not an FDNY letter, as DGA’s article on whether FDNY issues a sprinkler letter of completion explains.
Where are the local sprinkler review steps for each jurisdiction?
DGA’s jurisdiction guides hold the local forms, portals and inspection steps. The table summarizes each jurisdiction as of November 2026 and links its guide.
| Jurisdiction | Reviewing office | Filing or portal | Review clock set by law | Sign-off | Local guide |
|---|---|---|---|---|---|
| New York City | DOB; FDNY for sprinkler systems protecting hazardous or combustible material storage (Administrative Code 28-104.1.1) | Sprinkler (SP) work type in DOB NOW: Build, by full plan examination or professional certification | 40 calendar days after a complete application, extendable once by 20; 20 calendar days on a resubmission (Administrative Code 28-104.2.7 and 28-104.2.9) | Sprinkler permit sign-off after the TR1 special inspection, then the DOB Letter of Completion or certificate of occupancy | Fire protection plan review at NYC DOB |
| New York State (outside NYC) | City, town or village code enforcement official, or the county or Department of State where a locality opts out; in Nassau County the County Fire Marshal’s Office also reviews | Building permit application under 19 NYCRR 1203.3(a), on the local program’s forms | None statewide; appeal to a regional board of review for failure to act within a reasonable time (19 NYCRR 1205.3(a)(2)) | Certificate of occupancy or certificate of compliance (19 NYCRR 1203.3(d)) | Fire protection approvals in New York State |
| New Jersey | Fire protection subcode official in the municipal construction office; DCA’s Bureau of Construction Project Review for Class 1 and 2 projects the local office is not classified to review (N.J.A.C. 5:23-4.24) | Construction permit application on forms F100 and F140, with sealed plans | 20 business days; 7 business days for resubmitted plans; no action counts as an appealable denial (N.J.A.C. 5:23-2.16(a)) | Certificate of approval for work in an existing building; certificate of occupancy for a new building (N.J.A.C. 5:23-2.23) | Fire protection plan review under the NJ UCC |
| Pennsylvania | Municipal building code official or its third-party agency; L&I for commercial work in opt-out municipalities and for state-owned buildings; the Department of Licenses and Inspections in Philadelphia; the Department of Permits, Licenses, and Inspections in Pittsburgh | Commercial building permit, with sprinkler shop drawings as a deferred submittal where the code official allows it (34 Pa. Code 403.43(k)); Fire Suppression Systems Permit in eCLIPSE (Philadelphia); Suppression Systems Permit in OneStopPGH (Pittsburgh) | 30 business days for a commercial application, extendable by written agreement (34 Pa. Code 403.43(a)) | UCC certificate of occupancy (34 Pa. Code 403.46); Certificate of Approval in Philadelphia | Fire protection plan review under the PA UCC |
| Maryland | The county’s fire protection reviewer, such as Montgomery County’s Department of Permitting Services, Prince George’s County through a third-party reviewer the owner hires, or the Baltimore City Fire Department; the Office of the State Fire Marshal where no local fire official reviews | County fire protection or sprinkler permit, for example through ePlans in Montgomery County and Baltimore City | None statewide | County use and occupancy permit after the fire protection inspections; the name varies by county | Fire protection plan review in Maryland |
| Delaware | Office of the State Fire Marshal, New Castle, Kent and Sussex divisions; the city fire marshal in Wilmington, Dover, Newark and the City of New Castle | Water Based Fire Suppression System Application with plans, calculations and the Preliminary Sprinkler Form | None published | State Fire Marshal acceptance test and final inspection, then the county or city certificate of occupancy | Delaware State Fire Marshal plan review |
As of November 2026. Review clocks set by statute or regulation only; agency-published review targets and local amendments are not shown.
Key Takeaway: Sprinkler plan review runs in the same order everywhere: design basis and a current flow test, working plans and hydraulic calculations, a complete submittal, comments and resubmission, then approved drawings and a permit before any pipe is installed. What changes is the reviewer, the seal or license rule, the NFPA 13 edition and the clock: as of November 2026, 20 business days in New Jersey, 30 for commercial work in Pennsylvania and 40 calendar days at NYC DOB, with no statewide clock in New York State, Maryland or Delaware.
Frequently asked questions
Who reviews sprinkler drawings in New Jersey?
The fire protection subcode official in the municipal construction office reviews them under the fire protection subcode (N.J.A.C. 5:23-3.17, with its scope set in 5:23-3.4), and the construction official issues the permit. DCA’s Bureau of Construction Project Review reviews Class 1 and Class 2 projects that the local office is not classified to review, plus the project types the bureau lists (N.J.A.C. 5:23-4.24).
Do sprinkler shop drawings need a professional engineer’s seal?
Conditional: the jurisdiction decides. New Jersey and New York State require an architect’s or engineer’s seal on the plans (N.J.A.C. 5:23-2.15(f); 19 NYCRR 1203.3(a)), while Maryland lets a licensed contractor’s NICET Level III technician sign commercial layouts, with a Maryland professional engineer’s seal as the alternative (COMAR 29.06.05.04L). The Delaware State Fire Marshal takes plans signed by the licensed sprinkler company’s certificate holder, and in NYC, DOB accepts shop drawings sealed by a registered design professional or stamped approved by the applicant of record.
How old can the flow test be in a sprinkler submittal?
12 months, unless the authority having jurisdiction approves an older test, in every NFPA 13 edition the region enforces: Section 4.5.1.1 in the 2022 and 2025 editions, 4.6.1.1 in 2019 and 23.2.1.1 in 2016. The Delaware State Fire Marshal’s Preliminary Sprinkler Form also asks for a test from the past 12 months on the water utility’s letterhead.
Can sprinkler installation start before the drawings are approved?
No. The 2021 International Fire Code requires fire protection shop drawings to be approved before installation starts (Section 106.2.2), Pennsylvania’s rule is the same (34 Pa. Code 403.42a(f)(3) and 403.43(k)), and NYC DOB issues no permit until it approves the required construction documents (Administrative Code 28-104.1). Pipe installed before approval has to be changed if the reviewer changes the design.
Does the fire marshal review sprinkler plans separately from the building department?
Conditional: it depends on the jurisdiction. In Delaware the State Fire Marshal or a city fire marshal reviews a separate sprinkler submittal, Maryland plans go to a county fire protection reviewer or the Office of the State Fire Marshal, and in Nassau County, New York, the County Fire Marshal’s Office reviews them alongside the local building department. In New Jersey the fire protection subcode official reviews them inside the construction office, and in NYC and Pennsylvania the building department or code official does, with FDNY reviewing NYC systems for hazardous and combustible material storage.
More in Sprinkler Systems
- What Is NFPA 13? A Plain-English Guide for Owners
- When Does a Sprinkler System Need Seismic Bracing?
- How Do You Size a Water Supply for a 13R or 13D System?
- Do Balconies and Decks Need Sprinklers Under NFPA 13R?
- When Does a Stage or Exhibit Hall Need Special Sprinklers?
- Do Closets, Bathrooms and Small Rooms Need Sprinklers?
This article is general information, not a code determination for any project. Code editions, local amendments and reviewer practice change; confirm the adopted code, the NFPA 13 edition and the reviewing office for the project.
Taking Sprinkler Drawings Through Plan Review?
Send the address, the building use, the scope of the sprinkler work and any flow test on file. DGA prepares the sprinkler shop drawings and hydraulic calculations, assembles the submittal for the reviewing office and answers the review comments. Project briefs get confirmation and preliminary code feedback within one business day.