General guidance, not a code determination for any project. Confirm the adopted code and local amendments with the authority having jurisdiction.

Under NFPA 13 (2022), the sprinkler installation standard of the National Fire Protection Association (NFPA), a concealed space or attic needs sprinklers when exposed combustible construction such as wood joists, trusses or roof framing forms or encloses it, unless the space meets one of the omission conditions in the standard’s Chapter 9. A space built of noncombustible materials needs them only when it holds storage or more than minor combustibles. In buildings on NFPA 13R, the standard for low-rise residential buildings, attics and concealed spaces not used for living or storage and without fuel-fired equipment can go without sprinklers, but Section 903.3.1.2.3 of the International Building Code (IBC) adds attic protection in four cases, starting with attics used for living or storage and attics that hold fuel-fired equipment.

The question comes up on wood-frame apartment buildings, on renovations of older buildings with wood roofs and on tenant fit-outs under suspended ceilings. The answer turns on four facts about each space: what it is built of, how deep and how divided it is, whether insulation fills it, and what it is used for. Balconies, decks, closets and bathrooms follow separate omission rules not covered here.

At a Glance: Sprinklers in Concealed Spaces and Attics

  • Threshold(s) with units: under NFPA 13 (2022), any concealed space formed or enclosed by exposed combustible construction, unless it meets a Chapter 9 omission condition such as a ceiling within 6 inches of solid wood joists, composite joist channels of 160 cu ft or less, or a full fill of noncombustible insulation. In buildings on NFPA 13R, attics used or intended for living or storage, attics with fuel-fired equipment, attics of Type III, IV or V podium buildings whose roof is more than 55 ft above fire department vehicle access (2018 and 2021 IBC text), and Group R-4 Condition 2 attics.
  • Code, edition, section: NFPA 13 (2022) Chapter 9 (concealed spaces) and Chapter 19 (design area) in New York State and New Jersey, with the same subjects covered by the 2019 edition in Pennsylvania and Maryland county permits, the 2025 edition in Delaware and the 2016 edition with Appendix Q in New York City; NFPA 13R; IBC Section 903.3.1.2.3 (2018, 2021 and 2024 editions); IBC Sections 708.4.2 (708.4.3 in 2024) and 718; New York City Building Code Appendix Q, sections Q103 and Q104.
  • Main exceptions: noncombustible or limited-combustible spaces with only minor combustibles and no storage; shallow joist spaces, small joist channels, insulation-filled spaces and fire-retardant-treated wood surfaces; under NFPA 13R, attics and concealed spaces not used for living or storage and without fuel-fired equipment; for the podium item, noncombustible construction, fire-retardant-treated wood or noncombustible insulation in place of sprinklers.
  • What applies once triggered: sprinklers suited to the space, such as sprinklers listed for attics, with a dry pipe system or other freeze protection where the attic is unheated; a 30 percent larger design area for dry pipe systems; a minimum design area that can rise to 3,000 sq ft beside combustible concealed spaces left unsprinklered; fireblocking in all combustible construction, and draftstopping unless the building is sprinklered throughout to NFPA 13 or its NFPA 13R sprinklers protect the space.
  • Permit or filing: the sprinkler shop drawings, which show every concealed space and the code basis for each omission; in Delaware, the Preliminary Sprinkler Form lists combustible concealed spaces and unsprinklered areas; attic construction options belong on the architectural drawings.
  • Who decides: the authority having jurisdiction (AHJ) for sprinkler plans: the Department of Buildings in New York City, the fire protection subcode official in New Jersey (with the building subcode for attic construction options), the State Fire Marshal in Delaware, and the local or county code official elsewhere. The AHJ judges whether an attic is used or intended for living or storage.

When does NFPA 13 require sprinklers in a concealed space?

NFPA 13 treats a concealed space, such as the void above a ceiling, the cavity inside a floor-ceiling assembly, an attic, a soffit or a chase, as part of the building it protects. Under NFPA 13 (2022) Chapter 9, a concealed space formed wholly or partly by exposed combustible construction needs sprinklers unless it meets one of the conditions the chapter lists. The reason is fire growth: a fire that starts or spreads in an unsprinklered combustible cavity grows above the sprinklers below the ceiling, where they cannot reach it.

A concealed space built of noncombustible or limited-combustible materials, such as a steel deck on steel joists above a suspended ceiling, needs no sprinklers when it holds only minor combustibles and is not used for storage. Storage in a noncombustible concealed space brings the sprinklers back.

Every edition in force across the region has these rules, numbered differently and with some differences in detail: NFPA 13 (2016) as modified by Appendix Q of the 2022 New York City Building Code in New York City, the 2019 edition in Pennsylvania and the Maryland county permits, the 2022 edition in New York State and New Jersey, and the 2025 edition in Delaware. Whether a building needs a sprinkler system at all is answered in DGA’s guide to when a building needs fire sprinklers. The table shows when NFPA 13 requires sprinklers in a concealed space.

Concealed space or attic conditionSprinklers required?NFPA 13 (2022)
Formed or partly enclosed by exposed combustible construction (wood joists, trusses, rafters or decking)Yes, unless a condition below appliesChapter 9
Noncombustible or limited-combustible construction with only minor combustibles, such as some cabling, and no storageNoChapter 9
Ceiling attached directly to, or within 6 inches of, the bottom of solid wood joistsNoChapter 9
Ceiling attached to composite wood joists (I-joists), with the joist channels blocked into volumes of 160 cu ft or lessNo, where the attachment and blocking conditions are metChapter 9
Space filled completely with noncombustible insulation, with a gap of up to 2 inches at the topNoChapter 9
Wood or composite joist space with noncombustible insulation filling it from the ceiling up to the bottom of the joistsNo; composite joist channels must also stay at 160 cu ft or lessChapter 9
Exposed surfaces made entirely of fire-retardant-treated wood, or of rigid materials with a flame spread index of 25 or less that also pass an extended tunnel testNoChapter 9
Space below insulation laid directly on or between the ceiling joists of an otherwise sprinklered atticNoChapter 9
Noncombustible concealed space used for storageYesChapter 9
Combustible concealed space left unsprinklered under one of the conditions aboveThe minimum design area beside it can rise to 3,000 sq ft, depending on the condition usedChapter 19

Paraphrased by DGA from NFPA 13 (2022), not NFPA text; each condition carries further limits in the standard. New York City (2016 edition with Appendix Q), Pennsylvania and the Maryland county permits (2019) and Delaware (2025) number these provisions differently.

Which concealed spaces can NFPA 13 leave unsprinklered, and on what conditions?

The omission conditions in NFPA 13 (2022) Chapter 9 fall into three groups. Construction: noncombustible or limited-combustible spaces with minor combustible loading. Geometry: a ceiling attached directly to, or within 6 inches of, solid wood joists, or composite wood joist channels blocked into volumes of 160 cu ft or less. Insulation and surfaces: a complete fill of noncombustible insulation, noncombustible insulation from the ceiling up to the bottom of wood or composite joists, or exposed surfaces of fire-retardant-treated wood or tested low flame spread materials.

An omission can carry a cost elsewhere in the design. Where a combustible concealed space is left without sprinklers, NFPA 13 (2022) Chapter 19 can raise the minimum design area beside it to 3,000 sq ft, depending on which omission condition the space relies on. A larger design area puts more sprinklers into the hydraulic calculation and raises the water demand the supply has to meet.

Construction type often settles the question above suspended ceilings. IBC Section 718.5 bars most combustible materials from the concealed spaces of Type I and Type II construction, so the space above a suspended ceiling in those buildings usually qualifies as noncombustible, provided cables, plastic piping and other combustibles stay minor and nothing is stored there. In Type III and Type V buildings, wood floor and roof framing makes most concealed spaces combustible, and each one needs sprinklers or a documented omission condition.

How do NFPA 13R and the IBC treat attics in residential buildings?

NFPA 13R is written for life safety in low-rise residential buildings, so it puts sprinklers where people live and sleep and lets designers leave them out of attics, crawl spaces, floor-ceiling spaces and other concealed spaces that are not used or intended for living or storage and hold no fuel-fired equipment (Section 6.6.6 of the 2022 edition). The IBC decides when a building may use NFPA 13R at all, a choice DGA’s comparison of NFPA 13, 13R and 13D walks through. Where NFPA 13R is used, IBC Section 903.3.1.2.3 adds attic protection in four cases.

Attic in a building on NFPA 13RProtection the IBC requiresIBC Section 903.3.1.2.3
Used or intended for living purposes or storageAutomatic sprinkler protectionItem 1
Fuel-fired equipment in an otherwise unsprinklered atticAt least one quick-response, intermediate-temperature sprinkler above the equipmentItem 2
Type III, IV or V building designed under the podium provisions (Section 510.2 or 510.4), with the roof assembly more than 55 ft above the lowest required fire department vehicle accessOne of four: sprinklers, noncombustible construction, fire-retardant-treated wood complying with Section 2303.2, or an attic filled with noncombustible insulationItems 3.1 to 3.4
Group R-4 Condition 2 (residential care where some residents need limited help to evacuate), attic not covered by item 1One of five: sprinklers, heat detection throughout the attic that activates the building fire alarm, noncombustible construction, fire-retardant-treated wood or noncombustible insulationItems 4.1 to 4.5
Any other attic not used for living or storageNothing more from Section 903.3.1.2.3; the NFPA 13R attic omission applies, and the draftstopping rules still applyNot listed

Item text as printed in the 2018 and 2021 IBC, which match. New Jersey’s subcode responsibility table for the 2024 IBC lists the same item numbers. The New York City Building Code has no attic subsection under Section 903.3.1.2.

New York City handles attics through the standards instead. Section 903.3.1.2 of the 2022 New York City Building Code allows NFPA 13R in Group R buildings up to six stories and has no attic subsection, while Appendix Q adds the words “without floors” after “attics” in the attic provisions of NFPA 13R and NFPA 13D (2016), in sections Q104 and Q103. An attic with a floor in a New York City building on NFPA 13R or 13D therefore falls outside the standards’ attic allowance.

NFPA 13D, used in one- and two-family dwellings and townhouses under the residential code, also leaves out attics, with or without storage, crawl spaces and other concealed spaces not used for living (Section 8.3.5 of the 2022 edition). Apartment buildings use NFPA 13R or NFPA 13 instead, and DGA’s guide to the fire protection a multifamily building needs covers the other systems those buildings require.

How is a concealed space or attic judged: Depth, combustibility, insulation and use?

Each omission condition rests on a measurement or a material fact that the drawings have to show. Depth is measured from the ceiling to the underside of the joists above it, so a suspended ceiling hung more than 6 inches below solid wood joists creates a combustible concealed space that needs sprinklers unless another condition applies. Joist channel volume is the length, width and depth of each blocked bay, which in composite wood joist construction must stay at or below 160 cu ft.

Combustibility covers everything exposed inside the space, not only the framing: sheathing, insulation facings, cables and plastic piping all count. Insulation supports an omission only when it is noncombustible as installed and fills the space as the condition requires, so foam plastic insulation, or a partial fill that leaves a larger gap than the standard allows, does not qualify. The product data and the installation details belong on the architectural drawings, because the sprinkler contractor does not install them.

Use is the judgment call. Whether an attic is used or intended for living or storage is decided by the AHJ from the drawings and the construction: flooring, a fixed stair and a finished access opening all point toward storage.

For IBC item 3, the roof height runs from the lowest required fire vehicle access road surface beside the building to the eave of the highest pitched roof, the line where the highest roof meets the exterior wall or the top of the highest parapet, whichever is highest, counting only roads needed under Section 503 of the International Fire Code (IFC). Under the 2021 IBC, which keeps the highest floor of a 13R building within 30 ft of fire department vehicle access, a roof seldom reaches 55 ft; the 2018 IBC, still used in Kent County and Wilmington, Delaware, allowed 13R up to 60 ft above grade plane with podium stories counted from the podium. In Pennsylvania, whose amended Section 903.3.1.2 keeps Group R-2 buildings on 13R below a 45 ft roof assembly measured the same way, item 3 cannot reach an R-2 building.

Figure 1: Does the concealed space need sprinklers?

A concealed space or attic in a building sprinklered to NFPA 13
Is it formed or enclosed by exposed combustible construction?
No: noncombustible or limited-combustible
Storage, or more than minor combustiblesSprinklers requiredProtect it like an occupied area
Minor combustibles, no storageMay be omittedNFPA 13 Chapter 9
Yes: wood joists, trusses, rafters or decking
Ceiling within 6 inches of solid joists, or channels of 160 cu ft or lessMay be omittedCheck the 3,000 sq ft design area rule
Full noncombustible insulation fill, or fire-retardant-treated woodMay be omittedFireblocking still applies
None of theseSprinklers requiredDry pipe or other freeze protection if unheated
Under NFPA 13 (2022) Chapter 9, a concealed space enclosed by exposed combustible construction is sprinklered unless a listed condition applies, such as a ceiling within 6 inches of solid wood joists, composite joist channels of 160 cu ft or less, a full fill of noncombustible insulation or fire-retardant-treated wood surfaces; a noncombustible space needs sprinklers when it holds storage or more than minor combustibles. An unsprinklered combustible concealed space can raise the minimum design area beside it to 3,000 sq ft under Chapter 19.

What applies once a concealed space or attic must be sprinklered?

A sprinklered attic or combustible concealed space is designed like any other area of the system, with conditions of its own. Pitched attics take standard sprinklers placed under NFPA 13’s rules for sloped ceilings, or sprinklers listed specifically for attics and used within their listing. Trusses, ducts and equipment in an attic block the spray the same way beams and ducts do below a ceiling, so the rules in DGA’s guide to why sprinkler obstructions fail inspection apply to the attic layout.

Most attics are unheated, and NFPA 13 (2022) Section 16.4.1.1 requires wet pipe systems to be kept at 40°F or above. An unheated attic therefore usually gets a dry pipe system or another freeze protection method the standard allows, and a dry pipe system enlarges the design area by 30 percent (Section 19.2.3.2.5). That larger area, in a space far from the riser, can make the attic the hydraulically most demanding area of the building.

The shop drawings have to show every concealed space and the basis for leaving any of them unsprinklered. Delaware’s State Fire Marshal asks on its Preliminary Sprinkler Form whether the building has combustible concealed spaces, which must appear on the plans, and which areas are not sprinklered and why. Prince George’s County, Maryland goes further in the county code amendments it filed with the Maryland Department of Labor: reviewers assume full coverage, including attics and combustible concealed spaces, unless the shop drawings cite the code section that allows each omission (County Code Subtitle 4, Section 4-157).

Opens the Project Desk with your sentence. Our licensed PEs review every brief and reply within one business day.

What do draftstopping and fireblocking have to do when sprinklers are omitted?

Fireblocking and draftstopping are the IBC’s passive answer to fire spread in concealed spaces, and they matter most where sprinklers are left out. Fireblocking closes concealed vertical and horizontal openings in combustible construction: at the floor and ceiling levels of stud walls, at 10 ft intervals within them, and where wall cavities meet soffits, drop ceilings and floor or roof framing (IBC Section 718.2). Section 718.2 has no sprinkler exception, so fireblocking goes in whether or not the space is sprinklered.

Draftstopping subdivides combustible floor-ceiling and attic spaces. Outside Group R, Section 718 requires draftstops that divide combustible floor-ceiling spaces into areas of no more than 1,000 sq ft and combustible attics into areas of no more than 3,000 sq ft, and waives both in buildings sprinklered throughout to NFPA 13. In Group R buildings the IBC ties draftstopping to the dwelling unit and sleeping unit separations: where those fire partitions stop at the ceiling, the space above them gets fireblocking or draftstopping up to the floor or roof sheathing (Section 708.4.2 in the 2021 IBC, 708.4.3 in the 2024 IBC).

A building on NFPA 13R keeps those draftstops unless sprinklers protect the space above the fire partitions the way an NFPA 13 system would; a building on NFPA 13 throughout does not need them. Group R-2 buildings of up to four stories and 60 ft may instead divide the attic with draftstops into areas of 3,000 sq ft or less, or above every two dwelling units, whichever is smaller. Group R-2 buildings with fewer than four dwelling units need neither fireblocking nor draftstopping above the partitions.

Figure 2: Attic and floor-ceiling spaces in a four-story 13R building

Draftstop Fire access road surface Dwelling unit Dwelling unit Fuel-fired equipment: at least 1 quick-response, intermediate- temperature sprinkler (item 2) ATTIC No sprinklers under 13R unless used for living or storage (item 1) FLOOR-CEILING SPACE 13R may leave it unsprinklered UNIT SEPARATION WALL Stops at ceiling: fireblock or draftstop above (IBC 708.4.2) Roof height, road surface to eave Item 3 applies over 55 ft on a podium Group R-2, four stories, NFPA 13R, 2021 IBC. Red lines: fireblocking or draftstops. Attic draftstops may instead fall every 3,000 sq ft or every two units, whichever is smaller.
In a four-story Group R-2 building on NFPA 13R under the 2021 IBC, an attic not used for living or storage and the floor-ceiling spaces can stay unsprinklered, but fuel-fired equipment in the attic needs at least one quick-response, intermediate-temperature sprinkler above it (Section 903.3.1.2.3), and unit separation walls that stop at the ceiling need fireblocking or draftstopping above them (Section 708.4.2). In the attic, draftstops may instead divide the space into areas of 3,000 sq ft or less, or above every two dwelling units, whichever is smaller.

New Jersey adds two points. Its amended Section 903.1.2 gives NFPA 13R and 13D systems no code reduction unless the code names them, and the draftstopping exception names NFPA 13R systems by section, so the exception remains available there. New Jersey’s subcode responsibility table also sends the attic construction options in Section 903.3.1.2.3 (items 3.2 to 3.4 and 4.3 to 4.5) to joint building and fire plan review and to the building inspector.

How do New York, New Jersey, Pennsylvania, Maryland and Delaware apply the attic rules?

The NFPA 13 rules apply everywhere in the edition each jurisdiction adopts. The IBC attic and draftstopping rules follow the local IBC edition, as of November 2026.

JurisdictionCode pathLocal rule worth knowingReviewer and filing
New York State (outside New York City)2025 Building Code of New York State (BCNYS), based on the 2024 IBC, in effect since December 31, 2025; NFPA 13 (2022) and NFPA 13R in the edition the BCNYS referencesThe 2025 rule text (Title 19 of the New York Codes, Rules and Regulations (NYCRR), Part 1221) makes no Chapter 9 amendment, so the NFPA 13R attic provisions follow the 2024 IBCLocal code enforcement official; building permit with construction documents sealed by a New York licensed architect or engineer (19 NYCRR 1203.3(a))
New York City2022 New York City Building Code; NFPA 13, 13R and 13D (2016) as modified by Appendix Q; NFPA 13R allowed in Group R buildings up to six stories (Section 903.3.1.2)No attic subsection under Section 903.3.1.2; Appendix Q adds “without floors” after “attics” in the NFPA 13R and 13D attic provisions (Q104, Q103)Department of Buildings (DOB); sprinkler (SP) work type in DOB NOW: Build
New JerseyUniform Construction Code (UCC) on the 2024 IBC since August 17, 2026, with complete applications under the 2021-based codes accepted through February 17, 2027; NFPA 13 (2022)No New Jersey amendment to Section 903.3.1.2 or its subsections; amended Section 903.1.2 grants NFPA 13R and 13D systems no code reduction unless the code names themFire protection subcode official; the attic construction options are reviewed with the building subcode and inspected by it (New Jersey Administrative Code (N.J.A.C.) 5:23-3.4(a)); construction permit with the fire protection technical section
PennsylvaniaPennsylvania Uniform Construction Code on the 2021 IBC since January 1, 2026; NFPA 13 and 13R (2019)Section 903.3.1.2.3 as published; Pennsylvania’s only statewide Chapter 9 change, to Section 903.3.1.2, holds Group R-2 buildings on NFPA 13R to a roof assembly under 45 ftMunicipal building code official, third-party agency or the state Department of Labor and Industry; in Philadelphia, the Department of Licenses and Inspections Fire Suppression Systems Permit; in Pittsburgh, the Department of Permits, Licenses, and Inspections Suppression Systems Permit
Maryland2021 IBC through the Maryland Building Performance Standards (Code of Maryland Regulations (COMAR) 09.12.51) and the county permit; NFPA 13 and 13R (2019); NFPA 1 (2024) references the 2022 editionsNo state amendment to IBC Section 903; Prince George’s County’s filed amendments (Section 4-157) assume full coverage, including attics and combustible concealed spaces, unless the shop drawings cite the omissionCounty reviewer, such as the Montgomery County Department of Permitting Services or the Prince George’s County Department of Permitting, Inspections and Enforcement; the Office of the State Fire Marshal where the county does not review; county fire protection system permit
DelawareIBC by local adoption: 2021 in New Castle County and Sussex County, 2018 in Kent County and Wilmington, 2024 in the City of New Castle; the State Fire Marshal reviews to NFPA 13 and 13R (2025) under Regulation 701The Preliminary Sprinkler Form asks whether the building has combustible concealed spaces, shown on the plans, and which areas are not sprinklered and whyOffice of the State Fire Marshal, or the city fire marshal in Dover, Newark, the City of New Castle and Wilmington; water-based fire suppression system application with the Preliminary Sprinkler Form

As of November 2026. Other local amendments are not shown.

In Maryland, the county building permit reviews sprinklers to NFPA 13 (2019) through the 2021 IBC, while the State Fire Prevention Code (NFPA 1, 2024) references NFPA 13 (2022). The same split applies to NFPA 13R.

Key Takeaway: Under NFPA 13 (2022), combustible concealed spaces and attics get sprinklers unless a Chapter 9 condition takes them out, and an omission can enlarge the design area. Under NFPA 13R, attics and concealed spaces not used for living or storage can stay unsprinklered, but IBC Section 903.3.1.2.3 adds protection for attics in use, fuel-fired equipment, tall podium buildings and Group R-4 Condition 2. Fireblocking applies in combustible construction either way, and draftstops stay wherever a 13R building leaves the space above its unit separations unsprinklered. Settle every omission on the architectural drawings before the sprinkler layout starts.

Frequently asked questions

Do combustible concealed spaces need sprinklers?

Yes, under NFPA 13 (2022), unless the space meets one of the omission conditions in Chapter 9, such as a ceiling attached within 6 inches of solid wood joists, composite joist channels blocked into volumes of 160 cu ft or less, a complete fill of noncombustible insulation, or exposed surfaces made entirely of fire-retardant-treated wood. Leaving a combustible concealed space unsprinklered can raise the minimum design area beside it to 3,000 sq ft.

Does a 13R building need attic sprinklers?

Conditional: NFPA 13R lets an attic that is not used for living or storage and holds no fuel-fired equipment go without sprinklers, but IBC Section 903.3.1.2.3 requires sprinklers in an attic used or intended for living or storage, at least one quick-response, intermediate-temperature sprinkler above fuel-fired equipment in an unsprinklered attic, and attic protection in Type III, IV or V podium buildings whose roof is more than 55 ft above fire department vehicle access (2018 and 2021 IBC). In New York City, Appendix Q narrows the NFPA 13R attic provision to attics without floors.

Can insulation fill avoid sprinklers in a concealed space?

Conditional: yes, when noncombustible insulation fills the space completely, leaving no more than a 2-inch gap at the top, or, in wood and composite joist construction, fills it from the ceiling up to the bottom of the joists, with composite joist channels also blocked into volumes of 160 cu ft or less. Combustible insulation such as foam plastic does not qualify, and the IBC fireblocking rules still apply to the framing.

Are sprinklers required above a drop ceiling?

Conditional: not when the space above is noncombustible or limited-combustible construction with only minor combustibles and no storage, which is the usual case in Type I and II buildings because IBC Section 718.5 keeps most combustible materials out of their concealed spaces. Above a drop ceiling hung more than 6 inches below wood joists, sprinklers are required unless the space meets another NFPA 13 omission condition, such as a full fill of noncombustible insulation.

Does an attic with a furnace need a sprinkler?

Conditional: in a building on NFPA 13R, IBC Section 903.3.1.2.3 requires at least one quick-response, intermediate-temperature sprinkler above fuel-fired equipment installed in an otherwise unsprinklered attic. In a building on NFPA 13, a combustible attic is sprinklered throughout unless it meets one of the standard’s omission conditions.

This article is general information, not a substitute for a project-specific code analysis. Confirm the adopted code editions, local amendments and the authority having jurisdiction’s position on each omission before the design is fixed.

Deciding Which Attics and Ceiling Spaces Get Sprinklers?

Send the architectural sections, the roof and floor framing and the intended use of each attic. DGA checks which spaces NFPA 13 or 13R and the IBC allow the design to leave unsprinklered, documents the basis on the shop drawings and lays out sprinklers for the rest. Project briefs get confirmation and preliminary code feedback within one business day.

Send a project brief → View related services

Leave a reply

Your email address will not be published. Required fields are marked *

Quick inquiry

Ready when you are.

Your name, a way to reach you, and where the project is. A licensed PE replies within one business day. Every inquiry is confidential.

Prefer to describe it first? Open the Project Desk

FirmDGA Fire Protection Engineering
SheetFP-5209
OfficesNew York · Harrisburg · Seattle
LicensedNY NJ PA MD DE WA OR FL
Rev11.2026
Sheet index